Opinion
This petition, brought by a nonsettling defendant in a multiparty construction defect case, challenges an order made by the trial court which found the plaintiff’s settlement with a number of codefendants to be “in good faith” in accordance with the terms of Code of Civil Procedure section 877.6. 1 The action was brought by Cambridge Terrace Owners’ Association, a homeowners association representing numerous condominium owners (Association). Framed in counts for negligence, strict liability and breach of warranty, the complaint named as defendants the developer and general contractor on the project (collectively Developers). Developers cross-complained against and joined numerous subcontractors who worked on the project, claiming rights of indemnification. Association sought recovery for numerous categories of alleged construction defects, theoretically giving rise to cross-claims by Developers against virtually every subcontractor.
Global settlement discussions eventually resulted in an agreement whereby Association settled with Developers and Developers settled with 21 of the subcontractors. Three subcontractors did not settle, one of which was Gouvis Engineering, the petitioner herein. The terms of the settlement, as revealed by the petition for its approval, were as follows:
1. Developers would pay $4 million to Association.
2. A portion of this $4 million was “funded” (to use the wording of Developers’ moving papers) by the contribution of $925,500 by the subcontractors.
3. Developers committed to continue their action against the three non-settling subcontractors, and agreed to payments from this source as follows:
(a) The first $500,000 so recovered would be paid to Association.
(b) The next $1 million to be recovered would also be paid to Association. As to this $1 million, Developers guaranteed its payment by December 27, *646 1995—that is, if the sum so recovered by that date were less than the additional $1 million, Developers would pay the difference.
(c) All additional recovery from the three nonsettling subcontractors would be divided 50 percent to Developers and 50 percent to Association,
The motion for good faith settlement included an analysis of the value of the settlement. The initial payment was valued at $4 million (notwithstanding that $925,500 had come from the subcontractors). The commitments to pay $500,000 and $1 million from the action against nonsettling defendants were valued at face amounts, or $500,000 and $1 million respectively. The commitment to pay 50 percent of any additional recovery was valued at $1 million. Hence, the petitioning parties asserted that their total settlement with the Association had a value of $6.5 million.
The petitioners lodged with their motion a detailed analysis breaking down total settlement to component values attributable to the various subcategories of the construction project. The documentation utilized damage estimates which had been prepared by experts for the plaintiffs as well as experts for the Developers. Allocations of damage were then made to the specific categories of alleged damage. Defective roofs, for instance, received an allocation of $356,871. The total of all allocated damage, including 18 separate classifications, aggregated the total settlement figure of $6.5 million. It is not possible readily to identify from this list the portion of damage therefrom which might be ascribed to negligence of Gouvis. However, by letter dated October 7, 1994 (a date preceding the date of the global settlement agreement, which was in January 1995) counsel for Developers asserted that the portion of the $6.5 million settlement attributable to Gouvis’s fault was $451,291.
A hearing of the motion for determination of good faith settlement was held on January 26, 1995. After reviewing the moving and opposing paperwork the court granted the motion. The portions of the order relevant to our review are as follows:
“The motion for determination of good faith settlement by Defendants and Cross-Complainants [Developers] is granted pursuant to CCP §§ 877 and 877.6. The court finds the settlements between the Defendants and Cross-Complainants with both the Plaintiffs and the twenty-one (21) named settling Cross-Defendants are in good faith. . . .
“The court finds the opposing parties have not met their burden under CCP § 877.6(d). The Court further notes the allocations merely serve as a[] *647 cap on potential liability for the non-settling Cross-Defendants. Therefore, all pending Cross-Complaints for equitable indemnity and/or contribution against the settling parties are dismissed; all such future actions are barred.”
Accompanying the motion for determination of good faith settlement was a motion by Association for leave to amend its complaint to name the nonsettling defendants, the complaint previously having named no subcontractors. This motion was denied. Accordingly, following settlement with Developers, the Association had no further direct recourse against any of the participants in the construction. Developers, of course, retained their cross-complaints for indemnity against the three nonsettling subcontractors, and as a result of the settlement agreement had an obligation to pursue these actions and to share the recovery with Association.
One would reasonably assume that Gouvis is a “party aggrieved” by the court’s good faith ruling. Gouvis filed opposition papers and appeared at the hearing to oppose the determination. Gouvis was, therefore, entitled to file this petition in accordance with section 877.6, subdivision (e).
2
Just exactly how Gouvis has been prejudiced by the ruling is, however, a somewhat elusive concept. In the typical case of this kind the plaintiffs, having not settled with some of the subcontractors, would maintain their claims, subject to an offset for the portion of the settlement with the contractor appropriately allocable to areas of joint obligation by the contractor and the nonsettling subcontractors. (See, e.g.,
Erreca’s
v.
