This is a petition under the provisions of G. L. (Ter. Ed.) e. 258, which confers jurisdiction upon the Superior Court, except as otherwise expressly provided, of all claims at law or in equity against the Commonwealth. The case was referred to an auditor (c. 258, § 2). It was thereafter heard by a judge of the Superior Court upon the auditor’s report, no other evidence being introduced. The judge denied the petitioner’s requests for rulings of law and allowed the respondent’s motion for judgment. The petitioner excepted to the allowance of this motion, to the refusal to give its requests, and to other rulings of the judge. The petitioner also claimed an appeal from the order of the judge allowing the respondent’s motion for judgment. The appeal is not before us and the case will be considered on the petitioner’s exceptions.
The petitioner and the Commonwealth, through its department of public works, entered into a contract on May 23, 1934, for the construction of a portion of a State highway. The work involved also a part of a Federal aid project, thirty per cent of the cost of which was to be borne by the Federal government, and seventy per cent by the Commonwealth. The project itself and the contract were approved by the emergency public works commission of the Commonwealth, acting under St. 1933, c. 365. The contract was a so called unit price contract based upon specifications made by the department of public works, according to which the estimated amount to be paid under the contract was $364,652.43. As the work progressed it developed that the estimates of quantities varied from the quantities which were in fact used, and the work actually done was greater than that which was originally estimated. Payments were made under the contract estimates, which were documents, prepared by the department of public works, purporting to show the work that had been done and which contained the certificate of the chief engineer and the department of public works. The work
It is a fundamental principle of our form of government that the Legislature, which is the appropriating branch, has sole power to authorize the payment of claims against the Commonwealth. Opinion of the Justices,
In our opinion the consent of the Legislature conferring jurisdiction upon the Superior Court of claims against the Commonwealth, does not grant power to governmental departments to settle such claims when they involve the particular department, and cases where it has been held that town and fire districts have the power to settle claims against them are distinguishable. As was said in the case of Matthews v. Westborough,
The petitioner contends, however, that the power to-make and supervise the execution of contracts impliedly carries with it the power to adjust and compromise disputes arising out of or in connection with the work to be done under the contract. G. L. (Ter. Ed.) c. 16 provides for the creation of the department of public works but contains no reference to the duties of that body with respect to the making of contracts, except that the commissioner, who is the executive and administrative head of the department, is required to approve all contracts made by the department. Its duties are defined generally in G. L. (Ter. Ed.) c. 81, relating to State highways, which empowers the department to make various contracts necessarily incident to the construction, repair and maintenance of certain highways, in some instances subject to the approval of the Governor and Council, and also to acquire land for highway purposes by purchase, gift or the right of eminent domain, in some instances subject to the approval of the Governor and Council. As to contracts generally for building construction, see G. L. (Ter. Ed.) c. 29, §§ 7 and 8. Section 27 of said c. 29 excepts
We do not think the alleged compromise agreement is enforceable. The conclusion reached is supported by the reasoning in William Cramp & Sons Ship & Engine Building Co. v. United States,
Exceptions overruled.
