79 W. Va. 167 | W. Va. | 1916
Plaintiffs, a co-partnership, sub-contractors, filed their bill in the court below against The Virginian Railway Company, owner, The Vaughan Construction Company, of Virginia, principal contractor, and The Vaughan Construction Company, of West Virginia, also a sub-contractor, to enforce against the railway company’s property, or that portion thereof covered by their contract, their lien for the work and labor performed and machinery and supplies furnished, in the construction, including grading, of a second track, and for additional tracks in the yard of said railway company at Elmore, and for all work done for said company, between Mullens and Bud on the main line, and between Mullens and Tams on the Winding Gulf branch of said railway company, pursuant to their sub-contract with The Vaughan Construction Company, of Virginia, principal contractor.
The decree below sustained the railway company’s general and special demurrer going to certain specified items in the plaintiffs’ account filed, overruled it as to others, and also sustained its demurrer to the answer and cross-bill of The Vaughan Construction Company, of Virginia, principal contractor, “in so far as the same is a cross-bill against the said Virginian Railway Company”, and dismissed the same, and plaintiffs replied generally to the answers of the railway company and The Vaughan Construction Company, of Virginia. And as to The Vaughan Construction Company, of West Virginia, against which no relief ivas sought, the bill was taken for confessed.
The Vaughan Construction Company, of Virginia, principal contractor, filed no lien, but by its cross-answer making all other parties to the suit defendants thereto, it sought a general accounting with the railway company, for all the
The single question presented by appellant’s appeal is,
The question then recurs, had appellant the right to maintain its cross-bill answer upon any of its theories respecting the nature of its contract with the railway company and the sub-contractors? We answer, as before, that we do not think so. The only subject matter of-plaintiffs’ suit was the amount of their lien for the labor, material, machinery, etc., furnished by them, and whether or not they had complied with the provisions of the statute, ^o as to perfect and preserve that' lien. Their contract was in no way involved in the sub-contract of The Vaughan Construction Company, of West Virginia, the other sub-contractor; the work done under .the one was in no way overlapped by the work of the other. Nor did their right to recover from the principal contractor, or to fix or enforce their lien on that part of the railway company’s property covered by their contract, depend upon the performance of the contract c*5 the other sub-contractor. These sub-contracts were let, the one independently of the other,
Section 35, chapter 125, Code 1913, relied on by appellant, authorizes such cross-answer only where before the statute a cross-bill Avould have been proper. The matter of such cross-answer calling for affirmative relief against plaintiffs in the original bill or against a co-defendant, is to be treated in the same manner and to have the same effect as if alleged in a cross-bill. Goff v. Price, 42 W. Va. 384; 16 Cyc. 333, 334. And the rule of law respecting a cross-bill is that the subject matter thereof must be germane to the original bill; must be confined to the same matters as the original bill, and should not introduce a new and independent controversy not embraced in the original bill. 10 R. C. L. 485, section 263; 1 Hogg’s Eq. Proc., section 193, p. 258; Peters v. Case, 62 W. Va. 33; 16 Cyc. 331, 332. And these authorities hold that as a cross-bill is limited to the subject matter of the original bill, and is generally in aid of the defense thereto, it cannot introduce new and distinct matters not embraced in the original bill, nor a controversy between co-defendants not necessary to a complete decree in the case made by the original bill. In the case here plaintiffs are in no way interested in the claim of The Yáughan Construction Company, of West
The railway company by cross assignments of error complains of the decree, that the court in addition to sustaining its demurrer to some of the items of plaintiffs’ account should also have sustained the same as to other specified items thereof. We are of opinion that items in such an account are not properly reached by demurrer. The whole account constituted one cause of action, and one distinct lien upon the owner’s property. Where the bill, by separate paragraphs, presents several distinct causes of action, and some of the claims are of such a character as to authorize no relief, those may be dismissed upon demurrer specifically pointing them out, but where some of the items only in a general account are controverted they are not properly reached by a demurrer, but are more properly disposed of on the merits. Gay, Admr. v. Skeen, 36 W. Va. 582.
As to the items, the demurrer to which was overruled, we cannot say as matter of law that they are not covered by the statute, and properly included in plaintiffs’ account. It may turn out on proof that they are not. They are as follows: “Extra work, ordered by engrs — bills 1-2, 1, 581.12; Extra, work, hauling east of Elmore, 5,209.00; Extra work, on slide Vaughan Shovel, 1,847.68; Extra work, old coal tipple,
The other cross-assignment of error of the railway company is that on the state of the pleadings the court erred in the absence of proof in referring the cause to a commissioner. We think the answer of the railway company substantially denies every material allegation of the bill, and no proof having been taken thereafter to sustain the bill it was error to refer the cause to a commissioner to enable plaintiffs to make out their case. This rule is applicable to all kinds of causes, including suits to enforce alleged liens against real property. Neely v. Jones, 16 W. Va. 625; Boggess v. Goff, 47 W. Va. 139; Goff v. McBee, Id. 153; Bank v. Parsons, 42 W. Va. 138; 1 Hogg’s Eq. Proc. section 628.
For this error in the decree the same must be reversed and the cause remanded for further proceedings, and it will be so ordered.
Reversed and remanded.