257 F. 906 | 6th Cir. | 1919
Plaintiffs in error, whom we style defendants, had a contract for altering and extending a building in Cleveland, Ohio, which was to be completed January 1, 1916. In April, 1915, they made a subcontract with defendant in error (the plaintiff), whereby the latter agreed, for a stated price, to furnish and install the metal doors and trim, picture molding, and base, and to apply the hardware, such installation to be completed by October 1, 1915. On October 16, 1915, the building had not progressed far enough to permit plaintiff to begin its work, and on that date plaintiff gave defendants notice of its rescission of the contract, and brought this suit for the recovery of damages sustained by defendants’ failure to permit plaintiff to perform. Defendants denied plaintiffs’ right to rescind, and asked for damages by way of counterclaim for plaintiff’s refusal to perform. The jury was instructed that under the undisputed testimony plaintiff had the right to refuse to go on with its contract, that defendants had thus no right of action under their counterclaim, and that plaintiff, if not then itself in default, was entitled to recover its damages. Plaintiff recovered verdict and judgment for ,$7,500. This proceeding is-brought to review that judgment.
On July 13, 1915, defendants replied to plaintiff’s inquiry that—
“We expect the steel work to go right ahead now, and in all probability will not require the steel bucks before September or October, and will advise you later on when we receive the steel drawings and give you outlines as to dates of delivery.”
On September 7th defendants replied to like inquiry:
“We expect to have the steel for approximately up to the third floor shipped and erected by the end of next month, and as soon as they start on the upper portion the tile floors will follow right along.’!
In the latter part of September plaintiff learned definitely that the building would not be ready in October for its installation, and it thereupon gave, on October 16th, its notice of rescission. As it turned out, the building was not ready for the bucks before December. It is enough, for present purposes, to say that it must be, and it is, conceded that as the result of the correspondence and dealings between the parties plaintiff waived whatever right it had, to complete the contract by October 1st.
Had time been of the essence of the contract, so far as concerns plaintiff’s right (as distinguished from its obligation) to complete its work by October 1st, and had the waiver been for a definite period or to a definite date, plaintiff would have had the absolute right to cancel at the expiration of that date. General Elec. Co. v. Chattanooga Co. (C. C. A. 6) 241 Fed. 38, 42, 154 C. C. A. 38. But, in our opinion, neither of these conditions existed. The contract did not in terms make time of its essence, so far as concerns the plaintiff’s right to complete by October 1st. Such was the implied effect as to its obligation. But the obligatory provision was for defendants’ benefit. The reason for a difference between the rights of the parties in this respect is clear. Defendants were under contract with the owner to complete by January 1, 1916, with stipulation for damages at $100 per day for delay. The fact that the delay occurred through the fault of the subcontractor would not avoid defendánts’ liability. Plaintiff accordingly agreed to like stipulated damages in case of its delay, but for delays not occurring through its fault it would not be liable. The. contract, moreover, expressly provided for a suspension from time to time of such parts of the work as defendants should require, and for a resumption of performance thereafter according to defendants’ direction, no claim therefor to be made other than an extension of time for completion equivalent to the delay involved. It was also provided that plaintiff’s work should be performed and completed as soon as the progress of the build
Moreover, the defendants had not in terms promised that the build - ing would be ready for plaintiff by October 1st. At the most thej? had said (on July 13th) that it would not be ready before September or October, with promise of further advice, and (on September 7th) in effect that it was expected that the steel erection would by the last of October have proceeded far enough to permit the commencement of plaintiff’s installation. However, the suspension and other provisions just referred to gave defendants no right arbitrarily or unreasonably to suspend the work. And, as the case shaped itself, the controlling question on this branch of the case is whether the court rightly held, as matter of law, that, under the circumstances mentioned, a delay by which plaintiff would be prevented from beginning work until December or later was an unreasonable delay, which would justify plaintiff in canceling the contract. If so, we are not prepared to say that the notice was invalid because stating, as ground for rescission, that there had been no extension of time for completion beyond October 1st.
We think that, upon this record, the peremptory instruction as to unreasonable delay was erroneous. It is the general rule that questions of reasonable time and reasonable delay are for the jury. The only exception is where the facts are not in dispute and where there is no room for differing inferences. International Co. v. Stadler (C. C. A. 6) 212 Fed. 378, 382, 129 C. C. A. 54; Marmet Co. v. Peoples Co. (C. C. A. 6) 226 Fed. 646, 651, 141 C. C. A. 402. Such is not the case here. The evidence was not in complete harmony. There was testimony (considering it, as we must, most favorably to defendants) tending to show that plaintiff was kept acquainted with the progress of defendants’ work and had the means of knowing with reasonable accuracy what the prospects were from time to time. Notwithstanding the delays, it was in frequent conference with defendants throughout the summer regarding the progress of the work. Its representatives visited Cleveland as often as once a month until October; one of them consulting with defendants about details left open by the contract, at least one of which, details was never settled. These representatives were to that extent plaintiff’s agents, and their knowledge and information thus acquired was that of plaintiff. G. R. & I. Ry. Co. v. United States (C. C. A. 6) 212 Fed. 577, 583, 129 C. C. A. 113.
After the letter of September 7th, which stated defendants’ expectation that the work would by the last of October have progressed far enough for the beginning of plaintiff’s installation, it kept on with its preparations without intimating any intention to discontinue. As late as September 22d it wrote defendants regarding proposed “extra” partitions. On September 18th to 22d plaintiff’s engineer consulted with defendants at Cleveland regarding the details of plaintiff’s work,
It is because of the engineer’s report of his visit referred to in the letter of October 1st, as to the then condition of the building, that the notice of rescission was given 15 days later. The letter of October 1st contained no reference to this subject, nor did plaintiff from the time ■of its engineer’s visit in September until its cancellation letter of October 16th disclose to defendants any intention of rescinding the contract. After October 1st plaintiff wrote three letters, one acknowledging receipt from defendants of certain drawings, another asking for certain instructions from the architect, and the third to the hardware men, relative to certain doors and transoms. Plaintiff’s fabrication of metal work continued up to October 16thj although the information conveyed in defendants’ letter of July 13th, considered in connection with plaintiff’s letter of August 30th, showed that plaintiff’s installation could not be completed by October 1st. One item of the fabrication seems to have gone through the shops on October 29th.
What is reasonable time depends on a consideration of all the circumstances of the particular case. Without intimating any opinion'upon the merits, and without setting out the testimony more at large or in detail, it seems enough to say that we think there was substantial evidence tending to support a conclusion that defendants were justified in relying upon an apparent intention on plaintiff’s part to continue under the contract, and that a further delay of two or three months beyond October 1st would not be, under all the circumstances, unreasonable. The testimony thus presented a question of fact for the jury. The question whether plaintiff would have been entitled to damages for the delay, had it completed its contract, is not involved.
2. It follows from what we have said that the defenses of waiver and estoppel should have been submitted under appropriate instruc
The judgment of the District Court is reversed, and the record remanded, with directions to award a new trial.