In this appeal, we consider (1) whether a civil action to enforce a mechanic’s hen may be filed as a counterclaim in the property owner’s action to discharge that same hen, and (2) if so, whether such a counterclaim relates back to the filing date of the property owner’s complaint for purposes of determining whether the hen enforcement action was timely commenced. See G. L. c. 254, §§ 5, 11, 15A; G. L. c. 260, § 36. The plaintiff owner, Sandra K. Golden, filed an action to discharge the defendant’s hen pursuant to G. L. c. 254, § 15A (b) and (c). The defendant, General Builders Supply LLC (General Builders), sought to enforce its mechanic’s lien by way of a counterclaim filed four weeks after the deadline set forth in
1. Background. In the fall of 2000, Golden and her husband hired a contractor to construct an addition on their home in Quincy. Over the course of the project, General Builders delivered supplies and materials to the site pursuant to an alleged written subcontract with the contractor, but received only partial payment from the contractor. On April 25, 2001, General Builders recorded a notice of contract with the Norfolk County registry of deeds, see G. L. c. 254, § 4, and on May 29, 2001, General Builders recorded a document entitled “Statement of Lien,” claiming that it was owed $15,220.59 for the materials furnished to Golden’s property, see G. L. c. 254, § 8.
The deadhne for General Builders to commence an action to enforce its hen was August 27, 2001 (ninety days from the May 29, 2001, recording of the statement of account). G. L. c. 254, § 11. No enforcement action was filed prior to the expiration of
2. Discussion, a. Counterclaim to enforce a mechanic’s lien. Golden contends that an action to enforce a mechanic’s Hen may only be brought by way of an original complaint, not by means of a counterclaim. She relies on the statute’s requirements that the “plaintiff shall bring his action” to enforce the Hen, that the Hen be dissolved “unless a civil action to enforce it is commenced,” and that a copy of “the complaint” be recorded in the registry of deeds “within thirty days of the commencement of the action,” contending that those words in the mechanic’s Hen statute must be literally interpreted to preclude a lien enforcement action by way of any procedural device other than an action “commenced” by original complaint brought by the contractor as plaintiff. See G. L. c. 254, § 5. See also G. L. c. 254, § 11; Mass. R. Civ. R 3, as amended,
Because a mechanic’s Hen is purely a creation of statute, we have consistently required exact comphance with the statute in order to create, perfect, and enforce such a Hen. See Ng Bros. Constr. v. Cranney,
The rules liberally allow a party to “state as a counterclaim any claim against an opposing party” (emphasis added). Mass. R. Civ. P. 13 (b),
Notwithstanding that straightforward conclusion under the
Nor would the filing of a contractor’s or subcontractor’s counterclaim prevent the prompt determination of the owner’s claim of entitlement to discharge of the hen. By definition, the lien cannot be enforced if it is invalid or defective, and the judge would presumably rule on those claimed defects “expeditiously,” as required by G. L. c. 254, § 15A, before proceeding with any enforcement of the lien pursuant to the counterclaim. The types of defects that can result in an order “summarily
We thus see no conflict between rule 13 (b) and the mechanic’s hen statute that would convince us to suspend the operation of rule 13 (b) for proceedings involving mechanic’s
b. Relation back. Because General Builders’s counterclaim seeking to enforce its lien was not filed until after the expiration of the ninety-day time period in which to bring such an enforcement action, see G. L. c. 254, § 11, General Builders invokes the doctrine of “relation back” articulated in G. L. c. 260, § 36,
Application of the relation back doctrine to salvage untimely filed counterclaims for lien enforcement would be contrary to the terms of the mechanic’s lien statute and would seriously undermine its operation. The statute does not simply set a limitations period for the filing of lien enforcement actions, but specifies the consequence of failing to bring an action within that time frame: “The lien shall be dissolved unless a civil action to enforce it is commenced within ninety days after the filing of the statement [of account]” (emphasis added). G. L. c. 254,
Once the August 27 deadhne had come and gone with no action filed by General Builders, Golden was automatically entitled to the rehef she sought in her complaint. At that juncture, it required no further action on Golden’s part (or even any action by the court) to “discharge” the hen, as the hen had already “dissolved.” It would be perverse to tell Golden that she could now be denied the rehef to which she was previously entitled because, before the judge ruled on her request for rehef, the very pendency of her request gave General Builders an opportunity to resurrect its hen by filing a counterclaim.
