133 N.Y.S. 978 | N.Y. App. Div. | 1912
On the 22d day of August, 1906, the plaintiff, a domestic corporation engaged in building construction, and the appellant made a contract in writing by which plaintiff undertook to erect on premises owned by appellant situate at the northeast corner of Sixty-fourth street and Broadway, borough of Manhattan, New York, a six-story reinforced concrete building in accordance with specifications and drawings theretofore prepared by one F. M. Andrews, an architect, under whose direction the work was to be done. The main floor of the building was to consist of stores and the remainder of the building was to be used as a garage. The contract provided that the building was to be completely finished and ready for occupancy on or before the 1st day of July, 1907, and in default thereof the respondent was to pay the appellant as liquidated damages the sum of $200 for each day thereafter until the building was completed and ready for occupancy. The respondent failed to complete the building within the time specified in the contract, and in fact had not completed the excavation work at one corner of the plot at that time, although the excavation work had been finished and some of the concrete work done on other parts of the plot. The contract contained the usual provision that should the contractor at any time refuse or neglect to supply a sufficient number of skilled workmen, or sufficient materials of proper quality, or fail in any other respect to prosecute the work promptly and diligently or to perform its agreement, the
The learned counsel for the appellant concedes that the con
We are of opinion, therefore, that the appellant was entitled to offset against the respondent’s claim the general damages which he sustained by the loss of the use of the building between the day when it was to be completed and the day appellant took charge of it in its uncompleted condition. This view necessarily requires a new trial, but in granting it it is proper to comment on some other claims with respect to the question of damage. The recovery by the respondent for brick and cement delivered on the premises by its sub-contractor who claimed the same cannot be sustained on the evidence in this record, which does not present facts showing that title to the material passed to the respondent. It was, of course, proper for witnesses in forming their opinions with respect to the value of the work done by the respondent to include the actual cost of material and labor and a reasonable profit to the contractor,; but the respondent was not entitled to recover for the separate items, and although the evidence in chief was not confined to the reasonable value of the work as a whole, the learned referee undoubtedly followed the proper rule in finally estimating the damages in this regard. The plaintiff’s claim on the theory of a quantum meruit is necessarily unliquidated and incapable of determination by market values or an arithmetical calculation and it was not entitled to recover interest. (Delafield v. Village of Westfield, 41 App. Div. 24; Excelsior Terra Cotta Co. v. Harde, 181 N. Y. 11; Coates v. Village of Nyack, 127 App. Div. 153; Fox v. Davidson, 111 id. 174; Beckwith v. City of New York, 121 id. 462; O’Reilly v. Mahoney, 123 id. 275.)
It follows, therefore, that the judgment should be reversed
Ingraham, P. J., Clarke and Miller, JJ., concurred; Scott, J., concurred in result.
Judgment reversed, new. trial ordered before another referee, costs to appellant to abide event. Order to be settled on notice.