Evelyn GONZALEZ, Administratrix of the Estate of Candido Gonzalez, Deceased, Appellant, at No. 239, v. UNITED STATES STEEL CORPORATION, a corporation, Appellant at No. 241, v. EDWARD GRAY CORPORATION. Vincent CARDILLO, Appellant at No. 240, v. UNITED STATES STEEL CORPORATION, a corporation, Appellant at No. 242, v. EDWARD GRAY CORPORATION.
No. 239, 241, 240, 242
Supreme Court of Pennsylvania
March 16, 1979
398 A.2d 1378 | 484 Pa. 277
Argued May 25, 1978.
Paul A. Manion, Reed, Smith, Shaw & McClay, Pittsburgh, for appellees at Nos. 239 & 240 and appellant at Nos. 241 & 242.
Before EAGEN, C. J., and O‘BRIEN, ROBERTS, POMEROY, NIX, and MANDERINO, JJ.
OPINION OF THE COURT
ROBERTS, Justice.
Cases involving less than two of the exceptions to the general rule that “the employer of an independent contractor is not liable for physical harm caused to another by an
I. Background
United States Steel Corporation hired an independent contractor, Edward Gray Corporation, to “tear out” deteriorating bricks inside the Number 4 blast furnace at U.S. Steel‘s Duquesne plant. One Gray employee, Vincent Cardillo, was injured and another Gray employee, Candido Gonzalez, was killed in an accident on the job site. Cardillo and the administratrix of the estate of Gonzalez filed separate complaints against U.S. Steel in the Court of Common Pleas of Allegheny County. Cardillo alleged U.S. Steel‘s negligence caused his injury, and the administratrix claimed U.S. Steel‘s negligence caused Gonzalez‘s death. U.S. Steel denied each plaintiff‘s allegations of negligence and joined Gray as an additional defendant in each case. The court of common pleas consolidated the cases and the parties presented their evidence to a jury. The jury returned verdicts in favor of plaintiffs, and against both U.S. Steel and Gray. The court of common pleas denied U.S. Steel‘s motions for judgment notwithstanding the verdicts and for a new trial. (Gray did not challenge the jury‘s verdicts.) U.S. Steel appealed to the Superior Court. The Superior Court unanimously upheld the denial of U.S. Steel‘s motions for judgment n. o. v., and a majority granted U.S. Steel a new trial. Both U.S. Steel and plaintiffs petitioned for allowance of appeal, and this Court granted both petitions.2
The Duquesne plant‘s Number 4 blast furnace has four stoves as components. Each stove is approximately 110 feet high and cylindrical. Inside each stove are two adjacent vertical chambers of different widths. The wider of the
U.S. Steel hired Gray to tear out, from the Number 4 blast furnace stoves, “approximately ten feet” of deteriorating checker bricks at the top of each checker chamber and twenty feet of deteriorating skimwall at the bottom of each well. Gray specialized in brick removal and was not hired to install new bricks. U.S. Steel and Gray signed a contract supplied by U.S. Steel which contains a printed provision that “[t]he safety of all persons employed by contractor shall be the sole responsibility of contractor” and a provision that “[c]ontractor shall take all reasonable measures and precautions at all times to prevent injuries to or the death of any of his employees . . . .” The contract incorporates several sets of “owner‘s specifications.” One set includes a typed clause stating that “[t]he contractor shall provide and maintain all required barricades, planks, handrails, lanterns, warning signs and everything necessary for the safe and proper conduct of the work and for the protection of all equipment, property, Contractor‘s employees, Purchaser‘s employees and all other equipment.” Another set contains a typed clause stating that “[c]ontractor shall equip work covered by this contract with all proper safety devices for the protection of workmen . . . .”
