Goodman v. Baerlocher

88 Wis. 287 | Wis. | 1894

Pinney, J.

1. The original contractors, Gross & Heimer, had not performed their contract when the first building, being in an incomplete condition, was destroyed. It had not been delivered to or accepted by the owner, and was therefore at the risk of the contractors, and the destruction of the building did not excuse them from performing the contract. Dermott v. Jones, 2 Wall. 1; Adams v. Nichols, 19 Pick. 275; Tompkins v. Dudley, 25 N. Y. 272; School Trustees v. Bennett, 27 N. J. Law, 515. In Tompkins v. Dudley, supra, it was held that the owner of the lots might recover back from his contractor payments in such case which he had made on account of the building. In this case the building had not only not been completed, but it had been utterly destroyed, so that the owner of the ground had received no benefit from the materials and work and labor employed in attempting to build it, and the original contractors could not have recovered anything or enforced *292a lien for what had been furnished or done in attempting to construct and erect the building. Whether the subcontractors or material men and laborers under the contractors are in any better situation, is the question to be determined;

Sec. 3314, R. S., provides that: “Every person who as principal contractor, . . . performs any wrork or labor, furnishes any material, . . . in or about the erection, construction, ... of any dwelling house, building, . . . shall haw a lien thereon, and upon the interest of the owner of sueh dwelling house, building, ... in and to the land upon which the same is situated, . . . not exceeding in extent,” etc. And see. 3315 extends the right to “ every person who, as subcontractor of a principal contractor, or employee of any contractor or subcontractor, performs any work or labor for, or furnishes any materials' to a principal contractor or subcontractor in any of the cases mentioned in the preceding section,” if within sixty days thereafter he gives the specified notice in writing to the owner, or his agent, of the property to be affected by such lien, “ with a statement of the labor performed or materials furnished, and the amounts due from such principal contractor or subcontractor, and that he claims the lien given ” by oh. 143, R. S.

The lien provided by the statute is in the nature of a charge on land given by statute to the persons named therein to secure a priority or preference of payment for the performance of labor or supply of materials to buildings or other improvements, to be enforced against the particular property in which they have become incorporated, in the manner and under the limitations therein expressly provided.” Phil. Mech. Liens, § 9. In Van Stone v. Stillwell & B. Mfg. Co. 142 U. S. 128, 136, it was said, in substance, that the lien is given to secure priority of payment of the price and value of work performed and the maté-.rials furnished; that “ it is the use of the materials fur-*293nishecl and labor expended by the contractor, whereby the building becomes a part of the freehold, that gives the material man or laborer his lien under the statute.” The object is not only to encourage building, but to afford the contractor, material man, or laborer security upon and against the property of the owner materially increased in value by the materials and labor wrought into it, and so rests upon the strongest equitable basis, for the building becomes a part of the realty, and it is the principal matter, to which the lien on the realty seems to be an incident, and without which the lien on the building would be fruitless or of little value. In Mallory v. La Crosse Abattoir Co. 80 Wis. 170, 175, in which the remedy given by this statute to subcontractors, laborers, and material men was considered, it was said: “ The theory of the law giving to laborers and material men specific liens upon the property upon which their labor was performed or their materials used seems to be that, because the value of such property has been enhanced thereby, it is just that the property should be specifically charged with the sums expended thereon for those purposes. The reason of the law extends to expenditures on the property by subcontractors as well as by those who contract directly with the owner.” And the cases, of Munger v. Lenroot, 32 Wis. 544, and Winslow v. Urquhart, 39 Wis. 260, really rest upon this ground.

