39 Ind. App. 653 | Ind. Ct. App. | 1907
The complaint alleges that Edward E. Claypool was the owner in fee simple, and the Indiana Hotel Company was lessee, in possession under a ninety-nine-year lease, of certain real estate in the city of Indianapolis, Indiana; that in July, 1901, the Indiana Hotel Company entered into a contract with the George B. Swift Company to erect on said real estate a building; that in the same month the Ransome Concrete Fireproofing Company, hereinafter called the Ransome Company, entered into a contract with the George B. Swift Company to furnish the fireproofing for said building; that said Ransome Company did furnish materials and labor for the construction of said building, to the value of $25,000; that in April, 1902, and within sixty days of the date of the furnishing of said materials, the Ransome Company filed in the recorder’s office of Marion county its written notice of its intention to hold a lien on said real estate in the amount of $25,000. It further alleges that a reasonable fee for plaintiff’s attorney is $1,000, and demands judgment for $28,000, and an enforcement of a lien against the real estate. Afterward, on its petition, the George B. Swift Company was made a party defendant over the objection of the appellee.
The George B. Swift Company, in addition to the general denial, filed a special answer alleging: That on July 8, 1901, it entered into a written contract with the Indiana Hotel Company to build for it an eight-story fire-proof
Edward E. Claypool answered by general denial. The Indi'ana Hotel Company, in addition to a general denial and plea of payment, -filed a special answer, in which it set up the contract between the Ransome Company and the George B. Swift Company. It alleged that the Ransome Company did not comply with its contract, and delayed its work to such an extent that the George B. Swift Company took charge of the same; that the Ransome Company, in its contract, agreed to keep the real estate upon which the building was to be erected free of any mechanics’ liens, but that it violated said agreement, and allowed a large number of liens to be filed for material put into said'building by said Ransome Company; that in said contract the Ransome Company agreed to accept in payment of $5,000 of the contract price, fifty shares of preferred stock of the Indiana Hotel Company at the par value of $100 per share; that it never took said shares, and, by its failure to carry out said contract, was never entitled to receive said shares; that the Ransome Company violated the terms of its contract by failing to execute the bond for $50,000 which it agreed to execute ; that at the time plaintiff’s action was begun the Ran-some Company was indebted to the Geore B. Swift Company in the sum of $25,000, after allowing it credit for any labor performed or material furnished in the execution of said contract; that at the time the action was begun there was nothing due the Ransome Company, but, on the contrary, on settlement of accounts between the fireproofing company, represented by the appellee, and the George B. Swift Company, allowing credits for materials furnished and labor performed on said building, there would still be
In tbe fourth paragraph of answer the Indiana Hotel Company set out that in the contract between the Bansome Company and the George B. Swift Company it was provided, among other things, that the Bansome Company agreed to keep the real estate described in said contract free from any mechanics’ liens, and in the contract between the George B. Swift Company and the Indiana Hotel Company it was provided that the George B. Swift Company would keep the real estate free from any mechanics’ liens, alleging that the appellee was not entitled to any relief against the defendant, and that there was no lien upon the real estate in favor of appellee.
The case was tried by the court without a jury, a special finding of facts made, and conclusions of law stated thereon. The assignment of error is that the court erred in its conclusions of law.
The court found that the defendant Olaypool is the owner of the real estate, and the Indiana Hotel Company holds the same under a ninety-nine-year lease; that the Indiana Hotel Company entered into a contract with the George B. Swift Company for the erection of the building on said real estate; that said contract was in writing, being the same set forth in the cross-complaint of the George B. Swift Company, and that one of the agreements and conditions of said contract was that the George B. Swift Company would “keep said real estate free from all mechanics’ liens;” that the George B. Swift Company made a subcontract with the Bansome Company, being the same contract .set forth in the answer and counterclaim of the defendant the George B. Swift Company; that after work had been begun, on the written contract between the George B. Swift Company and the Bansome Company, an oral contract was entered into between them whereby the Bansome Company agreed to
As conclusions of law the court found that the George B. Swift Company was justified in excluding the Eansome
Upon the question here involved it is stated in 2 Jones, Liens (2d ed.), §1502, that “if a contractor has agreed not to encumber the property by a lien, or to permit it to be so encumbered by any subcontractor or other person, a subcontractor knowing of the existence of the contract is put on inquiry, and is affected with notice of its contents and stipulations.”
