delivered the opinion of the Court.
This case comes on appeal from a judgment of the Seventeenth Judicial District Court, Valley County, finding the existence of an oral contract for the sale of 20,000 bushels of wheat and crediting the respondents with two deliveries of wheat rejected by the appellant.
Between June 7, 1973 and July 27, 1973, the Zerbes delivered a total of 16,593 bushels of dark northern spring wheat to the General Mills grain elevator in Great Falls, Montana. In addition, the Zerbes tendered two additional loads of wheat to General Mills. One load was tendered on July 24, 1973, and consisted of 800 bushels of wheat. Another load of 800 bushels was tendered on July 28, 1973. Both loads were rejected by General Mills because they were allegedly contaminated by insects. However, the Zerbes sold the same loads of wheat to another elevator in Great Falls without discount for contamination. After rejection of the two loads, the Zerbes discontinued deliveries under the contract. On April 11, 1974, General Mills learned that the Zerbes were not going to make any further deliveries. The market price for dark northern spring wheat in Great Falls on April 11, 1974 was $4.44 per bushel.
On July 10, 1975, General Mills brought suit against the Zerbes alleging breach of contract and seeking $61,802.95 in damages. On November 4, 1982, the case was tried before the District Court sitting without a jury. After hearing the evidence presented by the parties the District Court held: (1) the original contract was for 20,000 bushels of wheat; (2) the defendants tendered or delivered a total of 18,193 bushels to plaintiff, a quantity that included the two 800 bushel loads the plaintiff rejected on July 24, 1973 and July 28, 1973; (3) the defendants failed to deliver 1,807 bushels under the terms of the contract; and (4) the plaintiff was entitled to a judgment in the amount of 1,807 bushels times $1.85 which was the difference between the $2.56 per bushel the defendants agreed to accept for the wheat and the $4.41 per bushel market price on April 11, 1974.
The plaintiff now appeals claiming the District Court erred in finding that the oral contract was for 20,000 bushels rather than 50,000 bushels and crediting defendants for the two 800 bushel loads tendered on July 24, 1973 and July 28, 1973. Specifically, appellant argues there is a presumption under Montana law that a mailing has been received if customary office mailing procedures have been followed and respondents failed to produce credible evidence to rebut that presumption. In addition, appellant asserts the respondents should be estopped from claiming they only agreed to sell up to 20,000 bushels of wheat rather than the 50,000 claimed by appellant because of the respondents’ past practice of not signing and returning confirmation forms but delivering the quantities of wheat agreed to by the parties. Finally, .appellant contends the District Court erred in crediting the respondents with the two 800 bushel loads because the evidence presented at trial showed the appellant was justified in rejecting the loads as contaminated.
After considering the evidence and ascertaining the witnesses’ credibility, the District Court determined that respondent did not receive the confirmation form reflecting the 50,000 bushel quantity and the terms of the contract provided for delivery of 20,000 bushels. The District Court properly weighed the presumption of receipt against respondent’s denial and the other evidence presented at trial and arrived at its conclusion. We cannot deviate from our function as an appellate court and reverse the District Court’s decision. Our functions do not include a retrial of the case. We will not substitute our judgment for that of the trial court. We are “confined to determining whether there is substantial credible evidence to support the findings of fact and conclusions of law.”
Cameron v. Cameron
(1978),
Appellant also asserts that respondents should be es-topped from denying the contract was for 50,000 bushels because in prior transactions between the parties the respondents never signed or returned confirmation forms. The essential elements of estoppel are the following: (1) there must be conduct, acts, language or silence amounting to a representation or concealment of facts; (2) facts must be known to party estopped at the time of his conduct; (3) truth concerning the facts must be unknown to the other party; (4) the conduct must be done with the intention that it be acted upon by the other party or under circumstances so that it is both natural and probable that it will be so acted upon; (5) the conduct must in fact have acted upon it to his detriment.
In re the Matter of Shaw
(Mont.1980),
In sum, we find no reversible error and therefore affirm.