In this case the defendant Baerlocher, the owner of the lots, has received no benefit whatever from the material and labor in question, and the principal contractors were clearly not entitled to any compensation for them, nor to any lien on the lots, on that account. This case is not, we think, within the statute relied on, for the statute does not extend to the case where no building is erected or constructed and no benefit has passed to or been accepted by the lot owner. To apply the statute so as to extend its provisions to such a case as the present would, we think, *294be giving it not merely a liberal, but a most latitudinarián and unreasonable, construction, and to mistake the incident as the subject of the lien for the principal thing which gives increased value to the ground upon which it has been erected, and would require the lot owner to answer through his property for the materials and labor that had entered into the building destroyed, from which he has not and could not derive any benefit, and would leave him without any remedy whatever against the principal contractor; making him practically an insurer of property over which he had not acquired control, and which remained at the risk of the contractors. If the second building shall be destroyed before its completion, it might thus transpire that the lot owner, according to the respondents’ contention, might be wholly deprived of his lots without any fault of ■his own, and without having received any benefit or compensation therefor whatever.

Under a statute in Pennsylvania not materially different from the one in question, it has been held that the lien on the building is the principal thing, and the lien upon the land on which it is situated is an incident of the completion of the building, and that when the building is destroyed, by fire or otherwise, before completion, there can be no lien against the land on which it was attempted to erect it; that the lien shares the fate of the building; and that the reason for binding the land ceases with the destruction of the. building. Presbyterian Church v. Stettler, 26 Pa. St. 246; Wigton and Brook's Appeal, 28 Pa. St. 161; Linden Steel Co. v. Rough Run Mfg. Co. 158 Pa. St. 238, 246. This view is sustained by Coddington v. Dry-Dock Co. 31 N. J. Law, 477, 480, where it is said: “ The act did not intend to give a lien on labor not performed on the land upon which it is to be a lien, nor on lumber before it was made land. . . . As soon as the lumber is converted into land, then, the land is seized by the lien by reason of the building, and *295the building because it is a part of the land; and from thence it follows that if the land and the building, by any chance, become separated, the lien is lost on both,— the land, because it has lost the building and the increased value thereby given to it; and the building, because separated from the land.” Houck, Liens, §§ 203-205; Schukraft v. Ruck, 6 Daly, 1. A different view, however, has been taken of the question by the courts of other states having statutes more or less similar to our own. Freeman v. Carson, 27 Minn. 516; Gaty v. Casey, 15 Ill. 189; Steigleman v. McBride, 17 Ill. 300; Clark & Co. v. Parker, 58 Iowa, 509.

The statute (sec. 3315), as it existed before the amendments thereto noted in S. & B. Ann. Stats, sec. 3315, provided that “ in no case shall the owner be compelled to pay a greater sum for or on account of such house, building, or other improvement than the price or sum stipulated in the original contract or agreement.” It was then amended (ch. 312, Laws of 1885, and ch. 535, Laws of 1887) so that if the price shall be fixed unnecessarily low, with intent to defraud subcontractors, the basis of the owner’s liability shall be a fair price for the labor and materials used in the building, instead of the contract price. The next enactment (ch. 333, Laws of 1889) repealed the above restriction upon the liability of the owner, and makes him absolutely liable to such contractors as comply with the requirements of the law, for the amount of their claims, without regard to the contact price of the building or the sum the owner may be indebted to the contractor when' notice of the subcontractor’s claim for a lien is served, or at any other time. Hall v. Banks, 79 Wis. 233; Mallory v. La Crosse Abattoir Co. 80 Wis. 174, 175. The operation of the amendment of 1889 seems to be confined to the question of the amount for which a subcontractor, material man, or laborer under him may have a lien against the building and premises of the *296owner, and does not in any manner affect the question as to what may or may not wholly defeat or deprive him of any lien at all.

