73 Mich. 356 | Mich. | 1889
The plaintiff brought suit against the defendant to recover for money which it claims is due from the defendant for driving logs during the years 1883 and 1884.
On June 11, 1883, the parties entered into an agreement in writing, a copy of which is as follows:
“ Memorandum of agreement made this 11th day of June, A. D. 1883, between E. L. G-ray, of Newaygo, Mich., and the G-. W. Roby Lumber Company, of Ludington, and State aforesaid:
“ 1. Said Gray is to furnish said company with water from his two dams by means of floods to run out of the ‘ Middle Branch/ so called, all logs now in said stream, and put therein, or on the banks thereof, by said company during the present season; said floods, in case both dams are used, to be raised to the height as follows: The upper dam five feet, and the lower dam ten feet; said floods to be let off and given at times as requested in writing by the said company or its agent. In case said dams go out, said G-ray to pay back a relative proportion of the amount received as the whole consideration paid bears to amount of logs run out compared with the amount remaining in the creek, unless he repairs the dams, which he agrees to do. In case there is more than three million in the creek belonging to said company, then ¡said Gray to furnish water to run them out at the rate •of 30 cents per M.
“ In consideration of the above agreement, the said party of the second part agrees to furnish, in case they need the floods from both of Gray’s dams, two persons, whom said company are to pay, in addition to the consideration paid, as hereinafter stated. Said company agrees to pay down the sum of $500 by draft, — the receipt is hereby acknowledged, — and hereby sell and convey to*358 said Gray all the pine timber now cut and being, standing, and lying on the north half of north-west quarter, and the north-east quarter, of section 27, town 15 north, of range 14 west, with the right of egress and ingress on and from off said land for the purpose of removing said timber at any time during a year from this date; said timber and draft to be in full satisfaction for the use of floods for both or only one dam, as the said company may elect; said company to run out Gray’s logs-where their dam was located, and the latter to pay a-reasonable price therefor, to be paid when they are sawed. Said Gray is to furnish water by flood from his said dams, with which to put afloat and drive out the timber remaining on section 15, town 17 north, of range 12 west, at the rate of 30 cents per thousand feet, to be paid as the work progresses, and said company is to use reasonable diligence to put all timber in said creek next winter.”
It is also claimed by plaintiff that in the fall of 1883 a contract was made by mail, by which it was agreed that the plaintiff should have of the defendant $1.25 per thousand for the logs driven out that fall and the spring of 1884. It was also claimed by the plaintiff that the dams were washed out, and the plaintiff had to repair them, and did repair them, and charged defendant therefor. The plaintiff’s entire claim against the defendant, as its counsel presented it to the jury, was—
1. For running logs in the river when the contract was-made in June, called “old logs,” and under the contract, in 1883, 742,653 feet, $742.65.
2. For running 1,015,000 feet of defendant’s logs under agreement made in October, $1,268.75.
3. For repairs made upon defendant’s dams when washed out, $300.
Under a notice of set-off and plea of recoupment the-defendant filed the following as the items of his claim against the plaintiff:
“To use dams on Middle Branch from May 1, 1883, to December 21, 1883....................................$1,500.00
Board of two men from June 1, 1883, to December 1, 1883. 75.00-
*359 Board of Jos. Gizans, from October 27 to December 22, 56 days.............................................. 28.00
Furnishing dams, etc., for driving logs out of Middle Branch during the year 1884, up to September, 1884, being 8,000,000 feet, at 30 cents per M................ 2,400.00
Use of two dams from the 1st day of September, 1884, to December, 1884, at §25 per day.....................- 1,500.00
§5,503.00
Damages on 23,000 feet of logs left in Middle Branch____ 138.00
§5,641.00”
The case was tried in the Mason circuit by jury, and the plaintiff obtained a verdict for §472.69. Defendant brings error.
The record is very large, the bill of exceptions containing all the testimony in the case.
On November 15, 1884, the plaintiff forwarded to the defendant a statement of the account, as it claimed it, between the parties, showing a balance due from the defendant of §720.35.
The contract of June 11 was counted upon, and sufficiently proved to admit it in evidence.
