GMMM Westover LLC v. New York State Electric & Gas Corp.GMMM Westover LLC v. New York State Electric & Gas Corp.
GMMM WESTOVER LLC, Respondent, v NEW YORK STATE ELECTRIC AND GAS CORPORATION, Appellant.
Calendar Date: September 8, 2017
Before: McCarthy, J.P., Egan Jr., Lynch, Devine and Pritzker, JJ.
Nixon Peabody LLP, Rochester (Christopher D. Thomas of counsel), for appellant.
Goldberg Segalla LLP, Syracuse (James M. Paulino II of counsel), for respondent.
Egan Jr., J.
MEMORANDUM AND ORDER
Appeals (1) from an order of the Supreme Court (Tait, J.), entered June 14, 2016 in Broome County, which, among other things, partially granted plaintiff‘s motion for summary judgment, and (2) from an order of said court, entered December 6, 2016 in Broome County, which, upon reargument, among other things, modified a prior order.
Defendant is a public utility corporation that provides gas and electric services within New York. Defendant previously owned and operated several power generating facilities throughout the state, including, as relevant here, the Westover Plant,1 located in the Village of Johnson City, Broome County. As a result of New York‘s mandated deregulation of the electricity industry in the late-1990s, defendant was prohibited from owning and operating transmission and distribution facilities while concomitantly owning and operating power generating facilities. Accordingly, in 1998, defendant sold the Westover Plant and associated property (hereinafter the site) to AES Eastern Energy, L.P. Notably, the sale did not include certain real property and assets located adjacent to the actual Westover Power Plant Building (hereinafter the Power Plant), including two reserved parcels related to defendant‘s transmission and distribution
In 2011, AES filed for bankruptcy. As part of the bankruptcy proceedings, the Power Plant was to be sold to plaintiff, who indicated that it intended to salvage or scrap the equipment and demolish the plant for potential redevelopment. Because defendant still owned and operated its transmission facilities — which remained intertwined with the Power Plant — in May 2012, Bankruptcy Court approved a settlement agreement between AES and defendant that, among other things, ensured that defendant would have continued access to and use of these transmission facilities until such time as it could separate them from the Power Plant (hereinafter referred to as the separation project). Thereafter, in October 2012, Bankruptcy Court approved an asset purchase agreement between plaintiff and AES with respect to the site and, in December 2012, an assignment and assumption agreement, wherein plaintiff agreed to assume certain duties and responsibilities pursuant to the settlement agreement between AES and defendant.
Subsequently, a dispute arose between the parties with respect to the project completion date for the separation project. The parties’ attempts to settle the dispute proved unsuccessful, and, when the separation project was not completed by the purported October 14, 2014 project completion date, plaintiff served defendant with a notice to quit the premises. Plaintiff thereafter commenced a proceeding by order to show cause and petition, which, among other things, set forth
In June 2016, Supreme Court partially granted plaintiff‘s motion to dismiss by dismissing defendant‘s first, third and fourth counterclaims and granted plaintiff summary judgment on its ejectment cause of action3. In granting the latter, Supreme Court used language that could be interpreted as ejecting defendant from the entire site — i.e., both the Power Plant and its adjacent reserved parcels. Defendant thereafter moved to reargue and/or clarify Supreme Court‘s June 2016 order, specifically requesting clarification on whether (1) the REA was still in force, and (2) what specific property at the site it was required to vacate. In December 2016,
Plaintiff met its initial burden on its motion for summary judgment for its ejectment cause of action by demonstrating that it was the record owner of the Westover Plant, with a present and immediate right to possession, and that defendant continued to occupy portions thereof insofar as it had not completed the separation of its transmission facilities from the Westover Plant (see RPAI Pelham Manor, LLC v Two Twenty Four Enters., LLC, 144 AD3d 1125, 1126 [2016]; Merkos L‘Inyonei Chinuch, Inc. v Sharf, 59 AD3d 408, 410 [2009])6. The burden, therefore, shifted to defendant to demonstrate the existence of a triable issue of fact; namely, that it remained lawfully on the premises.
In opposition, defendant failed to raise a triable issue of fact. Defendant failed to timely sever its transmission system from the Power Plant by the stated project completion date. In determining whether the project completion date — as provided for in the May 2012 settlement agreement — was intended to be the actual date that the separation project was to be completed, we recognize the well-settled principle that “a written agreement that is complete, clear and unambiguous on its face must be enforced according to the plain meaning of its terms” (Matter of Olszewski v Cannon Point Assn., Inc., 148 AD3d 1306, 1309 [2017]). Here, the settlement agreement entered into between AES and defendant governed the separation project and, pursuant to the December 2012 assignment and assumption agreement, such agreement was
Nor do we find that Supreme Court erred in not searching the record and granting defendant summary judgment with respect to the existence of easements to the reserved parcels despite defendant‘s failure to cross-move for such relief (see
Lastly, we do not find that Supreme Court erred in dismissing defendant‘s inverse condemnation counterclaim. “On a motion to dismiss pursuant to
To the extent not specifically addressed herein, the remaining claims have been considered and are either academic or without merit.
McCarthy, J.P., Lynch, Devine and Pritzker, JJ., concur.
ORDERED that the orders are affirmed, with costs.