This long-running contract dispute is before the court again. In this appeal, Gould, Inc. (Gould) appeals the judgment of the United States Court of Federal Claims,
Gould, Inc. v. United States,
BACKGROUND
In 1983, the Naval Electronics Systems Command (Navy) solicited bids for a fixed-price, five-year contract to produce “Ban-eroft”-type radios. 1 In its request for proposals (RFP), the Navy included detailed performance specifications for the radios. In addition, the RFP included drawings, la-belled “for informational purposes only,” of prior Bancroft radios that had been developed for the Army.
On October 3, 1983, the Navy awarded Gould the Contract, No. N00039-83-C-0407 (the ’0407 Contract), for a fixed price of $44,778,779. Gould contends that its bid, in part, reflected a belief that it could simply modify the Army Bancroft radio to satisfy the Navy’s enhanced performance requirements. However, when Gould’s attempts to modify failed, it expended additional time, in excess of that contemplated when bidding on the contract, completely redesigning the radio. During contract performance, the Navy provided Gould with data which confirmed Gould’s findings that simply upgrading the Army’s radio would not meet the performance requirements of the Navy contract. According to Gould, it had requested this information from the Navy during the pre-award conference.
On December 11, 1986, Gould submitted a certified claim to the contracting officer seeking an “equitable reformation and upward adjustment in the price of [the] contract.” Gould sought more than $57 million in added costs due to the unanticipated design work that Gould had performed under the contract. In support of its requested relief the claim contained three separate counts. In Count one, Gould alleged that the Navy had violated 10 U.S.C. § 2306(h)(1)(D) (1982) by failing to supply a “stable design” for the multi-year contract, 2 thereby making the contract illegal. Count two alleged that the Navy improperly withheld information that would have apprised bidders of “the degree of design effort and risk involved in meeting the Navy’s performance specification.” Count three alleged that there was a mutual mistake by both Gould and the Navy regarding a basic assumption of the contract, namely that there was only minimal design and development work to be performed under the contract. 3
On January 6,1988, the contracting officer issued a decision denying Gould’s claim. Gould appealed that decision to the then Claims Court pursuant to 41 U.S.C. § 609(a)(1) (1988). In addition to raising jurisdictional issues, the government moved to dismiss for failure to state a claim upon which relief can be granted.
In a decision dated January 16, 1990, the Claims Court granted the government’s motion.
Gould, Inc. v. United States,
On June 7, 1991, we vacated the decision of the Claims Court and remanded the case for trial.
Gould, Inc. v. United States,
Upon remand, the government filed a motion to dismiss for lack of jurisdiction. In an opinion dated October 29, 1993, the Court of Federal Claims
4
granted the government’s motion.
Gould, Inc. v. United States,
Because Gould’s complaint is based solely on a contract with the United States and yet it alleges both that there was no stable design and that the contract (whether express or implied in fact) was illegal, the only possible basis for contract jurisdiction is a contract implied in law. The Tucker Act’s grant of jurisdiction is limited, however, to cases based “upon any express or implied contract with the United States,” 28 U.S.C. § 1491(a)(1) (1988). Implied-in-law contracts, if contracts at all, are not contracts within this court’s jurisdiction. Merritt v. United States,267 U.S. 338 , 341,45 S.Ct. 278 , 279,69 L.Ed. 643 (1925); City of El Centro v. United States,922 F.2d 816 , 823 (Fed.Cir.1990).
Id.
at 761 (footnotes omitted). Furthermore, the court held that payment on Gould’s claim was barred by the Supreme Court’s decision in
Office of Personnel Management v. Richmond,
DISCUSSION
I.
Whether a motion to dismiss for lack of jurisdiction has been properly granted is a question of law subject to complete and independent review on appeal.
Shearin v. United States,
The government argues that the contracting officer lacked actual authority to enter into an express or implied-in-fact contract with Gould, and therefore Gould’s only theory of recovery is under an implied-at-law claim which is outside the jurisdiction of the Court of Federal Claims. In its amended complaint Gould alleged that its procurement contract with the government was entered into in violation of law since the government did not provide a “stable design” as required in 10 U.S.C. § 2306(h)(1)(D). Given Gould’s allegation, argues the government, no contract (express or implied-in-fact) could have arisen because a contracting officer does not have actual authority to enter into illegal contracts. Therefore, the government argues, the Court of Federal Claims correctly found that the only possible basis for contract jurisdiction is a contract implied-at-law. Since it is well established that such claims are outside the jurisdiction of the Court of Federal Claims, the government concludes that the trial court properly dismissed Gould’s amended complaint for lack of jurisdiction.
As an initial matter, the government mischaracterizes the issue in this case. In
Spruill v. Merit Sys. Protection Bd.,
A dismissal for failure to state a claim, however, is a decision on the merits which focuses on whether the complaint contains allegations, that, if proven, are sufficient to entitle a party to relief.
