The General Electric Company (“G.E.”) petitions this court for review of a decision and order of the National Labor Relations Board (“N.L.R.B.” or “Board”), reported at
I
G.E. operates an appliance manufacturing facility in Cicero, Illinois. The Union represents a unit of production and maintenance employees at G.E.’s Cicero facility. The two have been parties to collective-bargaining agreements (“CBAs”) since 1963. In all of these CBAs, including the 1985-88 CBA that was effective at the time of the actions involved here, G.E. management retained the right to subcontract. As stated in the “Management Rights” provision of the 1985-88 CBA:
The Union recognizes that the Company maintains the exclusive right to manage its business in such manner as the Company shall determine, subject only to those provisions of this Agreement which expressly qualify this right. The Company’s right to manage its business affairs shall include, but not be limited to, its rights to determine the methods and means by which its operations are to be carried on, to subcontract, to discontinue or relocate all or any portion of such operations, to assign work, to schedule hours of work including overtime, and to establish the size, composition and qualifications of the work force, to determine job classifications, standards and rates of pay and to maintain safety, efficiency and order in its plants and operations.
(Emphasis added.)
G.E.’s retention of this right has not been without some opposition. At the negotiations that preceded the 1982-85 and 1985-88 CBAs, the Union proposed changes in this language, which would have limited or eliminated G.E.’s right to subcontract maintenance work. These Union proposals were unsuccessful. Nonetheless, the Union filed numerous grievances between 1981 and 1987 regarding G.E.’s subcontracting of maintenance jobs, and the Union three times went out on strike in support of these grievances.
Most of these subcontracting grievances followed immediately on the heels of one of G.E.’s “peak periods” for maintenance jobs. For two-to-three weeks in the summer and again for two-to-three weeks in late December/ early January, G.E. shuts down its production operations at the Cicero facility. It is during these shutdowns or “peak periods” that G.E. performs its major maintenance projects. G.E. often employs subcontractors to perform some of the many individual jobs involved in these major maintenance projects, which include servicing and replacing production machinery, installing and repairing heating units, and the like.
In pursuing one of its shutdown-related grievances in 1982, the Union requested a variety of information regarding the challenged subcontracts, including the “cost per man hour of work.” In response, G.E. reiterated its “exclusive right to subcontract” contained in the CBA, and the matter appears to have ended there.
This case finds its genesis in a similar grievance filed in January, 1987. Again, the Union was grieving G.E.’s subcontracting during the late December/ early January shutdown. G.E. scheduled 64 maintenance jobs for that peak period in 1986-87. All but 12 of these jobs were designated by G.E. as “Priority 1,” which meant that they could be done only during shutdown and that cost was irrelevant. A few of the other jobs were designated “Priority 2,” which meant that they “should” be done during shutdown and that doing them during production would entail “greater cost.” The remaining jobs had no priority designation.
About 60 of the 64 scheduled jobs actually were performed during the 1986-87 shutdown. G.E.’s regular employees performed about 46 of them, subcontractors performed about 11, and the remainder were performed by both G.E. employees and subcontractors. Although there was conflicting testimony before the ALJ as to *1166 how many of the 11 subcontractor jobs could have been performed by G.E.’s regular maintenance employees, that number is no greater than three. Also, the record reveals that the vast majority of unit maintenance employees who were not on vacation during the 1986-87 shutdown worked overtime on the maintenance projects performed during that shutdown, and that all 11 of G.E.’s regular production employees who asked to work on the maintenance projects were brought over to help out.
On January 2, 1987, the Union filed a grievance protesting G.E.’s subcontracting during the 1986-87 shutdown. The grievance demanded that G.E. furnish the Union with a list of the subcontractors used, the jobs they performed, the cost of the individual jobs, and the identity of the bidders on these jobs. On January 16, G.E. and the Union held a “second-step” meeting on this grievance. (The CBA provided for a three-step grievance procedure, after which the grievance could go to arbitration if it involved an arbitrable matter under the CBA. Subcontracting was specifically exempted from the scope of arbitration.) At the second-step meeting, G.E. defended its decision to subcontract on the following grounds: its consistent and longstanding practice, protected by the CBA, of subcontracting during peak periods; all unit maintenance employees already were working at full capacity during the shutdown; much of the work had to be done during shutdown; and regular maintenance employees lacked the skills, knowledge and/or tools to perform some of the jobs.
