529 A.2d 576 | Pa. Commw. Ct. | 1987
Opinion by
Petitioner Glasgow, Inc. (Glasgow) appeals and Respondent Commonwealth of Pennsylvania, Department of Transportation (Department)' cross-appeals from an order of the Board of Claims (Board). We affirm.
The instant dispute arises out of delays in construction of a portion of L. R. 1016-8A at the interchange between L.R. I016-8A and the Penn Lincoln Parkway (Parkway).
A certain bypass and other temporary structures were necessary to this project for the purpose of routing traffic off the Parkway and onto the bypass during construction. This temporary bypass which enabled Glasgow to perform reconstruction of the Parkway was constructed and used throughout the term of the project.
The two-tiered substructure of S-7944, as originally designed by the Department, included pier footers,
The evidence before the Board revealed the following. After issuing the stop orders regarding pier 1 and pier 2, the Department decided to redesign the substructure for both piers. Glasgow had been, up until the issuance of the stop orders, performing its obligations under the contract in a timely fashion. On or about June 26, 1972, Glasgow received the new design for the piers. However, as a result of the Departments stop orders, redesign, and additional work, the construction of S-7944 was delayed for approximately three months. The delay in completion of S-7944 delayed removal of the bypass which in turn delayed completion of the project as per the terms of the contract. Glasgow, in fts complaint, alleged it suffered damages in the amount of $874,790.50 as a result of the Departments breach of contract. After twenty-three days of hearings, the Board issued an order on January 6, 1986 which concluded that the redesign by the Department was a breach of contract which resulted in $389,645.44 in damages to Glasgow.
The issues presented for our consideration are: (1) whether or not there was substantial evidence to indicate that the redesign of pier 1 and pier 2 resulted in damages to Glasgow; (2) whether or not the Board erred
We are mindful that our scope of review is limited to a determination of whether constitutional rights were violated, an error of law was committed, or whether necessary findings of fact are supported by substantial evidence. Section 704 of the Administrative Agency Law, 2 Pa. C. S. §704; Estate of McGovern v. State Employees’ Retirement Board, 512 Pa. 377, 517 A.2d 523 (1986).
First, we will discuss the Boards award of damages to Glasgow and its utilization of the total cost theory for calculating damages.
Glasgow has proven that the delay in this instance caused a breach of the contract between the parties and as a result thereof Glasgow did sustain certain damages. This proof has been of a sufficient nature to comply with the law of the Commonwealth. . . . The Board, was presented with evidence, both physical and testamentary in nature, that would allow it to find that damages are due to the injured party.
The Board, in concluding that the total cost method was the appropriate theory to be applied in calculating
The Boards calculations with regard to the total cost method are as follows. Glasgows overhead costs incurred as a direct result of the delay in construction were incurred during the year of 1973 and totalled $78,482.46. As to the amount of damages due Glasgow other than overhead costs the Board determined it could not accept the entire amount of delay damages claimed by Glasgow. More specifically, the Board concluded that the damages allegedly incurred for extra work performed could not be included in Glasgows damage calculations. The Board in calculating damages other than overhead did accept as a starting point Glasgows original damage calculation, including extra work, of $874,790.50. Based upon the testimony of the Departments accounting witness, Louis Rubino, the Board determined that extra work constituted 64.43% of the work performed.
The total cost method for calculating damages involves the subtraction of the estimated costs set forth in the contract from actual costs. See E. C. Ernst, Inc. v. Koppers Co., Inc., 626 F.2d 324 (1980) which applied Pennsylvania law involving construction contracts. The Courts, recognizing that the total cost method is subject to speculation, will only utilize this method when there
Glasgow presented extensive testimony regarding the effect of the three month delay, which was contrary to the terms of the contract, on the construction project, and the increased costs it incurred as a result of the delay.
