Gordon Sel-Way, Inc. v. Spence Bros.Gordon Sel-Way, Inc. v. Spence Bros.
In the private arbitration award which underlies this action, a panel of arbitrators in-
We granted leave to decide (1) whether the arbitrators improperly included interest as part of the award, (2) what interest rate applies under
i
This appeal arises out of a construction contract
A dispute arose between Sel-Way and Spence concerning compensation that Sel-Way claimed it was owed under the contract, and in September, 1982, Sel-Way demanded arbitration. Its original claim in the amount of $902,550.43 was later amended to $4,000,000. By mutual agreement, the Spence/Sel-Way arbitration proceedings were adjourned pending Spence’s settlement negotiations of its own arbitration claims against Washtenaw County.
Initially, on February 26, 1987, the trial judge issued an opinion and order denying Spence’s motion to vacate or modify the arbitration award, but expressly allowed Spence thirty days to file a motion for reconsideration. On May 22, 1987, the trial court issued its further opinion and order in this matter. It denied Spence’s motion for reconsideration. However, it did accept one of Spence’s arguments and found that there was no contractual basis for the arbitrators’ award of interest and ordered that the award be modified accordingly under MCR 3.602(K). The trial court also
Both Spence and Sel-Way appealed in the Court of Appeals. Spence once again sought to vacate the award "due to alleged 'evident partiality’ by one of the arbitrators and the failure of the arbitrators to state which of plaintiff’s multiple claims were the bases of the award.”
This Court denied Spence’s application for leave to appeal, but held in abeyance Sel-Way’s application for leave to appeal as cross-appellant pending its decision in
Old Orchard by the Bay Associates v Hamilton Mutual Ins
Co,
ii
We first consider Sel-Way’s contentions that the lower court erred when it modified the arbitration award by striking the amount identified as "interest” and that the Court of Appeals erred when it affirmed that decision. Spence argued, and the lower courts agreed, that the arbitrators exceeded the scope of their powers when they awarded $343,007.79 in interest absent express authority to do so under the terms of the Spence/Sel-Way contract. It is undisputed that there is no provision for interest in the Spence/Sel-Way contract.
4
Sel-Way contends nonetheless that the absence of an interest provision in the contract is not fatal. It
Because the Spence/Sel-Way arbitration clause provides that judgment may be entered on the arbitration award, it falls within the definition of a "statutory arbitration,” and is governed by
Although both MCR 3.602(J)(l)(c) and MCR 3.602(K)(l)(b) address the appropriate remedy when the court determines that the arbitrators
[T]he court shall modify or correct the award if:
(b) the arbitrator has awarded on a matter not submitted to the arbitrator, and the award may be corrected without affecting the merits of the decision on the issues submitted ....
Thus, MCR 3.602(K)(l)(b) is the pertinent court rule governing this appeal.
The appropriate standard of review for determining whether arbitrators have exceeded the scope of their authority was set forth by this Court in
DAIIE v Gavin, supra.
The
Gavin
Court elucidated the principle that it is the parties’ contract which defines and limits their rights and duties and the arbitration clause or agreement which confers upon the arbitrators their authority to act. Since arbitrators derive their authority from the parties’ contract and arbitration agreement, they are bound to act within those terms.
Using these principles, the
Gavin
Court concluded that it is appropriate for reviewing courts to find that arbitrators have exceeded their power "whenever they act beyond the material terms of the contract from which they primarily draw their authority . . . .”
