OPINION
This is a post-award bid protest brought by Government Technical Services (GTS), a successful offeror for United States Army Corps of Engineers (Corps, government or defendant) Contract W 912DY-05-D-0020 (Contract).
I. Background
On January 4, 2005 the Corps awarded the Contract to Government Technical Services (GTS). Def.’s Mot. 3. Upon winning the Contract, GTS became eligible to compete against other pre-qualified contractors for task orders to provide Electronic Security Systems procurement and installation services (ESS Services) and delivery оf security and force protection measures to the Electronic Technology Systems Center, Engineering and Support Center in Huntsville, Alabama. Def.’s Mot. 3. The Contract was a multiple award contract with multiple options. Compl. ¶ 4.
Plaintiffs Complaint characterizes the government’s failure to exercise an option to extend the Contract after the expiration of the initial term of the Contract as an action taken “in connection with a procurement”
(a) The Government may extend the term of this contract by written notice to the Contractor within 30 days of the current contract year; provided that the Government gives the Contractor a preliminary notice of its intent to extend at least 60 days before the contract expires. The preliminary notice does not commit the Government to an extension.
(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.
(c) The total duration of this contract, including the exercisе of any options under this clause, shall not exceed 5 years.
AR 50. It is undisputed that the extension option was not exercised by the Corps as to plaintiffs Contract. The Contract expired on January 3, 2009. See Compl. ¶ 22.
Under the Contract, the Corps awarded five task orders to GTS between February 5, 2007 and the expiration of the contract, January 3, 2009. See id,.; Def.’s Mot. 4-13. A dispute exists between the parties regarding whether or not the task orders were completed successfully. See Compl. ¶¶ 4, 7-14; Def.’s Mot. 4-11. Plaintiff alleges that GTS was treated unfairly by the Corps Contracting Officer Representative (COR) during the рerformance of Task Order 4 which culminated with the government’s bad faith decision not to exercise the renewal option. See Compl. ¶¶ 8-14, 36-37. Plaintiff alleges that the COR’s “unreasonable and arbitrary position regarding performance” contributed to delays in the completion of Task Order 4. Compl. ¶ 9. Plaintiff also asserts that the COR was rarely available for consultation because of his many scheduling conflicts, further delaying the progress of Task Order 4. Compl. ¶¶ 10-11. Plaintiff maintains that meetings regarding the progress of Task Order 4 between GTS and the Corps were marred by the COR’s untrue “allegations of poor performance [by GTS]” to the Contracting Officer (CO) and other Corps officials. Compl. ¶ 16. GTS contends that, as a result of the bad faith misrepresentations by the COR, it was excluded from competition for task orders, with the result that its contract terminated instead of being extended under the Contract’s option provision. Compl. ¶¶ 36-37. It is on this claim of bad faith in the management of task orders that plaintiff bases its Administrative Dispute Resolution Act (ADRA) claim under 28 U.S.C. § 1491(b). See Compl. ¶ 3.
The Complaint, filed by GTS on September 28, 2009, asserts that it is a bid protest pursuant to the Tucker Act, 28 U.S.C. § 1491, and, in particular, that the option provision of the Contract is within the ADRA jurisdiction of this court. Compl. ¶ 3; Pl.’s Resp. 2. Section 12 of the ADRA added jurisdiction over post-award bid protests to the Tucker Act. Pub.L. No. 104-320 (1996), 110 Stat. 3870, 3874-76 (1996); 28 U.S.C. § 1491(b)(1). Plaintiffs argument relies in principal part on language in a case before the United States Court of Appeals for the Federal Circuit (Federal Circuit), Distributed Solutions, Inc. v. United States (Distributed Solutions),
Defendant’s Motion to Dismiss argues that plaintiff has failed to state a claim within the jurisdiction of the court pursuant to the
II. Discussion
A.Tucker Act Jurisdiction
The United States “is immune from suit save as it consents to be sued.” United States v. Sherwood,
The Unite[d] States Court of Federal Claims ... shall have jurisdiction to render judgment on an action by an interested party objecting to a solicitation by a Federal agency for bids or proposals for a proposed contract or to a proposed award or the awаrd of a contract or any alleged violation of statute or regulation in connection with a procurement or a proposed procurement.
See 28 U.S.C. § 1491(b)(1). The relief available under the Tucker Act is “any ... that the court considers proper, including declaratory and injunctive relief except that any monetary relief shall be limited to bid preparation and proposal costs.” Id. § 1491(b)(2). The issue before the court is whether its bid protest jurisdiction encompasses the Corps’ decision not to exercise its option to extend the Contract with GTS.
