71 Ga. 518 | Ga. | 1883
The plaintiff, a theatrical manager, took passage for himself and troupe, consisting in all of seventeen persons, on board the defendant’s train of cars, at Madison, Georgia,
This suit was brought to recover damages sustained by this delay, and on the trial, the plaintiff recovered damages to the amount of $208, which was the sum refunded for tickets sold for the performance which was to have been given at Columbia, less the rail fare of the troupe from Augusta to that point and back.
The defendant moved for a new trial.
The first three grounds of this motion were that
(1), (2), (3.) The verdict was contrary to evidence, and
(4.) The court erred in refusing to sustain defendant’s objection to testimony relative to plaintiff’s engagement at Columbia, .and the losses incurred by reason of his failure to meet the same.
(5.) The court erred in charging that “damages are given as compensation for the injuries sustained. Speculative damages cannot be recovered, but all damages traceable to the breach of contract can be recovered; the plaintiff! should recover for any losses he suffered by the failure to bring his troupe to Augusta on schedule time. If the jury were satisfied from the evidence that the plaintiff had an engagement to perform with his troupe in Columbia, South Carolina, and purchased tickets and took passage upon defendant’s train for the purpose of meeting the engagement, and was prevented from reaching Columbia in time by failure of defendant to deliver them in Augusta on schedule time, the defendant is liable to the plaintiff for the damages sustained by him in Columbia from not meeting his engagement, unless the defendant could show some valid reason for not delivering them on schedule time. If the delay was occasioned by the collision of defendant’s own trains on its own road, caused by the conduct of its own employés, although the train upon which plaintiff had taken passage was not one of the colliding trains, this would be no legal excuse. The damage to be recovered by plaintiff is such as is traceable directly to the acts of defendant, and must be proved. Speculative damages cannot be allowed, but only so much as has been proved. It must appear that plaintiff made every reasonable effort to avert the loss.”
In immediate connection, the court .gave in charge, at the request of defendant’s counsel, that this was an action to recover damages for a breach of contract; that it was an express contract to bring passengers to Augusta, and
The court, however, refused to charge, as requested in writing by defendant’s counsel, that this is not an action for tort; that the damages include such only as are direct, and afe the parties contemplated, when the contract was made, would be likely to result from its breach; that damages are recoverable only for such direct consequences as usually ensue from the breach of such a contract, and such as the parties contemplated, at the making of the contract, were likely to result from its breach ; they must be such as are independent of the occupation, profession or calling of the person claiming to be injured; that damages which depend upon the particular character or business of one of the parties, cannot be recovered, unless known to the other party at the time of entering into the contract.
The new trial was refused, and this writ of error is prosecuted to reverse that judgment.
The breach of the contract by the defendant, and its consequent liability to proper damages, are both admitted. But it is contended here that the damages given were too remote, and were such as ought not to have been recovered; that this result was brought about by the refusal of the court to reject evidence in relation to the subject, by its charges, and its refusal to charge as requested by defendant’s counsel.
We think these objections well taken. Every position assumed is well supported by the leading English case upon the subject, Hadley vs. Baxendale, 9 Exch. R., 341,
Judgment reversed.