Plaintiff, Geneva Pipe Co., seeks reversal of a summary judgment awarded to S & H Insurance Co., defendant.
In February of 1981, defendant issued material payment bonds to insure payment to persons performing labor on and supplying materials to two construction projects with the city of Monticello in San Juan County, Utah. The general contractor on the projects was third-party defendant, John Maughan, dba Jonco Construction Co. (Jonco). At the request of Jonco, plaintiff supplied labor and materials to the two projects, for a total value of $222,282.18.
Plaintiff received three payments from Jonco in July, September, and October of 1981, totalling $105,000. These checks were designated by Jonco to be applied to the Monticello project account. Plaintiff received two additional checks, one in June for $45,000 and one in November for $7,500, which were not designated for specific application. Plaintiff applied both checks to the payment of charges made by Jonco prior to the Monticello projects.
Jonco failed to pay the plaintiff the balance owing on the Monticello projects and filed for bankruptcy. Plaintiff brought this action against the defendant to recover the balance owing on those projects and alleged that it had not been notified by Jonco to apply the June and November payments to those projects. It further alleged that during the years it had been doing business with Jonco, a period exceeding four years, its practice had been to apply checks not otherwise designated to Jonco’s oldest charges.
Defendant moved for summary judgment based on its contention that there was no genuine issue as to any fact relevant to the material issues raised. Jonco’s president, by affidavit, swore that when he learned that the checks had not been applied to the Monticello projects, he notified plaintiff that they should be so applied. Defendant subsequently tendered into court the amount claimed to be owing by plaintiff, reduced by the total amount of the June and November checks, $52,500, plus interest, for a total of $77,992.16. After entering its order awarding summary judgment to defendant, the court released the funds to plaintiff on June 6, 1983.
I.
On appeal from a summary judgment, we review the evidence in a light most favorable to the losing party. An award of summary judgment is appropriate if the pleadings, affidavits, and other submissions of the parties show that no genuine issue of material fact exists and that the moving party is entitled to judgment as a matter of law. Rule 56(c), Utah R.Civ.P.;
Norton v. Blackham,
Utah,
Plaintiff assails the lower court’s reliance on U.C.A., 1953, § 58A-1-19 1 in awarding summary judgment. That section provides:
*650 Any owner or contractor in making any payment to a materialman, contractor, or subcontractor with whom he has a running account, or with whom he has more than one contract, or to whom he is otherwise indebted, shall designate the contract under which the payment is made or the items of account to which it is to be applied. When a payment for materials or labor is made to a subcontractor, or materialman, such subcontractor or materialman shall demand of the person making such payment a designation of the account and the items of account to which the payment is to apply. In any case where a lien is claimed for materials furnished or labor performed by a subcontractor or materialman, it shall be a defense to the claim that a payment made, by the owner to the contractor for the materials has been so designated, and paid over to the subcontractor or materialman, and that when the payment was received by the subcontractor or ma-terialman he did not demand a designation of the account, and of the items of account to which the payment was to be applied.
Plaintiff contends that the lower court erred in relying on this section because it applies only when a mechanics’ lien is claimed. We agree. We find the section to be not applicable to this case, despite defendant’s contention that
Western Ready Mix Concrete Co. v. Rodriguez,
Utah,
II.
Concomitantly with the determination that section 58A-1-19 is not controlling here, we must now determine whether plaintiff was entitled to judgment against defendant as a matter of law. Similar cases have been before this Court on previous occasions. In
Salt Lake City v. O’Connor,
In transactions like the one under consideration, the surety has ample facilities for protecting itself. It may with propriety reserve an exercise of surveillance over the disbursement of the proceeds of contracts for the performance of which it is surety. Materialmen dealing with contractors cannot do so. They cannot, consistent with business proprieties, inquire into the sources of money paid them. When a surety as in the case at bar, permits money on the contract to be paid the contractor unconditionally, which it must know he may use for general purposes, we see no sufficient reason for sustaining any claim or equity in behalf of the surety, in such money, after it has been paid to another in the due course of business. The risk of such a loss is one of the hazards which a surety, for a fixed consideration assumes by its contract.
Thus, the materialman was at liberty to apply the payments to the old debt. Later, in
Utah State Building Commission v. Great American Indemnity Co.,
It is elementary law that: A creditor may apply a payment voluntarily made by a debtor without any specific appropriation, where there are two or more debts, to whichever debt he pleases.... Another exception to the rule ... obtains when the money ... is known to the creditor to have been derived from a particular source or fund, in which case he cannot, without the consent of the debtor, apply it otherwise than to the exoneration of the source or fund from which it was derived.
(Emphasis added; citations omitted.)
The Washington court, in Sturtevant, upheld a creditor’s right to apply the money as it saw fit and based its determination upon the fact that the creditor had no knowledge of the source of the money.
Subsequently, in
Davis County Board of Education v. Underwood,
Several jurisdictions have reached the same conclusion.
See Cooper v. Sparrow,
(1) Except as stated in Subsection (2), as between two or more contractual duties owed by an obligor to the same obligee, a performance is applied according to a direction made by the obligor to the obli-gee at or before the time of performance. (2) If the obligor is under a duty to a third person to devote a performance to the discharge of a particular duty that the obligor owes to the obligee and the obligee knows or has reason to know *652 this, the obligor’s performance is applied to that duty.
(Emphasis added.)
Thus, whether plaintiff knew or had reason to know the source of the two un-designated payments made in June and November becomes a relevant factual issue which, from the record on appeal, remains in dispute. We reverse and remand to the lower court to make that determination and for further proceedings. Costs to appellant.
Notes
. The language of section 58A-1-19, which was formerly section 58-23-14.5 (as cited in
Western Ready Mix Concrete Co. v. Rodriguez,
Utah,
. Section 38-1-1 provides: “The provisions of this chapter shall not apply to any public building, structure, or improvement."
. Section 63-56-38(3) requires that full payment be made "within 90 days from the date on which the last of the labor was performed or material was supplied...."