Defendant claims that the balance stated by the plaintiff to him was reached by allowing to the plaintiff in the statement the sum of §742.65 for driving 742,653 feet out of the Middle Branch into the Pere Marquette river to the Pere Marquette Boom Company’s drive, in 1883. The defendant insists there is no evidence in the case that the plaintiff ever performed that service. If this is true, but little more need be said to dispose of the case. The testimony of Mr. Roby was to the effect that he was the president of the company, and made the contract in behalf of the company, and after the contract was completed he agreed with the defendant that the scale of the logs driven out of the Middle Branch for him by the
Defendant further insists that plaintiff never drove any «logs for him, except the 1,015,000 feet at $1.25 per M., and that, with the proper deductions made, the statement would show a balance due defendant of $22.30, without giving defendant anything under his plea of recoupment.
Under the provisions of the contract, the payment for driving out defendant’s logs fz-om the Middle Branch by plaintiff was to be a reasonable price when they were sawed. These were the 742,653 feet which are chaz-ged for in the plaintiff’s account at one dollar per thousand; and defendant insists, further, that there is no proof in the case that any of the logs, if driven out of said stream, were ev.er sawed; that the parties had agreed upon what the evidence should, be of the driving and the amount of logs run for the defendant, and that was the mill-scale when the logs were sawed. This would be competent and material .evidence of the amount, especially made so by the parties. It was not, however, the only competent testiznony which might be given of that amount, and we
By the terms of the agreement the defendant was to furnish water to enable the plaintiff to run out of the Middle Branch 3,000,000 feet of logs. This the defendant could only do by the use of danis, of which he had two. For the use of the dams and water the defendant was to be paid a certain sum. If the dams went out (as they were liable to by freshets or' otherwise) before the amount of logs' agreed upon was run out, then the defendant was to refund a proportionate amount paid for the use thereof. The dams, however, lasted, with some repairs made, for the payment of which the defendant does not object, until the 3,000,000 feet were run out; but soon thereafter the dams went out, and defendant claims the plaintiff went on, without any direction from the defendant, and made repairs thereto, to the value, as plaintiff now claims, of $300, and seeks to recover the same in this suit against defendant. It is the contention cf the defendant that the repairs which plaintiff made'to the dams, for which this $300 is charged, the defendant was under no obligation to make, neither did he ever direct or assent to the plaintiff’s making them for him, and there is no liability upon his part to pay for the same.
It is difficult to see why the position of the defendant in regard to this charge of $300 for repairs upon the dam is not correct. It is not pretended there was any special agreement between the parties by which the defendant agreed to pay for this work, .and I can see no chance or ground for implying one. Under the contract between the parties, if there were not more than 3,000,000 feet to be run out of the Middle Branch, and the dam went out before the drive was completed, it was provided that defendant should make a' rebate from the moneys paid
When the court charged the jury that if the plaintiff drove the ’ defendant’s logs out of the Middle Branch within a reasonable time, “ and this dam washed out without their fault, and they made the repairs in good faith, they will be entitled to recover the entire charge against Mr. Gray,” it went too far. .The provisions of the contract would not warrant such a construction, for the reasons stated, and it was error. The following charge contains a similar fault:
“Taking the plaintiff’s theory of it, and my statement of one side of it, if they have driven the logs, and made the repairs, they would recover that amount as a matter of course.”
If the defendant was not obligated to make the repairs, and did not request them to be made, he certainly was not bound to pay for them, and his liability was not a matter of course under the contract, and no affirmative defense was necessary.
In several respects we think the charge was' too general, so much so as to mislead the jury to the prejudice of the defendant in several of the parts complained of. In stating the reasonable time within which the logs were to be driven in order to constitute a compliance with the
“You know more or less about this class of litigation, • — about lumber business and logging contracts, and the way this business is carried on. Use your own common sense, and do what is right between these two parties. This is all I care to say to you, besides these requests to charge.”
This substantially makes the jury judge of the law as well as the facts, whereas they are required to take the law from the court. We think the errors pointed out sufficient for the disposition which must be made of the case, as presented to us, and we see no occasion for further examination of the numerous exceptions which we find in the record. We may perhaps with propriety say, were the only claim made by plaintiff in the case the driving of the 742,653 feet of defendant’s logs (being the ‘old logs,’ so called), it might be regarded as very doubtful whether or not the case should have been allowed to go to the jury, as the evidence stands in this record.
The judgment must be reversed, and a new trial granted.
The declaration purported to set forth the contract, but the signatures were omitted, and the objection was based upon this variance.