U.S. Steel shut down the furnace and Gray began work on the stoves. In the Number 3 stove, as in the others, Gray first tore out checker bricks from the top of the chamber and then threw the bricks into the adjacent well. Discarded bricks accumulated at the bottom of the well. Gray workers entered the well through a hatch and carted out the discarded bricks. Gray removed approximately ten feet of bricks from the top of the checker chamber of the Number 3 stove. It then shifted its efforts to the skimwall at the bottom of the well. Before removing any skimwall, Gray installed scaffolding to support skimwall that would not be removed. Gray then removed about twenty feet of skimwall.
After Pittsburgh Pipe rodded the remaining checker bricks in the Number 3 stove, it was determined that Gray would have to remove more checker bricks. In order to remove more checker bricks at this stage of the work, an eighty foot wooden chute was installed in the well to funnel discarded checker bricks away from both remaining skimwall and its temporary supporting structure. U.S. Steel directed Gray “as to the amount of checker bricks to be torn out of the No. 3 stove after the initial ten feet of checker bricks had been torn out.”4 As Gray removed the additional bricks, torn out bricks accumulated at the bottom of the well, causing the bottom of the eighty foot chute to become embedded in checker bricks.
To permit additional accumulation of discarded checker brick, Gray ordered its employees to dismantle the bottom portion of the chute. Cardillo and Gonzalez entered the well to do so. They partially dismantled the bottom portion of the chute and discovered that the upper portion of the chute was clogged with discarded bricks. The chute collapsed, killing Gonzalez and injuring Cardillo.
Plaintiffs presented evidence in support of two theories of liability under the
“is concerned with special risks, peculiar to the work to be done, and arising out of its character, or out of the place where it is to be done, against which a reasonable man would recognize the necessity of taking special precautions. The situation is one in which a risk is created which is not a normal, routine matter of customary human activity, such as driving an automobile, but is rather a special danger to those in the vicinity, arising out of the particular situation created, and calling for special precautions. ‘Peculiar’ does not mean that the risk must be one which is abnormal to the type of work done or that it must be an abnormally great risk. It has reference only
to a special, recognizable danger arising out of the work itself.”
The court of common pleas denied U.S. Steel‘s motion for a directed verdict and charged the jury on
On its appeal, U.S. Steel again seeks judgment notwithstanding the verdicts. Plaintiffs, on their appeal, argue that their verdicts against U.S. Steel should be reinstated. We disagree with each claim, and are of the view that the Superior Court correctly granted U.S. Steel a new trial.
II. Motion for Judgment N.O.V.
U.S. Steel contests its liability to plaintiffs under
Plaintiffs introduced expert evidence that tear out work in a checker chamber normally is completed before tear out work is begun in a stove well. These experts contended that this procedure is designed to avoid the possibility that discarded checker bricks will cause the temporarily supported skimwall to collapse. Plaintiffs presented testimony to establish that U.S. Steel was familiar with this normal proce-
In assessing U.S. Steel‘s claim that judgment notwithstanding the verdicts should have been granted, this Court must, of course, give plaintiffs, as winners of jury verdicts, “the benefit of every fact and inference of fact which may be reasonably deduced from the evidence.” Evans v. Philadelphia Transportation Co., 418 Pa. 567, 571, 212 A.2d 440, 442 (1965). A view of the record from this perspective compels the conclusion that U.S. Steel‘s argument must be rejected. The jury, on either of two views of the evidence, may have reasonably concluded under the proper charge of the court that
From plaintiffs’ evidence, the jury could determine that U.S. Steel was familiar with standard tear out procedure, that at the time U.S. Steel ordered Gray to remove additional checker bricks U.S. Steel knew Gray had removed some skimwall and remaining skimwall was temporarily supported by scaffolding, and that Gray had not been hired to replace removed bricks. The jury could decide that U.S. Steel knew, or should have known, that implementation of its order to remove additional checker bricks would require Gray to depart from standard tear out procedure. Based on the testimony that a special metal chute used to facilitate removal of checker brick had clogged previously, the jury could reasonably conclude that U.S. Steel knew or should have known that the additional work would necessitate use of another special chute, and that this chute, like the other,