Superior Court
(1993)
The court’s order dismissing “all pending Cross-Complaints for equitable indemnity and/or contribution against the settling parties” might appear to affect Gouvis’s rights, except that we are not advised that Gouvis had any cross-complaint against any other subcontractor or, indeed, against Developers. The only litigation arising from this action yet pending which has the potential to affect Gouvis is the cross-complaint by Developers for indemnity.
As revealed by the pleadings in these cross-complaints, the elements of the causes of action for indemnity are (1) a showing of fault on the part of *648 the indemnitor (Gouvis), and (2) resulting damage to the indemnitee (Developers) for which Gouvis either contractually or equitably should be responsible. 3 (See 14 Cal.Jur.3d, Contribution and Indemnification, § 82, p. 754.) Herein lies the source of Gouvis’s complaint: Developers’ cross-complaint is limited to the amount it has paid in settlement to Association. The trial court has ruled that the totality of this amount is $6.5 million. While no specific ruling has been made on the breakdown of this total amount to whatever categories of damage may be the responsibility of Gouvis, it may be presumed that if the total is exaggerated the subparts also will be exaggerated. Gouvis therefore argues that Developers’ total valuation of the settlement as well as its presumptive estimate of Gouvis’s share of damage ($451,291) is excessive.
Our first consideration in facing this challenge to the good faith settlement order is to question how, if at all, the order might affect the subsequent action by Developers against Gouvis. The effect of an order adjudicating good faith of a settlement under sections 877 and 877.6 is to bar cross-complaints against parties who have settled and to provide an offset in the amount of the settlement to subsequent liability of nonsettlors. The cases dealing with the obligation of the settling parties to allocate the settlement to various claims all impose that requirement for the specific purpose of arriving at the proper offset. In
Alcal Roofing & Insulation
v.
Superior Court
(1992)
*649
A contractual settlement of a disputed claim is an agreement the interpretation and effect of which are governed by ordinary principles of contract law.
(Winet
v.
Price
(1992)
What, then, we may ask, is the legal effect of a determination of good faith? We apprehend that it can be no more than that specified in these unusual statutory provisions: namely, nondischarge of joint liability of non-settling parties and the creation of a credit against the claims against such nonsettling parties. Section 877 specifically provides that the determination of good faith “shall have the following effect,” suggesting that indeed no “other” effect is contemplated.
Our courts have somewhat expanded upon the brief description in the statutes of the scope and effect of “good faith” findings.
Southern Cal. Gas Co.
v.
Superior Court
(1986)
In Developers’ action against Gouvis for indemnity the terms of settlement approved at the good faith hearing are no doubt admissible in evidence, as suggested by
Peter Culley. A
key element of any action for indemnification is a showing of damage incurred by the indemnitee.
(Rossmoor Sanitation, Inc.
v.
Pylon, Inc.
(1975)
In this case it is true that Gouvis was a party to the litigation, and also that Gouvis was permitted to and did participate in the good faith hearing. As we have noted above, however, the procedures utilized at the hearing are those of motion practice (reliance upon affidavits) rather than the ordinary rules of evidence. Not only is the hearing abbreviated, but the objective of it is not precise or accurate determination of fact. As we stated in Regan Roofing, “. . . the inquiry at the good faith settlement stage is not the same as the inquiry at trial, where complete precision of allocation could presumably be achieved.”
(Regan Roofing
v.
Superior Court, supra,
We therefore conclude that the determination of the value of settlement and whatever underlying allocations may be deemed to have been approved at the good faith hearing have no precedential value in terms of the subsequent action by Developers against Gouvis for indemnification. Gouvis was therefore not legally prejudiced by the good faith order.
Disposition
The petition for writ of mandate is denied.
Kremer, P. J., and Haller, J., concurred.
Notes
Retired Justice of the Court of Appeal, Fourth District, sitting under assignment by the Chairperson of the Judicial Council.
All statutory references are to the Code of Civil Procedure unless otherwise specified.
Section 877.6, subdivision (e) provides in part: “When a determination of the good faith or lack of good faith of a settlement is made, any party aggrieved by the determination may petition the proper court to review the determination by writ of mandate.”
While the pleadings contain causes of action for breach of contract and breach of express and implied warranty, it would appear that the only viable cause of action against Gouvis, an engineer rather than a constructor of anything, would be for equitable indemnity. This was the position taken by Gouvis in the trial court and it was not there challenged.
As noted in
General Motors Corp.
v.
Superior Court
(1993)