If an arbitration clause is written in broad and comprehensive language, i.e., language including all claims and disputes, the computation of damages for breach of contract is presumed to be included. 6 CJS, Arbitration, § 25, p 200. See also
Orion Shipping & Trading Co v Eastern States Petroleum Corp,
312 F2d 299 (CA 2, 1963). Furthermore, an award will be presumed to be within the scope of the arbitrators’ authority absent express language to the contrary. 2 MLP, Arbitration, § 5, p 469; 6 CJS, Arbitration, § 107, pp 334-335. See
General Telephone Co of Ohio v Communication Workers,
648 F2d 452 (CA 6, 1981) (holding that awards should be upheld as long as they do not disregard the plain provisions of the contract). Thus, an allegation that the arbitrators have exceeded their powers must be carefully evaluated in order to assure that this claim is not used as a ruse to induce the court to review the merits of the arbitrators’ decision. Stated otherwise, courts may not substitute their judgment for that of the arbitrators and hence are reluctant to vacate or modify an award when the arbitration agreement does not expressly limit the arbitrators’ power in some way. Callahan, Bramble & Lurie,
supra,
p 191; 6 CJS, Arbitration, § 162, pp 428-429. See also
Gavin, supra,
p 429;
Kaleva-Norman-Dickson School Dist v Kaleva-Norman-Dickson Teachers’ Ass’n,
With these principles in mind, we conclude that the trial court improperly modified the arbitration award by deleting the interest amount. We agree
Furthermore, the Spence/Sel-Way arbitration clause incorporates Rule 43 of the American Arbitration Association’s Construction Industry Arbitration Rules (1986) which provides:
The arbitrator may grant any remedy or relief which is just and equitable and within the terms of the agreement of the parties. [Emphasis added.]
Consequently, absent a provision expressly precluding authority to award interest as an element of damages, we find that the arbitrators did not exceed the scope of their authority by including an interest amount in their award.
8
This finding comports with
A provision in a written contract to settle byarbitration ... a controversy thereafter arising between the parties to the contract . . . shall stand as a submission to arbitration of any controversy arising under said contract not expressly exempt from arbitration by the terms of the contract. [Emphasis added.]
Finally, we acknowledge, as did the Court of Appeals, the fact that Michigan has long recognized the common-law doctrine of awarding interest as an element of damages.
It is our belief that the important purposes underlying arbitration are
better served by considering, in the absence of an explicit agreement to the contrary, pre-award damage claims, including interest, to have been submitted to arbitration. [Sansone v Metropolitan Property & Liability Ins Co, 30 Mass App 660, 663;572 NE2d 588 (1991) (holding that it is improper for the trial judge to add preaward interest to an arbitration award).]
Commentators and courts in other jurisdictions have also concluded that arbitrators may include interest in an award unless the parties have expressly provided otherwise in their contract or arbitration agreement. 10
Thus, we conclude that the Court of Appeals erroneously relied on the contract’s silence concerning the right to interest and the parties’ decision to arbitrate their disputes as conclusive evidence of their intent to postpone the date the payments owing under the contract were to be paid. In reaching that conclusion, the Court of Appeals violated the general principles of arbitration which preclude the courts from reinterpreting a contract, deciding contract disputes submitted to arbitration, and upsetting an award for reasons going to the merits of the claim. Implicit in the arbitration award is the fact that the arbitrators
III
Next, we determine what interest rate applies under
After an arbitration award is rendered, the sue-
Sel-Way also contends that the legislative histories of both
In essence, Sel-Way asks this Court to complete the work begun in
Old Orchard, supra.
It urges us to adopt its construction of
Spence argues, and the lower courts agreed, that only
We hold that the appropriate rate of interest under
A
To ascertain the appropriate rate of interest under
A critical difference between
Although the Legislature has made numerous amendments to the predecessors of both
B
Finally, we must determine at what point in time, if at all, postaward statutory interest is governed by
For over a century, the two interest statutes worked in tandem in contract actions. The predecessor to
As a result of the 1965 amendment to
causes two formerly compatible statutes to be in irreconcilable conflict. Only by concluding that the§ 6013 interest provision has repealed MCL 438.7 ; MSA 19.4 by necessary implication, insofar as civil actions are concerned, can any sense be made of the two interest statutes.
While repeals by implication are not favored, it is a question of legislative intent whether or not there has been such a repeal of an earlier statute by a subsequently enacted one. See Attorney General ex rel Owen v Joyce,233 Mich 619 , 621;207 NW 863 (1926); Yarger v City of Hastings,375 Mich 413 , 417;134 NW2d 726 (1965). The latest legislative expression on the entitlement to prejudgment interest must control where two interest statutes specifically address the issue of entitlement and cannot be harmonized. [Id. at 257.]
In
Old Orchard,
this Court found, an implied repeal of
[n]othing contained in this [statutory arbitration] chapter shall be construed to impair, diminish, or in any manner to affect the equitable power and authority of any court over arbitrators, awards, or the parties thereto ....
