184 A.D.2d 278 | N.Y. App. Div. | 1992
Judgment, Supreme Court, New York County (William J. Davis, J.), entered March 27,1991, which, upon jury verdict, awarded plaintiff Globe Food Services Corp. $636,419, plus interest, costs and disbursements, for a total of $1,081,875.74, unanimously affirmed, with costs.
Plaintiff Globe Food Services Corp. provided food and labor and ran employee cafeterias and executive dining rooms, as well as newspaper stands, vending machines and special functions, at various of defendant Con Edison’s locations for approximately 25 years, until terminated by defendant in the fall of 1984. In the time relevant to this action, the relationship was governed by two successive contracts, the first running from June 1, 1979 through May 31, 1982 and the second from June 1, 1982 through May 31, 1985. Each contract contained an initial list of approved prices that plaintiff was permitted to charge defendant’s employees. While plaintiff could propose price changes, such were subject to defendant’s approval to be given, if warranted, within 45 working days
Defendant also contends, as it did in various motions ultimately denied by the trial court, that the provision of the later contract that "[t]his contract shall replace all prior agreements between Globe and Con Edison” extinguished any claim plaintiff might have for breach of the earlier contract. The trial court properly rejected this contention in the absence of more definitive language such as that contained in contracts held to have such an effect as a matter of law, e.g., " 'a revocation and cancellation of the prior agreement’ ” (Mallad Constr. Corp. v County Fed. Sav. & Loan Assn., 32 NY2d 285, 289 [1973]), " 'supersedes’ ” any prior agreement (Citigifts, Inc. v Pechnik, 112 AD2d 832, 833 [1985], affd 67 NY2d 774 [1986]), " 'in lieu of and shall supersede’ ” any prior agreements (Northville Indus. Corp. v Fort Neck Oil Terms. Corp., 100 AD2d 865, 866 [1984], affd 64 NY2d 930 [1985]). Whether a discharge is effected "depends on the intention of the parties, deduced from the documents and the circumstances of their execution” (Mallad Constr. Corp. v County Fed. Sav. & Loan Assn., 32 NY2d, supra, at 292). Here, both the contract language and the circumstances are ambiguous. At the time the later contract was executed, there was no outstanding dispute concerning the import of the earlier con
We have reviewed defendant’s other arguments and find them to be without merit. Concur — Murphy, P. J., Carro, Ellerin, Asch and Smith, JJ.