The court charged the jury that U.S. Steel‘s actionable “orders or directions may be given at the beginning of the contract,” and the rule of
“[W]here the cause is submitted to the jury on two issues, on one of which the defendant had the right to binding instructions, and on other of which he had not, and the verdict of jury may involve a finding against the defendant on first issue, or on the second, or on both, the verdict will be set aside and a new trial granted.” 6A Standard Pennsylvania Practice Ch. 28 § 74 (1960). We have concluded that plaintiffs’ general verdict properly may have been based upon liability under the court‘s charge on
III. Motion for New Trial
The court of common pleas concluded that U.S. Steel did not satisfy its duty under
Under
To decide whether Gray and U.S. Steel indeed anticipated possible use of a chute at the time of contract formation, we look to the contract. At the outset, it must be observed that whether the contracting parties, at the time of contract formation, anticipated possible use of a chute is ordinarily a question for the trial court. “For a variety of reasons the common law has long thought it best to leave to the court rather than to the jury the essentially factual question of what the contracting parties intended.” Community College of Beaver County v. Society of the Faculty, 473 Pa. 576, 592, 375 A.2d 1267, 1275 (1977). The common law rule “contributes to the stability and predictability of contractual relations” and “provides a method of assuring that like cases will be decided alike.” Restatement (Second) of Contracts § 238 Comment d (Tent. Draft No. 5, March, 1970).
At the same time, however, “[a] question of interpretation of an integrated agreement is to be determined by the trier of fact if it depends on the credibility of extrinsic evidence or on a choice among reasonable inferences to be
If the jury were to determine that Gray and U.S. Steel, at contract formation, anticipated possible use of a chute, U.S. Steel‘s obligation under
Though the Gray-U.S. Steel contract shifts to Gray those risks anticipated at the time of contract formation and the record would support a jury conclusion that Gray and U.S. Steel anticipated Gray‘s use of a chute at that time, the charge of the court improperly foreclosed a permissible jury verdict that U.S. Steel is not liable under
The order of the Superior Court, sustaining the trial court‘s denial of U.S. Steel‘s motion for judgment n. o. v., and reversing the trial court‘s denial of U.S. Steel‘s motion for a new trial, is affirmed.
POMEROY, former J., did not participate in the decision of this case.
LARSEN, J., did not participate in the consideration or decision of this case.
NIX, J., filed a dissenting opinion and would direct the trial court to grant U.S. Steel judgment n. o. v.
MANDERINO, J., filed a dissenting opinion and would direct the trial court to reinstate plaintiffs’ verdicts.
NIX, Justice, dissenting.
This appeal stems from an accident that occurred on December 16, 1970, at a plant of the United States Steel Corporation, (USS). A suit for personal injury was instituted by appellant, Vincent Cardillo, and an action for wrongful death was brought by the Administratrix of the estate of Candido Gonzalez, deceased. The accident occurred during the performance of a contract entered into between Edward
The accident occurred when a wooden chute built by Gray‘s employees, Gonzalez and Cardillo, collapsed upon them. The chute facilitated the removal of checker brick debris thrown down the checker chamber into the well and protected the scaffolding supporting the portions of the skimwall that had not been torn out. As a result of the injuries sustained, Gonzalez died and Cardillo suffered serious injury. The suits against USS for personal injury were consolidated for trial and Gray was joined by USS as an additional defendant.
Gonzalez and Cardillo sought to impose liability on USS based on the exceptions to the general rule that one employing an independent contractor is not liable for torts committed by the contractor contained in sections 410, 413, 416 and 427 of the
Section 410. Contractor‘s Conduct in Obedience to Employer‘s Directions
The employer of an independent contractor is subject to the same liability for physical harm caused by an act or omission committed by the contractor pursuant to orders or directions negligently given by the employer, as though the act or omission were that of the employer himself.