We agree with Sel-Way that the reason for filing a civil action has no bearing on the nature of the proceeding. Once the complaint is filed, as long as it results in a money judgment,
Moreover, there is every reason to apply § 6013 and none to preclude its application under these
IV
Sel-Way has urged this Court to assure that prevailing parties in arbitration proceedings receive full compensation. This decision accomplishes that goal within the confines of the parties’ contract and this state’s pre- and postjudgment interest statutes. On the question of preaward interest, we conclude that the arbitrators properly included interest as part of their award. Further
We reverse in part and affirm in part the decision of the Court of Appeals and remand this case to the trial court to reinstate the interest portion of the award and to recompute the proper post-award statutory interest under
Notes
The Spence/Sel-Way contract incorporates the following arbitration clause from the owner/Spence contract:
All claims, disputes and other matters in question arising out of, or relating to, the contract-documents or the breach thereof, except for claims which have been waived by the making and acceptance of final payment as provided by Section 20 [of the owner/Spence contract], shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. This agreement to arbitrate shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in any court having jurisdiction thereof.
At that time, Spence also deposited $1,925,944.79, the total amount of the challenged award, with the Washtenaw County Clerk subject to disposition by court order. On March 8, 1990, after this Court denied Spence’s application for leave to appeal, the trial court ordered that the noninterest portion of the award in the amount of $1,572,442.12 be paid to Sel-Way.
The court, by order dated October 31, 1990, authorized payment of $266,043.34 to Sel-Way. This payment represented interest on the $1,572,442.12 noninterest portion of the arbitration award at the rate of five percent per annum commencing from the date of the award through the date the judgment was satisfied.
Subsequently, the trial court also denied Sel-Way’s motion to correct the judgment, rejecting Sel-Way’s argument that
Sel-Way apparently argued at one point that the Spenee/Sel-Way contract incorporated ¶ 19.7 of the owner/Spence contract, which provides:
If the owner fails to make payment thirty (30) days after approval by the engineer, in addition to other remedies available to the contractor, there shall be added to each such payment interest at the maximum legal rate commencing on the first day after said payment is due and continuing until the payment is received by the contractor.
That claim appears to be abandoned by Sel-Way here perhaps by oversight or perhaps the parties now agree that ¶ 19.7 applied only to the owner/Spence contractual relationship and that the Spence/Sel-Way contract specified payment terms without reference to interest. In any event, we proceed on the assumption that the Spence/Sel-Way contract contains no provision for interest.
Unlike the situation in
Old Orchard, supra,
the arbitrators’ award of interest in this case encompasses a period during which neither
The Michigan Court Rules adopt the same grounds for vacating, modifying or correcting an arbitration award as set out in the Uniform Arbitration Act. 7 ULA 5.
See n 1.
It is precisely the lack of any express contractual provision concerning the arbitrators’ authority to grant preaward interest which distinguishes this case from Gavin, supra. In Gavin, this Court found it necessary to vacate an arbitration award because the arbitrators had exceeded the scope of their authority by granting relief which conflicted with an express provision in the parties’ contract.
The concept of common-law interest as an element of damages is distinct from the award of prejudgment interest which is derived from statute. See
Swift v Dodson,
See Domke, On Commercial Arbitration (rev ed), § 30.03, p 447; Callahan, Bramble & Lurie, §§ 3.5, 7.22, and 8.10, pp 54-57, Í65-168, 190-191. See also
Westminster Construction Corp, supra,
pp 210-211 (recognizing, as a general rule, that arbitrators may award interest, even if not claimed, unless the parties have specifically provided otherwise in their agreement);
Wayne Distributing Co v Piti Bldg Co, Inc,
In all actions founded on contracts express or implied, whenever in the execution thereof any amount in money shall be liquidated or ascertained in favor of either party, by verdict, report of referees, award of arbitrators, or by assessment made by the clerk of the court or by any other mode of assessment according to law, it shall be lawful, unless such verdict, report, award, or assessment shall be set aside, to allow and receive interest upon such amount so ascertained or liquidated, until payment thereof, or until judgment shall be thereupon rendered; and in making up and recording such judgment, the interest on such amount shall be added thereto, and included in the judgment.
The statute provides:
(1) Interest shall be allowed on a money judgment recovered in a civil action, as provided in this section.
(4) For complaints filed on or after June 1, 1980, interest shall be calculated from the date of filing the complaint to the date of satisfaction of the judgment at the rate of 12% per year compounded annually ....