120 Wis. 177 | Wis. | 1904
“If you find tbat tbe defendant, Laev, required plans and specifications for certain buildings, to cost about tbe sum of' $6,000, there can be no recovery by tbe plaintiff, Graf, unless tbe said buildings could have been erected for about tbe sum named.”
The parties differed widely as to tbe terms of tbe contract. Tbe instruction so requested is to tbe effect tbat, if tbe jury
“If you find for the plaintiff- — that is to say, if you find that the contract was entered into between the parties as contended for by the plaintiff — then you will take up the con■sideration of the damages recoverable in this action; and I instruct you, as a matter of law, that, if you find for the plaintiff, the damages recoverable by the plaintiff in this action are the sum of $305.04.”
The amount so stated was the full amount of the contract price, as claimed by the plaintiff. True, the terms of the contract were in dispute, and accordingly the amount of the plaintiff’s compensation was in dispute. But it will be ob-served that under the charge of the court, as given, the jury were precluded from finding any damages in favor of the plaintiff unless they first found that the contract between the parties was “as contended for by the plaintiff.” The jury having found that the contract was as claimed by the plaintiff, 'the question presented is whether in assessing damages there should have been an abatement from tho full contract price. There is no question but that the plaintiff performed most of the services under the contract, as he claimed it to be, and was ready at all times to perform the balance. Prior to the
“In the absence, therefore, of any evidence that the party might have obtained any other employment, the law can adopt no other rule of damages than the contract price, unless there is some legal presumption that such other employment might be obtained.” Danley v. Williams, 16 Wis. 581, 586. See, also, Hildebrand v. American F. A. Co. 109 Wis. 171, 181, 85 N. W. 268.
In the case at bar the defendant failed to prove that the' plaintiff might have obtained such employment elsewhere, or-any fact in mitigation of the plaintiff’s damages. The case is unlike Nilson v. Morse, 52 Wis. 241, 9 N. W. 1, and other cases cited by counsel, where the performance of the specific work contracted for could be delegated to others. We find no error in charging the jury on the measure of damages.
We find no error in the record.
By the Court. — The judgment of the circuit court is affirmed. •