Regarding the Boards exclusion of extra work costs in Department of Transportation v. Acchione and Canuso, 55 Pa. Commonwealth Ct. 65, 423 A.2d 30 (1980), reversed on other grounds, 501 Pa. 337, 461 A.2d 765 (1983), the Court, in denying a contractor recovery for costs incurred in performing additional work, reasoned that where a contractor fails to negotiate for an increase in the amount to be paid for additional work pursuant to the terms of the contract no recovery will be allowed in a subsequent suit brought to collect additional monies. Here, Glasgow, despite specific contract provisions regarding payment for extra and additional work, failed to negotiate for an increase.
With respect to Mr. Rubinos testimony, Glasgow contends that the Boards reliance on Mr. Rubinos estimate that 64.43% of the work performed by Glasgow in 1973 involved extra work was improper because Mr. Rubino testified that he did not want anyone “to apply that percentage [64.43%] to anything”. However, Glasgow has taken this testimony out of context. Mr. Rubino, who testified on behalf of the Department, indicated that Glasgows total estimate of damages of $874,790.50 was inaccurate, but if this amount was to be considered as Glasgows increased costs, then extra work consisted of 64.43% of this amount.
The last issue presented for our consideration is whether or not the Board erred when it held that Glasgows cause of action was not barred by res judicata
Therefore, our independent review of the record in this case constrains us to conclude that the order of the Board must be affirmed.
Order
And Now, this 28th day of July, 1987, the order of the Board of Claims in regard to the above-captioned matters is hereby affirmed.
The Penn Lincoln Parkway connects downtown Pittsburgh with the Airport.
Bridge S-7944 is a two-tiered structure with the lower portion carrying the Parkway over Campbells Run Road and the upper structure carrying ramp B of 1-79 over the Parkway.
The temporary bypass was located north of the Parkway.
Pier footers are the foundation of the bridge.
Pier caps are concrete beams poured into place to receive the structural steel.
It should be noted that the present cause of action was brought on behalf of Glasgow and its paving subcontractor Chapin for damages allegedly suffered by both parties as a result of the Departments breach of contract. However, Chapin does not participate in this appeal.
In order to avoid an unwarranted expenditure of time and space, we will discuss Glasgows and the Departments arguments regarding the total cost theory and the Boards award of damages collectively. We note, however, that we have carefully considered the record evidence regarding each argument presented by counsel for both parties.
Mr. Rubino based his opinion upon the project records.
William Gelbach, Vice-President and General Manager of Glasgow, testified as to the effect the three month delay had on Glasgows work as well as the work of Glasgows subcontractors on the project. Mr. Gelbach also testified that up until the time stop orders were issued, Glasgow was performing within the time constraints set forth in the contract, but that the three month delay resulted in, not only performing the remainder of the project in the less fevorable working months of fall and winter, but also schedul
The contract provides in Section 1.9.2: “Additional and Extra Work—the contractor shall do such additional work ... at the unit price shown in the contract, and in the same manner as if it had been included in the contract. Any work having no quantity and prices included in the contract . . . will be done as extra work, at a price to be agreed upon previously in writing by the contractor and the engineer and approved by the Chief Engineer . . .”.
Mr. Rubino testified in regard to Glasgows utilization of the total cost theory as follows:
Q: To get back to the percentage [64.43%] are you saying that the percentage is not all important in the section of your opinion that I read there?
A: The context with which I said the percentages is not important is that we are not coming up with an amount claimed on adjusted amount claimed. We have cited difficulties and problems with the methodology. Those difficulties and problems exist, they exist whether the percentage is 64% or 44%, okay?
Q: Or 20% or 5%?
A: Or 20% or 5%.
Q: The magnitude differs, doesn’t it?
A: No because what you are doing is you are taking that one segment and saying then, if we were to reconstruct the claim amount based solely on that alone we come up with a different number. That’s not what were saying and that’s not what were doing.
The Bethlehem Steel case is at Board of Claims Docket No. 317.
The Board indicated in its findings of feet that its reason for denying Glasgows motion for consolidation was because of the inadequate time which existed in which to prepare and present the second action (the present case) by the date set for hearing on the first action (the Bethlehem Steel case).