As already observed, it is very clear that the principal contractors in this case would not be entitled to recover or have a lien by reason of the partial construction of the building destroyed, and if the case is such that the principal contractor is not entitled to a lien for any other reason than that he has been paid in full, as in case of abandonment of his contract or of destruction of the building before completion, the subcontractors under him, and their material men and laborers, would not seem to be entitled to any lien. The law was so held in Malbon v. Birney, 11 Wis. 107, 110, where it was held that one who had furnished lumber to a principal contractor, which he had used in the construction of the building, and had voluntarily abandoned his work, could not recover against the owner as a subcontractor under such principal contractor by virtue of the lien law, and it was said that “ if Kennedy [the contractor] could not have recovered on a quantum meruit for his labor and on a quantum valebant for the materials, the respondents [the material men] ought not to sustain this action.” And it seems clear that the rule must be the same where the building has been wholly destroyed before completion. That the rule in Malbon v. Birney, supra, has not been affected by the amendment by ch. 333, Laws of 1889, of sec. 3315, R. S., seems obvious from an inspection of its language, making it the duty of the principal contractor to defend any action brought to enforce a lien by any subcontractor or material man or laborer under him at his own expense, and that “during the pendency of such action the owner may withhold from the contractor the amount of money for which such lien shall be filed, and in case of judgment against the owner or his property upon the lien, he shall be entitled to deduct from any *297amount clue from him to the contractor the amount of such judgment and cósts, and if he shall have settled with the contractor in full, shall be entitled to recover back from the principal contractor any amount so paid by the owner for which the principal contractor was originally liable.” The provision in question is plainly restricted to a case such as was before the court in Mallory v. La Crosse Abattoir Co. 80 Wis. 170, where the building had been completed, and where the controversy was as to the liability of the owner to pay, through his property, the sums due from the principal contractor to his subcontractors, material men, or laborers, although in excess of the contract price for erecting the building. Its entire scope is restricted to allowing the owner to deduct from the contract price due and unpaid by him to his contractor the amount of the judgment and costs recovered against' the latter, and, if he shall have settled wTith the contractor in full, he is allowed to recover back from the principal contractor any amount so paid by him, for which such principal contractor was originally liable. We hold, therefore, that by reason of the destruction of the first building before completion the several claimants plaintiffs who are material men and laborers are not entitled to liens on the lots for materials or for work and labor used and expended on such building; that those who furnished materials and performed work and labor on the second building are entitled to liens therefor on that building, and upon the right, title, and interest of the owner, Baerlooher, therein.

2. There is no preponderance of evidence against the finding of the court adverse to the defense set up by the appellant to the claim of Noyes & Co., and hence there is no ground for disturbing the finding on that subject.

3. The objection that the claim of Noyes & Co. for a lien was not seasonably filed is, we think, untenable. It was delivered in due form to the proper officer to be filed. His *298failure to put his file mark on it and to make the docket entries on the docket of mechanics’ liens within the prescribed six months for filing liens, will not defeat the claim. The statute provides for both filmg and docketing the claim, and these are entirely different things. The law requires the party to file his claim for a lien, and the clerk is to docket it. R. S. secs. 3318, 3319. And sec. 3321 is that “ any person having so filed such claim,” etc. The rights of the claimant to a lien are secured when his claim therefor is delivered to and left with the clerk to be filed. The statute requires him to file it and to docket it. The first part of the section provides that within six months, etc., it “ shall be filed as herevnafter provided,” and in the latter part that “such claim for lien may be filed and docketed within such six months, notwithstanding the death of the owner of the property affected by it,” etc.; and this is the “hereinafter provided,” and satisfies the previous requirement of the section, for there is no other provision in the statute to which it can possibly apply. It certainly does not refer to docketing the claim. When the claimant has delivered his claim for a lien to the clerk and left it with him to be filed, he has done all he is required to do — all he possibly can do — to secure his rights, and he will not be prejudiced by the neglect of the clerk to perform in respect to it his duty as directed by the statute. Docketing the claim is not a prerequisite to securing the lien. Smith v. Waggoner, 50 Wis. 155; Gorham v. Summers, 25 Minn. 81; People v. Bristol, 35 Mich. 28; Bishop v. Cook, 13 Barb. 329; Dodge v. Potter, 18 Barb. 193.

By the Qou/rt.— The judgment of the circuit court is reversed, and the cause remanded with directions to enter judgment according to this opinion.

midpage