Gleason v. United States
33 Ct. Cl. 65 | SCOTUS | 1900
Lead Opinion
The decision of the court below is reversed on the ground that the contractors, if they failed to complete the work within the time limited, had no right to further extension of time, except as approved by the engineer,
delivered the opinion of the Supreme Court January 8, 1900.
Dissenting Opinion
dissented from the construction of the contract on the subject of the power of the engineer officer.