147 Ark. 415 | Ark. | 1921
Appellee, plaintiff below, filed a complaint in the Sevier Circuit Court, in which he alleged that on December 6, 1919, he entered into a, contract with the defendant, G-ilstrap, who was acting as agent for his co-defendant, Mrs. Cox, by the terms of which he had bought Gom G-ilstrap, as the agent of Mrs. Cox, two lots in the town of De Queen, for the consideration of $2,575, of which $500 was cash in hand paid to said Gilstrap for Mrs. Cox. That it was provided in the contract of sale that -an abstract of title would be furnished and submitted to plaintiff for his inspection within thirty days, and that the cash payment of $500 was to be refunded in the event it should be impossible for Mrs. Cox to make a good title to said lands. A copy of that contract was made Exhibit A to the complaint. That on February 19, 1920, the said Mrs. Cox had wholly failed to submit to plaintiff the abstract of title in accordance with said agreement, and in order to give her an opportunity to do So plaintiff entered into a new contract with defendant — made Exhibit B to the complaint — by which time w’as extended to May 1, 1920, to furnish an abstract, with the opinion of B. E. Isbell, showing a good title in Mrs. Cox, with the proviso that upon failure so to do the $500 should be returned to plaintiff. It was alleged that the abstract and opinion were not furnished within the time limited, and the money had not been returned, and there was a prayer for judgment for the $500.
The answer admitted the execution of a contract for the sale of the lots for the price and upon the terms set out in the complaint; but it recites the fact to be that the abstract was furnished to plaintiff’s attorney, who, upon, an examination thereof, concluded that it would be necessary to obtain a certain order from the probate court, and the plaintiff was advised that this order could not be obtained before the second Monday in April, -when the court convened, and the plaintiff thereupon agreed that the necessary time should be given to obtain the order, and a supplemental agreement was then entered into, which provided that Mrs. Cox should have until May 1, 1920, in which to obtain the necessary order of court, it being the agreement and understanding of the parties that the order should be obtained at the earliest date consistent with the law and the procedure of the court, and that the supplemental contract was entered into for the sole purpose of giving Mrs. Cox an opportunity to obtain that order. That the April term of said court was not held, and was allowed by the judge thereof to lapse, but a session of the court was later held on the .........day of May under proclamation convening a special term of court. That the greatest diligence was used in perfecting the title, and that the title has been perfected and approved by the examiner. Wherefore it was prayed that plaintiff take nothing by his suit.
A demurrer to the answer was sustained, and upon defendants refusing to plead further judgment was rendered for the $500, and this appeal is from that order.
The suit is at law, and the allegations of the answer are not, therefore, controlled by the exhibits. But it is insisted that the recitals of the exhibits have been incorporated into the answer and have become a part of it, and that it appears from the recitals of the answer that May 1 was fixed as the time limit within which, an abstract showing a good title should be delivered, and that the abstract and opinion approving the title were not furnished by that time. In other words, the question to be decided is whether the parties have made time of the essence of the contract.
In the case of Nakdimen v. Brazil, 137 Ark. 188, we quoted from 9 Cyc., pp. 604-5, the following statement of the law: “In determining whether stipulations as to the time of performing a contract are conditions precedent, the court seeks simply to discover what the parties really intended; and if time appears, on a fair construction of the language and under the circumstances, to be of the essence of the contract, the stipulations in regard to it will be held conditions precedent. * * * Time is of the essence of a contract when it is a material object to which the parties looked in the first conceptions of it. ’ ’
Here the parties amended their original contract by extending to May 1 the time for furnishing abstract and for obtaining the opinion of Mr. Isbell. It does not contravene any rule of evidence to show the purpose of the parties in changing the date upon which the abstract and opinion were to be furnished. In interpreting a contract it is proper for .the court to consider the situation of the parties with reference to the subject-matter about which they have contracted, and it was, therefore, proper to show that the purpose of the extension was to afford an opportunity to procure the necessary court order. These orders are obtainable only by following the procedure prescribed by law; and while, under the allegations of the answer, it was the intent of the parties that the utmost diligence should be used in applying for and procuring this order, it was necessarily in their contemplation that the thing contracted for could only be obtained in the orderly processes of the law, and the answer alleges that it was thought that May 1 would afford reasonable time to obtain the order which made the extension of time necessary. In contemplation of the parties the thing really contracted for was expedition and diligence in obtaining the order. The contract does not recite that time was of the essence of the contract; nor is that inference necessarily deducible from the language employed; and, when this language is read in the light of the situation of the parties and the subject-matter with reference to which they were contracting, we conclude that the parties had no intention to make time of the essence of the contract. They were contracting in regard to the approval of the title to real estate, and it was known, when the supplemental contract extending the time was made,- that the attorney to whom the abstract, had been submitted had found a defect which, in his opinion, could be remedied only by an order of the court, and time for that purpose was-granted, and this was the purpose of the amendment to the original contract. The -contract between the parties was not a mere option to buy which might or might not be exercised. Ind. & Ark. Lbr. Co. v. Pharr, 82 Ark. 573. It was one for the sale of land to be consummated upon the approval of the title.
We think the recitals of the answer set out above show a substantial compliance with the contract, which entitles the defendants to demand that plaintiff proceed with the discharge of the terms of purchase before demanding the return of the money which was to be treated as an initial payment if the title was approved. Mays v. Blair, 120 Ark. 69; Smith v. Berkau, 123 Ark. 90; Feibelman v. Hill, 141 Ark. 297; Butler v. Colson, 99 Ark. 340; Atkins v. Rison, 25 Ark. 138; Evans v. Ozark Orchard Co., 103 Ark. 212.
We conclude that the demurrer to the answer should have been overruled, and, for the error in sustaining it and in rendering judgment on the complaint, that judgment will be reversed and the cause remanded with directions to overrule the demurrer.