From the comments to
This concept is not new to the law of this jurisdiction. The general rule provides that one who employs an independent contractor, who is qualified to perform the task, is not responsible for the negligence of the contractor or his employes provided the employer does not personally interfere or assume direction of the work. Heindenway v. Philadelphia, 168 Pa. 72, 31 A. 1063 (1895). See also Fuller v. Palazzolo, 329 Pa. 93, 197 A. 225 (1938); Silveus v. Gross- man, 307 Pa. 272, 161 A. 362 (1932). However, where the employer controlled the means of conducting and performing the work, our decisions have found a master-servant relationship and has been willing to impose liability. Thus the incident of responsibility is affected by the interference of the employer in the contractor‘s execution of the contract. Heindenway v. Philadelphia, supra. The Superior Court, relying upon these principles, held an employer liable because he instructed an independent contractor to erect a sign on a windy day. Weldon v. Steiner, 138 Pa.Super. 66, 10 A.2d 19 (1939). Similarly, in Lasch v. Cohn, 130 Pa.Super. 161, 196 A. 581 (1938), that court held an employer responsible for damages caused by the bursting of a water-back installed, pursuant to the employer‘s instructions, by an independent contractor.
The basic law does not appear to be at issue in this lawsuit, but rather the dispute appears to center around its application to the facts of this case. The dispute focuses upon whether there was interference by the employer in the performance of the terms of the contract by the contractor which created the unreasonable risk of harm. To resolve the dispute it must be determined whether the testimony provided a basis for a finding that there was some order or direction of the employer beyond “[the] general right of inspection and supervision that an owner normally enjoys and exercises to insure his receiving from the contractor the benefit of total performance bargained for.” Fisher v. United States, 441 F.2d 1288 (3rd Cir. 1971). The alleged negligent order of USS upon which liability under
In assessing a motion for judgment n. o. v., we are required to consider the evidence and all reasonable inferences that can be drawn from that evidence in the light most favorable to the verdict winner. Sorrentino v. Graziano, 341 Pa. 113, 17 A.2d 373 (1941). Relying upon this standard of review, the testimony established that the terms of the contract required Gray to remove bricks from the
The record indicates that it was Gray‘s idea to use the wooden chute, and that USS did not give Gray any directions whatsoever regarding the chute. Although USS did rig the chute into place, USS was contractually obligated to furnish a crane to perform rigging operations at Gray‘s behest. No negligence is alleged with respect to the installation of that equipment and it cannot be contended that the fulfillment of a contractual obligation at Gray‘s request evidences USS‘s control over the mode and manner through which Gray sought to achieve the bargained for results of its work. Pennsylvania decisions have generally refused to impose liability upon the employer of an independent contractor for injuries sustained by the independent contractor‘s employes when the injury neither resulted from lack of safety in the premises under the control of the employer-landowner nor from concealed defects in these premises. See, Crane v. ITE Circuit Breaker, 443 Pa. 442, 278 A.2d 362 (1971); Funari v. Valentino, 435 Pa. 363, 257 A.2d 259 (1969). Even then, fault based liability cannot be imposed on the
The other prong of
c. Meaning of “negligently given” orders or directions. The words “negligently given” are used to denote the fact that the employer knows or should know that the work which is to be done, pursuant to his orders and directions, involves an unreasonable risk of causing physical harm to others. Therefore, the orders and directions are not negligently given if the employer neither knows nor should know that the work involves such risk even though the contractor discovers during the progress of the work that such risks will be involved in following the orders and directions. In such a case, the contractor alone is negli-
gent in following his employer‘s orders and directions unless he has informed the employer of the risk which has now become appreciable. The employer is not liable unless, having been informed of the risk which the contractor has discovered, he requires the contractor to carry out his original orders and directions, or issues new orders and directions which a reasonable man would not regard as adequate to eliminate the risk involved in following the original orders. Restatement (Second) of Torts, comment to § 410 (emphasis added).
There is no testimony in the record either that Gray told USS of any increased dangers or that USS had any other basis for knowing of any such dangers.
