Globe Light & Heat Co. v. Doud

47 Mo. App. 439 | Mo. Ct. App. | 1892

Lead Opinion

Gill, J.

I. It will be seen that plaintiff framed its petition on two counts — one on the special contract, and the other on quantum meruit. When the evidence was all in, defendants moved the court to require plaintiff to elect upon which count it would proceed and take *446the verdict of the jury. The court overruled this motion, and this action by the court is now assigned as error. The trial judge in this matter was entirely correct. It is well settled in this state that the petition may allege the same cause of action in two counts so as to meet any possible state of the proof. Brinkman v. Hunter, 73 Mo. 178, and cases cited. And in no class of cases is this rule followed so frequently, and so properly, as in the character of cases we here deal with. The wisdom of the rule is here manifest. A may contract with B to furnish certain materials, or do certain work, according to certain defined stipulations. A dispute arises, and A is compelled to sue. He claims a performance of the contract, but B denies. Under the law A is entitled, either to recover on the contract the stipulated price, or if he has contributed certain material to the advantage of B’s property, but has not to the letter complied with the contract, even then A is entitled to recover the value of such materials and work to thfe extent of the benefit conferred on B, limited of course by the contract price. It is entirely proper to present the case in this double form, and permit in one suit a settlement of the entire controversy. A can only recover on one of the two counts, yet there is no reason why he should not be allowed to present his case in the alternative.

II. In the contract for doing the work, as entered into between the plaintiff and the defendant “ Electric Springs Company,” it was provided that said defendants shall pay therefor in throe notes of equal amounts, due respectively in six, twelve, and eighteen months from the completion of the work and bearing eight-percent. interest. Now defendants’ counsel contends that such a provision in the contract amounted to a waiver of plaintiff’s right to a mechanics’ lien. An instruction to that effect was requested, but refused by the court, and this action of court is assigned as error. If, when the work was completed, the.“ Electric Springs *447Company” had given these notes to plaintiff, and plaintiff had accepted the same for, and on account of, its work and materials, then I take it that such would have operated as a waiver of the mechanics’ lien. There would have been, in that event, an extension of time for payment of the work beyond the statutory limitations for beginning suit to enforce a lien which would be inconsistent with such proceedings, and very properly should be construed as a waiver. McMurray v. Taylor, 30 Mo. 263; Ashdown v. Woods, 31 Mo. 465; Gorman v. Sagner, 22 Mo. 137. But, however this may be, “all the cases agree that there will'be no waiver when the agreement to give the note or other security has not been performed by the promisor. It would be going too far to say that the builder must have intended to waive the lien in the event of the refusal to comply with the agreement.” Phillips on Mech. Liens [2 Ed.] sec. 285. This is a complete answer to the position contended for in this case. The defendants contracting to give the note refused to comply with their agreement in this particular, and it will not be understood as plaintiff’s intention to wraive the right to a lien, whether defendants gave or offered to give the note or not. We hold then the point against defendants.

III. The next point we notice is an objection relating to plaintiff’s second instruction, and which was given by the court. That instruction pertains only to the second or quantum meruit count of the petition. The court there substantially declared to the jury, that even though plaintiff did not comply with its contract, did not do the work, etc., in the manner it agreed to, yet if “said defendants used, possessed and enjoyed the same and still have it, in their possession, the jury will find for plaintiff on the second count in the petition,” etc. This instruction is subject to one just criticism. In this character of work, building contracts, if the mechanic fails to do the work as agreed, he cannot recover on quantum menoit on the mere showing thatthe *448owner of the building “possessed, used and enjoyed” his house. He, the owner, could not do otherwise except he abandon his premises, and this he will not be compelled to do. The work and material furnished must not only be used and enjoyed, but must be of real value to the owner over and above the damages resulting from non-compliance by the builder. Yeates v. Ballentine, 56 Mo. 530; Mohney v. Reed, 40 Mo. App. 112.

. Notwithstanding this defect in plaintiff’s second instruction, it was in this instance an error entirely harmless, since the jury did not found their verdict on the second count of the petition, but held the defendants on the first count, deciding that plaintiff did comply with the terms and conditions of the contract.

IV. The last objection we notice is, in the jvords of counsel’s brief, “that the judgment is erroneous in giving the lien against the ground precedence over the prior mortgages held by the Johnson County Savings Bank.” It is sufficient to say in answer to this, that the judgment does not attempt to adjudge or declare any such priority. The judgment neither reaches nor attempts to charge anything except the interest of the owner. The priority of the judgment creditor or incum - brancer is not settled in this instance. The court declined to let the jury pass on this question.

After a careful review of all the questions presented, the most important of which are here noticed, we discover no reason for disturbing the judgment of the circuit court, and the same is therefore affirmed.

All concur.





