157 Mo. App. 577 | Mo. Ct. App. | 1911
— This is an action on a special tax-bill issued by Kansas City August 20, 1897, for the-paving of Nineteenth street from Main street to Tracy avenue. The validity of the taxbill is attacked in the answer on a number of grounds. The cause was tried! without the aid of a jury and, finding the taxbill invalid on two grounds, the court rendered judgment in favor of defendant. Plaintiff appealed..
The taxbill belonged to the same series as that considered by the Supreme Court in Construction Co. v. Coal Co., 205 Mo. 49. The facts of the case are very fully stated in that decision and we find the record in hand presents about the same state of facts the Supreme Court had before them. There are some minor differences and- plaintiff argues, with -much earnestness, that they are important enough to differentiate' the two cases in vital particulars, but we do not agree with the view and hold, as did the trial court, that the improvement was not completed, within a reasonable time.
The evidence shows beyond dispute that the contractor took over seven months- to do work which, under favorable conditions, would not have required over a month. The contract specified ninety days as a reasonable time in the winter season. Since the ordinance allowed a reasonable time the stipulation in the contract was not conclusive but only evidence of what would be a reasonable period for the performance of the contract under conditions usually obtaining in the winter months. It was possible that severe weather might compel the suspension of work during the whole winter and in such case time so lost should not be charged against the contractor. Evidently the parties endeavored to make a reasonable allowance in the contract for time lost on account of the weather but it was the purpose of the contract to give effect to the requirement of the ordinance that the work be prosecuted with reasonable diligence which meant that the contractor reasonably should utilize favorable weather when it came and he had no right either with- or without the consent of the engineer to neglect such opportunities. The engineer had no authority to grant extensions that would delay the completion of the improvement' beyond a reasonable time. To hold
The judgment is affirmed.