See Conley v. Gibson,
The distinction between lack of jurisdiction and failure to state a claim upon which relief can be granted, is an important one: “[T]he court must assume jurisdiction to decide whether the allegations state a cause of action on which the court can grant relief as well as to determine issues of fact arising in the controversy. Jurisdiction, therefore, is not defeated ... by the possibility that the averments might fail to state a cause of action on which petitioners could actually recover....”
Id.
at 639-40 (quoting
Bell v. Hood,
The issue in this appeal is not jurisdiction, but whether Gould stated a claim upon which relief can be granted. First, there is no question that Gould’s complaint alleges the existence of an express contract, albeit one entered into allegedly in violation of 10 U.S.C. § 2306(h)(1)(D). This is sufficient, however, to confer jurisdiction in the Court of Federal Claims. The government’s argument that Gould’s allegation of illegality voided the procurement contract, thereby divesting the Court of Federal Claims of jurisdiction, ignores our precedent which states that a “court should ordinarily impose the binding stamp of nullity only when the illegality is plain.”
John Reiner & Co. v. United States,
Second, even if Gould’s allegations of an express contract are found insufficient, Gould’s amended complaint, when viewed in a light most favorable to Gould, alleges the existence of an implied-in-fact contract — a separate basis of jurisdiction in the Court of Federal Claims.
United States v. Amdahl Corp.,
The government’s argument that
Richmond,
II.
Regardless of the label the government places on its present motion, the issue on appeal is whether Gould stated a claim upon which relief can be granted. This is the same issue we addressed in Gould II, when we concluded that Gould had stated a claim upon which relief can be granted.
“The law of the case is a judicially created doctrine, the purposes of which are to prevent the relitigation of issues that have been decided and to ensure that trial courts follow the decisions of appellate courts.”
Jamesbury Corp. v. Litton Indus. Prods., Inc.,
Since the government seeks to relitigate in this appeal the issue of whether Gould stated a claim upon which relief can be granted, it must show that one of these exceptional circumstances is present. The government argues that subsequent controlling authority precludes recovery in this case.
5
Specifieal
*931
ly, the government maintains that our court’s decision in
CACI, Inc. v. Stone,
In CACI, the Army entered into a contract with VSE Corporation without obtaining a prior delegation of procurement authority (DPA) as required by regulation, 41 C.F.R. § 201-20.305-1 (1991). CACI at 1234-35. In an action by CACI to suspend the contract, CACI argued that because GSA had not delegated procurement authority to the Army prior to awarding VSE the contract, the Army had no actual authority to contract with VSE, and therefore the contract was void. Id. at 1235. VSE countered that the contract was not void because it was not plainly illegal as required in Reiner. Id. Applying the standard set forth in Reiner, the court concluded that the Army’s failure to obtain a DPA was a plain and clear error of law, and therefore the contract was void. Accordingly, CACI did not overrule the holding of Reiner, as suggested by the government, but merely applied the law in Reiner to the particular facts in that case.
Regarding Richmond, upon which the government heavily relies, we explained above why that case is beside the point. Furthermore, it was decided before we issued our opinion in Gould II; it is not subsequent controlling authority. Despite the government’s failure to cite to Richmond in its prior appeal, we were aware of this case when we issued our decision in Gould II. We fail to see how this prior precedent can be a basis for refusing to apply the law of the ease doctrine.
The issue of whether Gould stated a claim upon which relief can be granted is law of the ease. The judgment of the Court of Federal Claims is vacated and the case is remanded, a second time, for trial. This matter is approaching its tenth anniversary and Gould has yet to get its first hearing on the merits. Justice delayed is indeed justice denied. We trust that the Court of Federal Claims will expedite giving Gould the trial of its issues to which it is entitled.
VACATED AND REMANDED.
Notes
. A "Bancroft"-type radio is a VHF-FM radio built to certain military specifications. See MILT-49129 (EL) (1977).
. The statute provides:
(h)(1) To the extent that funds are otherwise available for obligation, the head of an agency may make multiyear contracts (other than contracts described in paragraph (6)) for the purchase of property, including weapon systems and items and services associated with weapon systems (or the logistics support thereof), whenever he finds—
* * * * * *
(D) that there is a stable design for the property to be acquired and that the technical risks associated with such property are not excessive.
10 U.S.C. § 2306(h)(1)(D) (1982).
.Counts II and III of Gould's amended complaint both incorporate the allegation in Count I that the contract was entered into in violation of 10 U.S.C. § 2306(h)(1)(D).
. The Claims Court was renamed the Court of Federal Claims pursuant to § 902 of the Federal Courts Administration Act of 1992, Pub.L. No. 102-572, 106 Stat. 4506, 4516 (1992), effective October 29, 1992.
. The government also argues that the law of the case does not apply because we never addressed the issue of actual authority in
Gould II.
But this appeal raises the same grounds for dismissal that we considered and rejected in
Gould
II— whether Gould stated a claim upon which relief can be granted. To allow the government to make new arguments regarding the same grounds for relief would violate the purpose of the law . of the case doctrine.
See Gindes,