The opinion of the court states that the jury would infer “that USS was negligent in requesting removal of additional bricks at a time when such removal would require Gray to depart from standard procedure and USS was responsible for the creation of circumstances rendering tear-out work dangerous in itself.” The fallacy in the court‘s reasoning turns on its assumption that, absent express knowledge of the danger or actual control of the operation of the independent contractor, the employer of an independent contractor has a duty to supervise the ongoing details of the contractor‘s performance of the contract under
Again, it should be borne in mind that we are not dealing in the instant case with nondelegable duties of the employer of an independent contractor under
Finally, Gonzalez and Cardillo cannot recover under
These observations concerning
Accordingly, I must respectfully dissent from the majority‘s disposition of the case, which should have been resolved by the grant of a judgment n. o. v. in favor of the United States Steel Corporation on all issues properly presented for appeal in this case.
MANDERINO, Justice, dissenting.
I dissent. The order of the Superior Court should be vacated and the order of the trial court affirmed. See
Notes
Except as stated in §§ 410–429, the employer of an independent contractor is not liable for physical harm caused to another by an act or omission of the contractor or his servants.
Restatement (Second) of Torts § 409 (1965).
The employer of an independent contractor is subject to the same liability for physical harm caused by an act or omission committed by the contractor pursuant to orders or directions negligently given by the employer, as though the act or omission were that of the employer himself.
One who employs an independent contractor to do work which the employer should recognize as likely to create during its progress, a peculiar unreasonable risk of physical harm to others unless special precautions are taken, is subject to liability for physical harm caused to them by the absence of such precautions if the employer
(a) fails to provide in the contract that the contractor shall take such precautions, or
(b) fails to exercise reasonable care to provide in some other manner for the taking of such precautions.
Id.
The safety of all persons employed by Contractor and his subcontractors on Owner‘s premises, or any other person who enters upon Owner‘s premises for reasons relating to this contract, shall be the sole responsibility of Contractor. Contractor shall at all times maintain good order among his employees and shall not employ on the work any unfit person or anyone not skilled in the work assigned to him. Contractor shall confine his employees and all other persons who come onto Owner‘s premises at Contractor‘s request or for reasons relating to this contract and his equipment to that portion of Owner‘s premises where the work under this contract is to be performed or to roads leading to and from such work sites, and to any other area which Owner may permit Contractor to use.
Contractor shall take all reasonable measures and precautions at all times to prevent injuries to or the death of any of his employees or any other person who enters upon Owner‘s premises. Such measures and precautions shall include, but shall not be limited to, all safeguards and warnings necessary to protect workmen and others against any conditions on Owner‘s premises which could be dangerous and to prevent accidents of any kind whenever work is being performed in proximity to any moving or operating machinery, equipment or facilities, whether such machinery, equipment or facilities are the property of or are being operated by, the Contractor, his subcontractors, the Owner or other persons.
It is understood that if employees of Owner shall perform any acts for the purpose of discharging the responsibility undertaken by the Contractor in this Article 16, whether requested to perform such acts by the Contractor or not, such employees of the Owner while performing such acts shall be considered the agents and servants of the Contractor subject to the exclusive control of the Contractor.
“Contractor‘s Conduct in Obedience to Employer‘s Directions
The employer of an independent contractor is subject to the same liability for physical harm caused by an act or omission committed by the contractor pursuant to orders or directions negligently given by the employer, as though the act or omission were that of the employer himself.”
“Duty to Provide for Taking of Precautions Against Dangers Involved in Work Entrusted to Contractor
One who employs an independent contractor to do work which the employer should recognize as likely to create, during its progress, a peculiar unreasonable risk of physical harm to others unless special precautions are taken, is subject to liability for physical harm caused to them by the absence of such precautions if the employer
(a) fails to provide in the contract that the contractor shall take such precautions, or
(b) fails to exercise reasonable care to provide in some other manner for the taking of such precautions.”
