OPINION
This is an appeal from the granting of two summary judgments based on a ten-year statute of repose. Appellees, Western Steel Company (“Western”) and Braselton Construction Company (“Braselton”), were subcontractors hired by appellants, Robert Frank Gordon and Port Royal Development Corporation (“Gordon” and “Port Royal,” respectively). By two points of error, appellants challenge the trial court’s holding that substantial completion of a subcontractor’s share of a construction project is an improvement that will trigger the statute of repose. We affirm.
Gordon and Port Royal were, at one time, developers of a condominium building project known as “Port Royal By-The-Sea” on Mustang Island in Corpus Christi, Texas. Subsequent to the completion of the entire project, the Port Royal Homeowners Association, Inc. brought suit against Gordon and Port Royal seeking damages for alleged defects in the construction of the condominiums. On October 21, 1994, Gordon and Port Royal filed third-party actions for contribution and indemnity against the various subcontractors involved in the construction, including Western and Braselton.
Western and Braselton moved for summary judgment based on the ten-year statute of repose for those who construct or repair improvements to real property. See Tex. Civ. Prac. & Rem.Code Ann. § 16.009 (Vernon 1986). By affidavit, Western’s president, *745 George Gains stated that Western’s subcontracting work, which involved delivering and erecting structural steel at Port Royal By-The-Sea, was substantially completed by August 24, 1984. Braselton’s president, Bill Braselton, also stated by way of affidavit that substantial completion of its share of the project, which involved building concrete structures, occurred on August 31, 1984. Braselton also attached verified copies of its “applications and certificates for payment” for work performed from August 8 through 31, 1984, and September 1 through 28, 1984, respectively. Gordon and Port Royal agreed that Braselton had submitted its final bill by September 28, 1984.
The condominiums were made up of several buildings, each finished at different stages. Thomas Hardin, a lender for the Port Royal project, determined that substantial completion of the entire project occurred on June 1, 1985. Based on the statute of repose, the trial court granted both Western’s and Bra-selton’s motions for summary judgment. The trial court effectively held that a subcontractor’s substantial completion of its share of a project can be an improvement to real property which triggers the statute of repose. As a result, Gordon and Port Royal were time-barred from bringing suit against Western and Braselton. Thereafter, the trial court severed appellant’s claims against Western and Braselton from the remaining litigation.
Appellants’ first point of error challenges the granting of summary judgment on this basis. They contend that the trial court erred in holding that a subcontractor is entitled to the protection of the statute of repose upon the substantial completion of his work, irrespective of the status of the entire construction project. Appellants maintain that the statute should only apply after the entire project is complete, and to rule otherwise contradicts the statute’s intent and unnecessarily complicates an aggrieved party’s ability to sue the proper parties. Before addressing the merits of appellants’ point, we will set out the standard of review for a summary judgment.
Standard of Review
The following factors guide our review of a summary judgment: (1) the pleadings and summary judgment evidence must establish that no genuine issue of material fact exists, and that the movant is entitled to judgment as a matter of law; (2) in deciding whether there is a disputed material fact issue, evidence favorable to the non-movant will be taken as true; and (3) every reasonable inference must be indulged in favor of the non-movant and any doubts resolved in its favor.
Nixon v. Mr. Property Management Co.,
Upon appeal of a summary judgment, the question is “whether the summary judgment proof establishes, as a matter of law, that there is no genuine issue of material fact as to one or more of the essential elements of plaintiffs cause of action.”
Muñoz v. Gulf Oil Co.,
The Statute of Repose
The statute of repose, found in Section 16.009 of the Texas Civil Practice and Remedies Code and entitled “Persons Furnishing Construction or Repair of Improvements,” states:
(a) A claimant must bring suit for damages ... against a person who constructs or repairs an improvement to real property not later than 10 years after the substantial completion of the improvement in an action arising out of a defective or unsafe condition of the real property or a deficiency in the construction or repair of the improvement.
(b) This section applies to suit for ...
(4) contribution; or
(5) indemnity.
Tex. Crv. PRAC. & Rem.Code Ann. § 16.009 (Vernon 1986). The statute of repose bars all claims after the prescribed ten-year peri
*746
od.
Tumminello v. U.S. Home Corp.,
801 S.W.2d
186,
187 (Tex.App.—Houston
[1st
Dist.] 1990, writ denied) (citing
Hasty v. Rust Eng’g Co.,
Whether the statute protects a subcontractor in this context depends upon the construction of the statute. Matters of statutory construction are questions of law for the court to decide.
Johnson v. City of Fort Worth,
By its clear language, the statute protects subcontractors from liability after ten years, so long as they constructed or repaired an improvement to realty.
See Williams v. U.S. Natural Resources, Inc.,
Because this question is not answered on the face of the statute, we look next to the legislative history. In 1969, the Texas Legislature enacted a statute of repose applicable to architects and engineers.
See
Tex. Civ. Prac. & Rem.Code Ann. § 16.008 (Vernon 1986). The statute had at its origin an intent to protect those who design improvements to realty.
Sonnier,
The sponsor of H.B. 1105, later codified as section 16.009, explained that the purpose of the statute was to avoid the situation “where a contractor builds a building or a construction project and he has a potential liability on that [improvement] until the day he dies.”
