146 N.W.2d 111 | Mich. Ct. App. | 1966
GEURINK
v.
HERLIHY MID-CONTINENT COMPANY.
Michigan Court of Appeals.
*156 Doyle, James & Dark, for defendant and third-party plaintiff.
Schmidt, Smith, Howlett & Halliday (Kent J. Vana, of counsel), for third-party defendants.
Leave to appeal denied by Supreme Court March 9, 1967. See 379 Mich. 754.
BURNS, J.
Herlihy Mid-Continent Company (hereinafter referred to as Herlihy), third-party plaintiff and appellant herein, was the general contractor for the building and erection of the Loy-Norrix high school in the city of Kalamazoo. Harold R. Sobie Company (hereinafter referred to as Sobie), third-party defendants and appellees[*], was the roofing subcontractor. Plaintiff John Geurink was an employee of Sobie.
A purchase order was issued and sent to Sobie by Herlihy and a signed acceptance of the purchase order was returned. The purchase order in part states:
"The subcontractor hereby waives and releases the general contractor from all liability for injuries to *157 persons and damages to and loss of property which the subcontractor may suffer or sustain in performance of this subcontract, or in connection herewith; and the subcontractor hereby agrees and covenants to indemnify and hold harmless the general contractor from all liability, claims, demands, causes of action and judgments arising by reason of any personal injuries or loss and damage to property suffered by or sustained by any of the subcontractor's employees, agents or officers while on the site of the work being performed under this subcontract, or going to or from said site, or in furnishing or carrying material to said site."
After the steel framework had been put into place by the general contractor, the Sobie crew came to the job site to unload trucks filled with roof decking and to install it on the steel framework. After unloading the material from the trucks onto the ground, Geurink, along with 2 other employees, went to the roof to remove the decking material from an unwelded beam. Almost as soon as the 3 men placed their added weight onto the decking material in the area where the unwelded beam was located, the roof collapsed to the ground, seriously injuring the plaintiff.
Nearly 3 years later John Geurink and Alice Geurink, his wife, brought these actions against Herlihy for damages arising out of the accident of February 1, 1960. On January 25, 1963, an order was entered joining Sobie as third-party defendant.
On February 6, 1963, a motion for summary judgment was filed by the third-party defendant, and later the motion was granted.
Upon trial, a jury returned verdicts which were reduced to judgments in favor of the Geurinks and against Herlihy, and it now appeals, claiming that the purchase order accepted by Sobie constituted an indemnity agreement wherein Sobie agreed to indemnify *158 Herlihy for the latter's negligence, and that the trial court erred in granting the summary judgment on the pleadings, oral argument and briefs.
The general rule in the interpretation of all contracts is to ascertain the intention of the parties. Klever v. Klever (1952), 333 Mich. 179. Indemnity clauses are construed most strictly against the party who drafts them and the party who is the indemnitee. Baker Contractor, Inc., v. Chris Nelsen & Son, Inc. (1965), 1 Mich. App. 450.
Herlihy's claim against Sobie was based on an all-inclusive indemnity clause contained in the purchase order. The appellant places great emphasis on the broad language, "any" damage or injury suffered "on" the site of the work. As stated in Batson-Cook Company v. Industrial Steel Erectors (CA 5, 1958), 257 F2d 410, on p 412:
"The problem inexorably begins and ends as one of construction of the specific contractual terms, and that in this process it is the law which steps in and tells the parties that while it need not be done in any particular language or form, unless the intention is unequivocally expressed in the plainest of words, the law will consider that the parties did not undertake to indemnify one against the consequences of his own negligence."
and on p 413:
"The phrase stressed heavily is indeed broad. But the broad, all-inclusiveness of language used is itself one of the indicia which the law regards as insufficient. The purpose to impose this extraordinary liability on the indemnitor must be spelled out in unmistakable terms. It cannot come from reading into the general words used the fullest meaning which lexicography would permit."
The indemnifying language in the purchase order does not insulate the appellant from the consequences *159 of his own negligent conduct unless it is clearly shown that the parties expressly agreed to this type of indemnification. Meadows v. Depco Equipment Company (Depco Equipment Company v. McLouth Steel Corporation) (1966), 4 Mich. App. 370. The trial court was correct in its ruling that the indemnity agreement did not give Herlihy a right of action against Sobie.
Appellant contends the trial court erred by granting a summary judgment based exclusively on the pleadings, oral arguments and briefs. GCR 1963, 117.2 states:
"Grounds. The motion for summary judgment shall state that the moving party is entitled to judgment in his favor because of any 1 of the following grounds:
"(1) the opposing party has failed to state a claim upon which relief can be granted."
There was no dispute as to any material fact; the determination of appellant's claim rested upon the interpretation of the indemnity clause. Once the court determined that the clause did not protect the appellant from the results of its own negligence, the appellant had failed to state a claim upon which relief could be granted. The trial court was correct in granting the summary judgment.
Judgment affirmed. Costs to appellee.
FITZGERALD, P.J., and J.H. GILLIS, J., concurred.
NOTES
[*] The third-party plaintiff filed suit against Harold R. Sobie, Harold R. Sobie Company and Harold R. Sobie Company, Inc.