B. Legal Standard for Motion to Dismiss under RCFC 12(b)(1)
When considering a motion under RCFC 12(b)(1) to dismiss for lack of subject matter jurisdiction, the court is generally “ ‘obligated to assume all factual allegations to be true and to draw all reasonable inferences in plaintiffs favor.’” FFTF Restoration Co. v. United States (FFTF Restoration),
In evaluating a motion under 12(b)(1), the court “ ‘may find it necessary to inquire into jurisdictional facts that are disputed.’ ” FFTF Restoration,
C. No Jurisdiction of GTS’s Claim as a Bid Protest Action
1. Tucker Act Jurisdiction
The Court of Federal Claims has jurisdiction to adjudicate bid protest claims pursuant to the Tucker Act, 28 U.S.C. § 1491(b)(1):
[The Court of Federal Claims has] jurisdiction to render judgment on an action by an interested party objecting to a solicitation by a Federal agency for bids or proposals for a proposed contract or to a proposed award or the award оf a contract*526 or any alleged violation of statute or regulation in connection with a procurement or a proposed procurement[;] ... without regard to whether suit is instituted before or after the contract is awarded.
28 U.S.C. § 1491(b)(1).
GTS brought this claim as a bid protest in order to challenge the Corps’ decision not to exercise an option to extend its indefinite delivery, indefinite quantity, multiple award task order contract (IDIQ MATOC). See Compl. ¶¶ 4,34, 38,40. GTS argues that it is a disappointed bidder and that this case is properly within the jurisdiction of the Court of Federal Claims beсause the failure to exercise an option to extend a contract fits squarely within the terms of the ADRA. See Compl. ¶¶4, 34. In particular, plaintiff argues that the determination not to extend a contract is within the broad definition of procurement adopted by the Federal Circuit. Pl.’s Resp. 2 (quoting Distributed Solutions,
2. The Government’s Failure to Exercise an Option is Governed by the CDA аnd is Not a Bid Protest Action
Defendant argues that the claim is improperly before the court because the claim is not a bid protest but a dispute over the exercise of an option on an existing contract which requires that it be brought under the Contract Disputes Act (CDA), 41 U.S.C. §§ 601-613 (2006). Def.’s Mot. 15-16. The government points out that defendant has not complied with the CDA requirement that an aggrieved contractor file a written claim with the CO, who must then issue an unfavorable final decision, before a contractor may file a claim with the court. See U.S.C. § 605(a); Def.’s Mot. 16-17 (describing the administrative exhaustion requirements of the CDA). A claim substantially similar to GTS’s claim against the government here was brought by the plaintiff in Continental Collection & Disposal, Inc. v. United States (Continental),
The Continental court dismissed a claim brought by Continental under 28 U.S.C. § 1491(b)(1) because Continental had failed to pursue administrative remedies under the CDA before filing its claim with the court. Id. at 648.
In its Response, plaintiff adds to the bad faith argument articulated in its Complaint an acknowledgment of the existence of the CDA; however, plaintiff argues that it is not obligated to meet the requirements of the CDA because its claim finds independent jurisdiction in the Tucker Act as amended by the ADRA. See Pl.’s Resp. 5 (citing FFTF Restoration,
Plaintiff appears to have misunderstood the government’s argument. Defendant does not suggest that the case should be resolved on its merits during the adjudication of the motion to dismiss. To the contrary, defendant argues that the claim, involving as it does an allegation of bad faith concerning an existing contract, must be decided under the CDA. Def.’s Reply 2-3; see Steel Co. v. Citizens for a Better Env’t,
Plaintiff argues that it is entitled to choose between the CDA and the ADRA as a jurisdictional basis for an action based on the government’s failure to exercise an option on an existing contract. Pl.’s Resp. 3 (“GTS’s claim does not have to satisfy the CDA, when it can independently find jurisdiction in the Tucker Act based upon an alleged violation in connection with a procurement or a proposed procurement.”). The court disagreеs. While the Federal Circuit set forth an expansive definition of the term “bid protest” in Distributed Solutions, that court also recognized limits to the scope of bid protest jurisdiction and noted that the CDA was not an “alternative administrative remedy, available at the contractor’s option.” Distributed Solutions,
The plaintiffs in Distributed Solutions established that their case was within the court’s bid protest jurisdiction because they were “prospective bidders [who] ... submitted qualifying proposals ... and ... were prepared to submit bids pursuant to the anticipated Request for Quotation (RFQ) or Request for Proposal (RFP)....” Distribut
Plaintiff also relies on FFTF Restoration, in support of its claim that the court has jurisdiction of the complaint under the Tucker Act. Pl.’s Resp. 3. The court does not find FFTF Restoration helpful to plaintiff. In FFTF Restoration the bid protest was filed in response to the government’s cancellation of a “negotiated procurement.” FFTF Restoration,