Rehearing

ON MOTION FOR REHEARING.

Gill, J.

It is contended on this motion for, rehearing that we overlooked a fatal objection made as to the nature of the action, brought by the plaintiff. It is claimed that “the real cause of action was the failure of the defendant company to execute the notes *449specified in the contract, and the form of action should have been for breach of contract, instead of on the contract and quantum meruit.” This position is grounded on the words of the contract as set out in the answer, to the effect that the compensation for plaintiff’s work was to be a certain sum of money, payable as follows : When the work, etc., is completed * * * defendant was to sign and deliver to plaintiff three notes of equal value, each bearing interest at eight per cent, of six, twelve and eighteen months from date of completion of work. It is asserted that this is an action of assumpsit for goods, etc., and that such an action cannot be maintained until the eighteen months have expired, whereas the suit was commenced within a month after the completion of the work.

There is more than one reason why this super-technical argument will not avail here. In the first place the defendants’ answer practically admits the consideration for the work was to be paid in money. In its petition the plaintiff alleges that for the work done, etc., “the said defendants agreed to pay plaintiff the sum of $1,030.” The answer admits “ that for and in consideration of, which these defendants promised to pay the plaintiff the sum of $1,030.”' It is true, however, that, in the subsequent count of the answer in the nature of an alleged counterclaim for dam i ges against plaintiff for alleged defective work, defendants set up the terms of the written contract in which it is stipulated that the work was to be paid for in notes. However, the allegations of the- answer proper make no such charge. The whole tenor and effect of the answer was to declare wherein the- plaintiff had failed to do the work in the manner agreed and provided for in the contract. So then, for this reason alone, the court properly refused defendants’ motion for judgment on the pleadings.

Again, it may be well doubted if counsel’s construction of the contract is the proper one. It seems *450assumed that the contract was for goods and labor furnished on an absolute credit of six, twelve and eighteen months. It was rather a promise of credit on condition that certain securities were furnished by the ■defendant. The $1,030 might have been paid in note signed by the “Electric Springs Company,” but no «credit was provided for unless such securities were given. O'Conner v. Dingley, 26 Cal. 39. By the terms of this .agreement, then, defendants had the right to an extension of time for six, twelve and eighteen months ■ on giving the notes provided for ; but failing and refusing in this, jffaintiff's right of action accrued immediately. Kronenberger v. Binz, 56 Mo. 121. So then we held in the original opinion in this case that there was no extension of time so as to avoid the plaintiff’s right to a mechanics’ lien, because defendants failed and refused to give the notes which were a con- ■ dition for such extension of credit.

But now conceding the effect of this provision in the contract to be as claimed, and that it was a sale of goods on time, is plaintiff denied the right to prosecute this action? In this connection we are cited to numerous cases under the common law, of which Mussen v. Price, 4 East, is the leading, and which last case decides “ where goods were sold upon the contract that the ■ vendee was to pay for them in three months by bill of ■ two months ; that the contract was for a credit of five ■ months, and that the action of assumpsit for goods sold : and delivered could not be brought at the end of three , months upon the neglect of the vendee to give his bill .at two months.” Or as more generally expressed in .another leading case, “ when goods are sold to be paid .for by note or bill payable at a future day, and the mote or bill is not given, the .vendor cannot maintain <msumpsit on the general count for goods sold and 'delivered, until the credit has expired.” Hannas v. Mills, 21 Wend. 92. However, we might as well say .here that all these authorities agree that the vendor *451may, on refusal of the vendee to give the notes, bring his action immediately for a breach of the special agreement. “The right of action,” says Bronson, J., in the case last cited, “is as perfect on a neglect or refusal to' give the note or bill as it can be after the credit has expired. The only difference between suing at the one time or the other relates to the form of the remedy ; in the one case the plaintiff must declare specially, — in the other he may declare generally. The remedy itself is the same in both cases. The damages are the price of the goods.” Now when it is remembered that in the word and spirit of our code we have nothing to do with these old forms of procedure; that we have “but one form of action for the enforcement or protection of private rights, etc., which shall be denominated a civil action;” and that our pleadings (whether petition or answer) shall'be sufficient if they state in a plain and concise manner the facts constituting the cause of action or defense, etc. (R. S. 1879, secs. 3461, 3511, 3321, etc.) we find ourselves relieved of any needed discussion of these intricacies in pleading which served more as pitfalls than as aids to a just administration of the law. It is enough under our system that such facts appear as justify a judgment the one way or the other. We have no concern as to the mere form of the pleading. Kansas City Nat. Bank v. Landis, 34 Mo. App. 440. The facts alleged and proved in this case are under the law sufficient to warrant a recovery. It makes no difference whether it be called an action of assumpsit, or a special action on the contract.

The motion is overruled.