Allowing resurrection of the hen by the filing of a counterclaim after expiration of the ninety-day period would also wreak havoc with one of the statute’s important purposes, namely, the provision of “an accurate system for recording and identifying encumbrances secured under the mechanic’s hen statute.” National Lumber Co. v. LeFrancois Constr. Corp., supra at 669. The statute is intended to ensure “that an enforcement action may readily be identified through routine title searching procedures,” id., and it accomplishes that objective by requiring that an attested copy of the enforcement complaint be recorded
Where, as here, application of the otherwise customary roles of relation back would compromise one of the objectives of a
We therefore decline to apply G. L. c. 260, § 36, to General Builders’s counterclaim, and will instead require that any counterclaims to enforce mechanic’s liens be filed with the court and recorded at the registry of deeds within the time frames mandated by G. L. c. 254, §§ 5 and 11. Because General Builders failed to file its counterclaim within the ninety-day period prescribed by G. L. c. 254, § 11, its hen was dissolved. As such, the judge properly ordered the lien discharged and dismissed General Builders’s counterclaim.
Judgment affirmed.
Notes
The statute requires the contractor or subcontractor claiming a lien to file and record “a statement, giving a just and true account of the amount due or to become due him, with all just credits, a brief description of the property, and the names of the owners set forth in the notice of contract.” G. L. c. 254, § 8. Such a statement is customarily referred to as a “statement of account,” see G. L. c. 254, § 15A (b); Tremont Tower Condominium, LLC v. George B.H. Macomber Co.,
The lien itself may only be enforced against the property by way of sale, G. L. c. 254, § 18, but an action to enforce the lien is nevertheless “commenced and prosecuted against” the owner. See G. L. c. 254, § 23.
Although the issue is not before us in the present appeal, it may well be that a mechanic’s lien enforcement action would qualify as a compulsory counterclaim that must be asserted in the property owner’s action seeking to discharge that same lien. See Mass. R. Civ. R 13 (a), as amended,
By comparison, we found such a conflict between the statute governing summary process actions and the rules of procedure that would otherwise have given commercial tenants the right to bring counterclaims against their landlords. Fafard v. Lincoln Pharmacy of Milford, Inc.,
The statute provides in pertinent part: “The provisions of law relative to limitations of actions shall apply to a counterclaim by the defendant. The time of such limitation shall be computed as if an action had been commenced therefor at the time the plaintiff’s action commenced.” G. L. c. 260, § 36.
Here, the judgment dismissing the counterclaim already had been entered prior to the expiration of the thirty-day period in which to file and record an attested copy at the registry of deeds. The record before us therefore does not reveal whether or when any copy was ever filed and recorded at the registry.
The statute does not require the property owner to record anything at the registry with respect to an action to dissolve a mechanic’s lien under G. L. c. 254, § 15A, nor is there a recording requirement for the other- causes of action that an owner might ordinarily bring against a contractor or subcontractor (e.g., breach of contract or negligence). As such, there would be nothing on record to alert a title examiner to the fact that a property owner’s own suit might have opened the door to a later counterclaim to enforce the mechanic’s lien.
By comparison, in National Lumber Co. v. LeFrancois Constr. Corp.,
Because our ruling on the relation back issue renders the lien enforcement counterclaim untimely, it is not necessary for us to address any of the other grounds on which Golden sought to have the lien discharged.