More helpful to the court are cases discussеd by defendant which address disputes arising from options and are, without exception, decided under the CDA. See Def.’s Mot. 15 n. 1 (citing Alliant Techsys., Inc. v. United States (Alliant Techsystems),
In Cessna Aircraft the Navy had a contract with Cessna for the provision of training and related maintenance for undergraduate Naval Officers at the U.S. Naval Air Station, Pensacola, Florida. Cessna Aircraft,
The Federal Circuit endorsed the characterization by the ASBCA of the option dispute in Cessna Aircraft as a claim under the CDA. Id. at 1447 (“Like the [ASBCA], we view Cessna’s claims as ‘grounded in the CDA.’ ”). Notably, Cessna complied with the administrative requirements of the CDA by filing a certified claim with the CO before filing a case with the ASBCA. Id. at 1446. The Federal Circuit agreed with the ASBCA on both its jurisdictional decision and its judgment on the merits of the case. Cessna Aircraft,
In Alliant Techsystems the government contractor objected to thе government’s attempt to exercise an option. Alliant Techsys.,
3. Expansion of the Court’s Tucker Act Jurisdiction Does Not Extend to the Government’s Failure to Exercise an Option on an Existing Contract
While the definition of “in connection with a procurement” under the ADRA has been clarified by the Court of Appeals for the Federal Circuit in a way which has broadened prior interpretations of this court, the government’s failure to exercise an option on an existing contract is not encompassed by that clarification. See Distributed Solutions,
The Court of Federal Claims decided that, because plaintiff had not asked the court to review the merits of the award of the base support services contract, it did not have jurisdiction. Id. at 1288. RAMCOR appealed, asserting that amendments to 28 U.S.C. § 1491 under the ADRA “granted the Court of Federal Claims jurisdiction over RAM-COR’s action for a preliminary injunction.” Id. The Federal Circuit agreed with RAM-COR that the Court of Federal Claims had jurisdiction, citing the portion of § 1491(b)(1) which affords jurisdiction to the Court of Federal Claims when “the award of a contract or any alleged violation of statute or regulation in connection with a procurement or a proposed procurement” is at issue. Id. at 1288, 1291. The Federal Circuit held that RAMCOR’s objection to the lifting of the stay was within the jurisdiction of the court under the ADRA because the objection to the § 3553(c)(2) override was an objection to a statute which had a “connection to a procurement proposal, [and] an alleged violation suffices to supply jurisdiction.” Id. at 1289. The RAMCOR court dеtermined that the case fell under the court’s ADRA jurisdiction because of the direct connection between the stay and the procurement. Id. Claims of bad faith in the exercise of options have been established to be within the province of the CDA. E.g., Krygoski Constr. Co. v. United States,
Nor is plaintiff assisted by Ozdemir v. United States,
In its opinion, the Ozdemir court discussed at length the jurisdictional grant of the Tucker Act as modified by the ADRA. Id. at 634-35; see 28 U.S.C. § 1491(b)(1). The court determined that ADRA “jurisdiction ... do[es] not require a procurement connection.” Ozdemir,
III. Conclusion
The court lacks jurisdiction to hear plaintiffs claim under the ADRA. Instead, plaintiff must pursue relief pursuant to the requirements set forth in the CDA. See Omega World Travel, Inc. v. United States,
Defendant’s Motion to Dismiss is GRANTED.
IT IS SO ORDERED.
Notes
. In briefing, the parties refer to Contract W 912DY-05-D-0020, the identifying number that is used on the first page of the Contract and most of the interior pages. See Administrative Record (AR) 1, 54-70, 306-543. A number of the interi- or pages of the contract use W 912DY05-D-0014 as the identifying number. See AR 2-53. Neither party has mentioned the discrepancy and it does not appear to be in any way material to the dispute.
. Plaintiff's Motion for Preliminary and Permanent Injunction (Pl.'s Mоt.) is contained within plaintiff's Verified Complaint And Petition for Preliminary And Permanent Injunction (plaintiff's Complaint or Compl.), file September 28, 2009, dkt. no. 1.
.A corrected version of the AR was filed on October 23, 2009, dkt. no. 21. The corrections to the AR are not material to the resolution of this dispute and all citations in the opinion to the AR are to the AR filed October 5, 2009, dkt. no. 13.
. The court in Continental Collection & Disposal, Inc. v. United States (Continental),
. In Cessna Aircraft Co. v. Dalton (Cessna Aircraft),
. Cessna informed its CO that it was "proceeding [in performance] under the assumption that its services would soon be embodied in a definitive contract.” Cessna Aircraft,
. Defendant argues that the administrative exhaustion requirement has been strictly enforced by the Federal Circuit. Def.'s Mot. 16 (citing England v. Swanson Group, Inc.,