Kneel and, Mechanics’ Liens, §§136, 137, says-: “It has been held that the express stipulation against liens will affect not only the contractor, but all persons acting under him or depending upon the original contract as a basis for their liens, upon the principle that persons agreeing to furnish labor or materials to the original contractor, do so with reference to such original contract in subordination to its provisions.” Section 137: “There is no substantial equity in the plea by a subcontractor of a want of knowledge of the conditions of the original contract. He knows
In Boisot, Mechanics’ Liens, §746, the law is laid down applicable to contracts of the kind under consideration, and in conclusion it is said: “The general rule to be deduced from these decisions seems to be that a covenant not to assert a mechanic’s lien, in order to be binding, must either be express, or be so clearly implied that the mechanic can understand its import without legal advice.”
In Bowen v. Aubrey (1863), 22 Cal. 566, the contract contained the following agreement on the part of Aubrey: “ ‘Said first party hereby agrees he will not encumber' or suffer to be encumbered said building or the lot on which it is erected, by any mechanics’ liens or debts of material, labor men, contractors, subcontractors, or otherwise.’ ” Aubrey sublet the brickwork to the intervener, Craft. Held, that as Craft knew that here was a contract between Aubrey and the appellant and that he was a subcontractor under it, this was sufficient to put him upon inquiry and he is to be considered as affected with notice of the contents of the contract. Held also, that the subcontractor could not acquire any right against the owner in contravention of the terms of the original contract, and that a party may, by agreement, waive a right created by a statute for his benefit.
In Evans v. Grogan (1893), 153 Pa. St. 121, 25 Atl. 804, a covenant by a contractor to furnish a clear release of liens, and to refund all money the owner may be compelled to pay in discharging any lien, is not a waiver of liens so as to prevent a material man from filing a lien against the property for materials furnished. Cited in Schroeder v. Galland (1890), 134 Pa. St. 277, 19 Atl. 632, 7 L. R. A. 711, 19 Am. St. 691, as deciding that when the owner and contractor enter into an agreement which contains an express covenant not to file a lien or when such
In Long v. Caffrey (1880), 93 Pa. St. 526, a mechanic, about to erect a building, stipulated in writing with the owner “that no mechanic’s lien or other lien should be entered against said building by said Long or the material contractor or workmen.” The mechanic cannot file a lien because of a separate agreement entered into by which the owner was to insure the building' and the owner did not insure.
In Dersheimer v. Maloney (1891), 143 Pa. St. 532, 22 Atl. 13, a building contract provided that there should not be any lawful claims against the contractor in any manner from any source whatever for work or material furnished, and that the owner “will not in any manner be answerable * * * for any of the materials or other things used and employed in finishing and completing said works.” Held, that such provisions constituted an implied covenant by the contractor that no lien should be filed against the building. A subcontractor was chargeable with notice and was bound by all the stipulations of the original contract and not entitled to file a lien for the material furnished. Citing Schroeder v. Galland, supra.
In Scheid v. Rapp (1888), 121 Pa. St. 593, 15 Atl. 652, the covenant of the contractor for work to be done and materials supplied for the erection of a building, that he will not suffer or permit any mechanics’ lien or liens to be filed, is a waiver of the right to file or cause to be filed a lien in his own favor, citing Long v. Caffrey, supra.
“The party of the second part hereby agrees to accept from the party of the first part (George B. Swift Company), in full payment of $5,000 of the contract price named herein, fifty shares of the preferred stock of the Indiana Hotel Company at par of $100 per share.”
The Ransome Company is not entitled to a mechanic’s lien against the Indiana Hotel Company and the property of Edward F. Claypool.
The judgment is reversed, with instructions to restate the conclusions of law, and render judgment in accordance with this opinion.