| Mo. Ct. App. | May 26, 1908

BLAND, P. J.

Defendant Schmidt, under a contract with defendant Louisa Wilson, constructed a dwelling house for her in the city of Cape Girardeau. Schmidt subcontracted the plastering to plaintiff or to one Thurbin, at 28 1-2 cents per yard. There was 911 yards of plastering and Thurbin put it all on. Plaintiff is a druggist and did none of the work, but contends that he subcontracted the plastering from *668Schmidt, the original contractor, and hired Thurbin to do the work. He filed his mechanic’s lien on the house for the contract price of the plastering, $259.65. The suit is to enforce the lien. The answer was a general denial. The trial was to the court without the intervention of a jury, and the finding and judgment for defendants.

1. Plaintiff makes the point that the record does not show a jury was waived. If a jury was not waived, plaintiff should have called the court’s attention to the fact in his motion for new trial and thus have given the court an opportunity to correct the error of mistake. This was not done and it is too late to raise the question here for the first time.

2. Schmidt testified by deposition, from which we quote the following:

“Q. To whom did you (Schmidt) let the contract to do the plastering for that house? Objected to; states a conclusion. Overruled and exception. A. Mr. Thur-bin.
“Q. State whether or not, you as the original contractor for that building, you made any contract or agreement with any other person for the plastering on that building? Objected to ; states a conclusion. Overruled; exception. A. I did not.” That the contract was a verbal one, at 27 3-8 per yard.
“Q. State whether or not you ever at any time made a contract with the plaintiff to do any of the plastering on that house or authorized him in any way to do the work or furnish any materials that went into the construction of that building? Objected to; overruled; exception. A. No, sir, I did not.”

It is contended that Schmidt’s answers, that he let the contract for. the plastering to Thurbin, and did not let it to Gillian, the plaintiff, were statements of legal conclusions and not statements of facts. Schmidt stated the facts as he understood them to be, and *669whether or not he was correct could have been developed by a cross-examination. This was not done. In such circumstances and in so simple a matter as letting a ■contract to plaster an ordinary dwelling house, when the contractor is not likely to be mistaken in the person to whom he subcontracted, we do not think his statement in his deposition, that he let it to one person and not to another, is open to the objection that it is a legal conclusion, especially when there was no attempt by cross-examination to shoiw the witness was mistaken.

3. Thurbin died and his widow, who was executrix of his estate, foreclosed a mechanic’s lien filed by Thurbin against the house for the contract price •of the plastering, and Mrs. Wilson paid the judgment. Over plaintiff’s objections, the court permitted defendant Wilson to offer the record of this proceeding in evidence. Gillian was not a party to Thurbin’s suit and was not bound by the judgment or any of the proceedings in the case. Both the Thurbin and Gillian liens were on file when the Thurbin suit was commenced, ■and if Mrs. Wilson did not want to contest two suits for the same fund, or was in doubt as to which of the ■claimants should have the fund, she should have paid it into court and asked that the rival claimants inter-plead for it; failing to do this, she cannot plead or •offer in evidence the judgment in the Thurbin case as' ■a defense against plaintiff’s claim. There was evidence pro and con as to whether Thurbin or Gillian were subcontractors under Schmidt for the plastering, and doubtless the admission of the Thurbin judgment in evidence influenced the court to Gillian’s prejudice, wherefore the judgment is reversed and the cause, remanded.

All concur.
© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.