The plaintiff appeals from the judgment of the trial court granting the defendant’s motion to
The trial court found the fоllowing facts: The plaintiff contractor entered into a subcontract with the defendant subcontractor to do painting work on a public project. A dispute arose because of the defendant’s use of nonunion painters. The defendant completed the subcontract in a timely fashion, and the architect and public authority accepted the project.
The defendant claimed that money was due it on the subcontract and the parties submitted the claim to arbitration. The submission encompassed two issues: (1) what money, if any, was owed to the defendant; and (2) whether General Statutes § 49-41a (b) 1 could be apрlied by the arbitrator in this case, and, if so, what remedy was to be awarded. 2
The plaintiff filed an application to vacate the arbitration award and the defendant filed a motion to confirm it. The defendant also moved for an order awarding it supplemental interest and attorney’s fees which had accrued subsequent to the date of the arbitration award. In a detailed memorаndum of decision, the trial court granted the defendant’s motion to confirm the award and denied the plaintiff’s application to vacate. It did not address the issue of the supplemental award of interest аnd attorney’s fees.
On appeal, the plaintiff claims that the trial court erred in upholding the arbitrator’s award because the arbitrator exceeded the scope of the submissions and his powers in interрreting the statute. The defendant, by way of a preliminary statement of issues; see Practice Book § 3012 (a); claims that the trial court erred in failing to award supplemental attorney’s fees and interest to the defendant. We find no error on either of the parties’ claims.
The plaintiffs claims that the arbitrator exceeded the scope of the submissions and his powers are unavailing. The two submissions to the arbitrator werе broadly phrased and included questions involving the merits of the appeal as well as questions of arbitrability of damages under General Statutes § 49-41a (b). As the trial court found, the submissions were unrestricted. No conditional lаnguage was used by the parties binding the
The first question submitted was plainly unrestricted by its terms. See footnote 2, supra. The parties are bound by the arbitrator’s decision on that question. Roraback v. Travelers Ins. Co., supra, 23-24.
The second question submitted embraced the issue of arbitrability under a certain statute and the applicability and availability of a remedy under thаt statute if found arbitrable. Neither party chose to compel a judicial determination of the issue of arbitrability prior to arbitration, although the option was available to them.
Schwarzschild
v.
Martin,
“[WJhere the issue of arbitrability is committed to an arbitrator for determination, ‘the court is bound by the arbitrator’s determination unless that determination clearly falls within the proscriptions of § 52-418 of the General Statutes, or procedurally violates the parties’ agreement.’ ”
Waterbury Board of Education
A challenge to an award оn the ground that the arbitrator has exceeded his powers or so imperfectly executed them that a mutual, final and definitive award was not made upon the matter submitted; General Statutes § 52-418 (a) (4); is reviewed by comparing the award with the submission.
Roraback
v.
Travelers Ins. Co.,
supra, 23. In making such a comparison, where the submission is unrestricted, the court will not review the evidence or the legal questions involved but is bound by the arbitrator’s legal and factual determinаtions.
Game-A-Tron Corporation
v.
Gordon,
There is no allegation here that the arbitrator’s determination procedurally violated the terms of the parties’ contract. The pertinent clauses of the contraсt indicate that the parties did not delineate any narrow procedural limits to govern arbitration which might arise between them. See Waterbury Board of Education v. Waterbury Teachers Assn., supra, 62. In addition, procedural irregularities may be waived. Id., 63. If any existed herе, they are deemed waived by the parties’ failure to raise them in the trial court. Id. The parties chose to submit the question of arbitrability of General Statutes § 49-41a (b), and of a potential award under that statute, tо the arbitrators. See Schwarzschild v. Martin, supra; New Britain v. Connecticut State Board of Mediation & Arbitration, supra. The parties, therefore, are also bound by the arbitrator’s decisions on the second question submitted. See footnote 2, supra.
A motion for rectification addressed to the trial court pursuant to Practice Book § 3082, followed by a motion to review addressed to this court under Practice Book § 3108, if necessary, would have been appropriate. Alternatively, the defendant could have requested that this court order the trial court to complete the rеcord pursuant to Practice Book §§ 3096 and 3107. Since the defendant did not follow any of these procedures,
4
the
There is no error.
In this opinion the other judges concurred.
Notes
General Statutes § 49-41a (b) provides: “If payment is not made by the general contractor or any оf its subcontractors in accordance with such requirements, the subcontractor shall set forth his claim against the general contractor and the subcontractor of a subcontractor shall set forth its claim against the subcontractor through notice by registered or certified mail. Ten days after the receipt of that notice, the general contractor shall be liable to its subcontractor, and the subcontractor shall be liable to its subcontractor, for interest on the amount due and owing at the rate of one per cent per month. In addition, the general contractor, upon written demand of its subcontrаctor, or the subcontractor, upon written demand of its subcontractor, shall be required to place funds in the amount of the claim, plus interest of one per cent, in an interest-bearing escrow acсount in a bank in this state, provided the general contractor or subcontractor may refuse to place the funds in escrow on the grounds that the subcontractor has not substantially performed the work aсcording to the terms of his or its employment. In the event that such general contractor or subcontractor refuses to place such funds in escrow, and the party making a claim against it under this section is found tо have substantially performed its work in accordance with the terms of its employment in any arbitration or litigation to determine the validity of such claim, then such general contractor or subcontractor shаll pay the attorney’s fees of such party.”
The submissions presented to the arbitrator took the following form:
“1. Does Gennarini Construction Co., Inc. owe Messina Painting & Decorating Co. any money pursuant to a subcontract entered into on Decernber 1,1982 for painting work on the Old Danbury Jail Rehabilitation Project? If so, how much money does Gennarini owe Messina?
“2. Does the Arbitrator have authority to enter a remedy under Seсtion 49-41a (b) of the General Statutes? If so, should the statute be applied in this case, and, if so, what shall the remedy be?”
This court, in response to the defendant’s motion, permitted the defendant to file its preliminary statement of issues in an untimely fashion. The defendant suggests that this meant the court would review the claims raised in it. The permission to file a preliminary statement of issues late is just that, a permission to file, and does not necessarily imply that this court will address the merits of the claims raised in that statement where they are otherwise improperly before us.
The defendant stated at oral argument before this court that its post-judgment “Motion fоr Order” sought relief pursuant to Practice Book § 3082. An examination of the order reveals that rectification was not sought and that § 3082 was not invoked. We cannot accept post-hoc explanations
The defendant also filed a “Motion for Further Articulation” in this court which was denied fоr failure to file a threshold motion for rectification in the trial court. Practice Book § 3082. This could not be viewed as a motion to review under Practice Book § 3108 since the requisite motion before the trial court was never made. Nor could it be interpreted as a motion asking this court to complete the record under Practice Book §§ 3096 or 3107. The failure of the defendant to adhere to any of the procedures set forth in the Practice Book to perfect the record for an appeal prevents us from addressing this issue. See
Montanaro
v.
Snow,