Petro Stopping Ctrs., Inc. v. Owens-Corning Fiberglas Corp.,
There shall be commenced and prosecuted within ten years after the substantial completion of any improvement to real property, and not afterward, all actions or suits in court for damages ... or for contribution or indemnity for damages ... arising out of the defective or unsafe condition of any *747 such real property or any deficiency in the construction or repair of any improvements on such real property....
Act of May 14, 1975, 64th Leg., R.S., ch. 269, § 2, 1975 Tex. Gen. Laws 649 (codified as Tex.Rev.Civ. Stat. Ann. art. 5536a, § 2 (1975)), (amended 1985) (current version at Tex. Crv. Prac. & Rem.Code Ann. § 16.009). Courts have held that, after reviewing the legislative proceedings, the intention of the legislature in adopting this provision was “to extend the protection afforded to architects and engineers to a new class of construction professional — contractors and repairers.”
Williams,
Because of the dearth of Texas case law on this issue, the parties have cited as persuasive authority cases from other jurisdictions as support for their respective interpretations of the statute. Appellants cite three eases which have interpreted the phrase “substantial completion” as meaning the completion of the entire project.
Patraka v. Armco Steel Co.,
Appellants rely on
Patraka v. Armco Steel Co.,
where the court held that the statute of repose did not begin to run against a general contractor until the entire project was substantially complete, which it interpreted to mean “so far completed that it may be used for its intended purposes.”
Patraka,
By contrast, appellees’ cases focus on the application of the rule
when different parties
*748
are responsible for different improvements within the context of a larger project.
Two New Jersey cases provide insight for when the period of repose should begin in such contexts. In
Welch v. Engineers, Inc.,
... the Legislature most likely meant that when a person rendered any construction-related services on a particular job, finished them and walked away from the job-site with the work accepted, that person could look back ten years and one day “after the performance or furnishing of such services and construction,” and know there was repose from liability. We do not think that the Legislature intended to let repose turn on serial cut-off dates accruing through various stages of the work [where the same person was involved], turning on fact-sensitive determinations and various analytic approaches to construction staging. The rule we approve here is the easiest to administer and the final date of any particular persons’ furnishing services or construction is the simplest to determine.
Id. at 165.
Similarly, in
Hopkins v. Fox & Lazo Realtors,
Under the facts on this case, where different subcontractors were responsible for the construction of different parts of a larger project, the statute of repose should be applied to each of those individual subcontractors when they have completed their respective improvements. Appellants suggest that general contractors or the intended beneficiaries of the services may be penalized by the compartmentalization of the improvements and the imposition of successive periods of repose, noting that our statute applies to indemnification suits, whereas California’s statute, for example, does not. This distinction does not alter our construction of the Texas statute. While we recognize the possibility that a party who constructed or repaired an improvement in a deficient manner may escape liability if not sued within ten years of that deficient performance, we do not conclude that such possibility militates in favor of an alternative construction of the statute. 2
In most scenarios, the various improvements contained within a larger project will not stretch beyond several years, and the general contractors or beneficiaries ordinarily have opportunities to supervise or disapprove of the work along the way. Secondly,
*749
it is not overly burdensome to decipher when respective contractors substantially complete their improvements
{e.g.
when they submit their final bills and/or walk away from the project). If a material issue arises as to whether the date they completed their work falls outside the period of repose, then summary judgment is not appropriate, and the trier of fact should resolve such issue. Finally, to the extent that appellants rely on the limitations of their rights by construing the statute as appellees urge, we only comment that the fairness of the statute of repose has already been litigated in the constitutional context.
See, e.g., Barnes,
In summary, we conclude that the trial court’s granting of summary judgment in favor of Braselton and Western based on the statute of repose should be affirmed if appel-lees met their burden of proving that they substantially completed them improvement to the project more than ten years before they were sued. Starting the statute of repose when each subcontractor finishes its improvement conforms with the legislative in-ted of preventing indefinite liability for those who construct or repair improvements to real property.
In this ease each appellee presented affidavits from their presidents asserting that they had substantially completed the work they contracted to perform, more than ten years before they were sued.
3
In addition to these assertions, each appellee presented as evidence of the completion verified receipts for payment. An affidavit of an interested party may serve as competent summary judgment proof so long as such affidavit evidence is clear, positive, direct, credible, free from contradictions, and susceptible of being readily controverted.
Gallegos v. Escalon,
Because appellees offered uneontroverted proof that they substantially completed their improvements more than ten years before they were sued, the trial court’s granting of summary judgment in their favor must stand. Points of error one and two are overruled. The judgment of the trial court is affirmed.
Notes
. Courts have repeatedly rejected arguments that the statute violates the federal and Texas guarantees of due process and equal protection, and the Texas open courts provision.
See e.g. Trinity River Auth. v. URS Consultants, Inc.,
. We would note that the beneficiaries in this action were allowed to proceed with their claims against the general contractor after the claims against appellees were severed from the underlying cause.
. Bill Braselton testified that his company was hired to build the concrete structure of Port Royal Resorts, including its columns, slabs, and beams. He said it was substantially completed on August 31, 1984. Western offered the deposition testimony of its president stating that it had supplied the steel for the roof structure and erected that structure in accordance with the terms of its contract. Western completed its improvement by August 24, 1984.