At the subsequent third-step meetings held in February, 1987, G.E. basically repeated these same factors in defense of its decision to subcontract. At these meetings, G.E. provided the Union with some of the requested information, but refused to provide cost data. G.E. specifically and consistently asserted that cost data was irrelevant both to its decision to subcontract and to the Union’s grievance protesting that decision. For its part, the Union asserted that G.E. should hire more maintenance employees, alleging that G.E. effectively had “replaced” unit maintenance employees with subcontractors by allowing attrition in the ranks of the maintenance employees. Union officials also asserted that they wanted G.E. to stop its practice of subcontracting altogether, that the Union had a right to all of the requested subcontracting information, and that without the cost information the Union would be unable to continue with the grievance procedure. At the meeting on February 12, the Union representative, in response to a question from G.E. as to why the Union needed the cost data, included in his answer the need to prepare for “upcoming negotiations.” Board Decision, ALJ Decision at 12-14. 1
It soon became clear to the Union that the cost data it wanted would not be forthcoming from G.E. Because arbitration was unavailable, the Union took its demand to the NLRB. The Union filed an unfair labor practice charge on February 27, 1987, alleging that G.E. unlawfully had refused to provide it with “information concerning certain subcontracting ... which is necessary to enable the [Union] to carry out its functions under the current collective bargaining agreement and the Act.” In July, 1987, the Board’s General Counsel issued a formal complaint based on the Union’s charge and set the matter for hearing before an AU.
The ALJ hearing on the Union’s charge took place in November, 1987. At that hearing, G.E. officials testified specifically that cost has never been a factor in G.E.’s CBA-protected decisions to subcontract, citing instead the reasons G.E. consistently offered to the Union, including especially that unit maintenance employees lacked the *1167 skills, equipment and/or time to do the subcontracted jobs. Union officials, for their part, repeated their demand for the cost data, and one Union official testified that in pursuing grievances he “continuously” heard from G.E. representatives in defense of their subcontracting and other business decisions “the rhetoric that [G.E.] has to be competitive.” Id. at 14.
Unsatisfied with G.E.’s stated reasons for subcontracting, the AU pressed G.E.’s representatives on this issue, and by so doing elicited the following additional evidence: 1) subcontracts are included in G.E.’s overall maintenance budget; 2) G.E. accepts competitive bids on subcontracts; 3) an internal G.E. worksheet used during the 1986-87 shutdown contains dollar entries as to the cost of some subcontracted jobs; 4) another internal G.E. worksheet used for a subcontracted janitorial job in 1982 includes an entry noting that the job was less costly if done by a subcontractor; 5) G.E. had a policy of retaining the number of regular maintenance employees needed on average rather than the number needed during peak periods at least in part because to do otherwise would be very inefficient and costly; and 6) at least one job was performed during the 1986-87 shutdown instead of during a produetion-time weekend because of cost considerations.
Citing this evidence, the AU concluded that G.E.’s contention that comparative labor cost played no part in its decisions to subcontract was a ruse. Based largely on the Union representative’s testimony concerning what he “continuously” heard at grievance meetings, the AU rejected in a footnote G.E.’s argument that it had no obligation to turn over the information because it never raised cost as a defense. Id. at 23 n. 23. The AU also concluded that the requested cost information was sufficiently relevant both to “forthcoming contract negotiations” and to “at least part of bargainable portions of the subcontracting grievance” that its production was required. In another footnote, the AU rejected G.E.’s argument that the proffered “negotiations” rationale for the Union’s request was premature and in bad faith, finding that preparation for negotiations was “among the purposes” for which the Union wanted the information. Id. at 24 n. 25. Finally, the AU concluded, as a kind of fallback position, that even if the Union did not give G.E. a sufficient, relevant reason for the information demand at the time it was first made, the fact that G.E. was apprised at the hearing that the information was “relevant for grievance-processing purposes” was enough to make G.E.’s “continuing refusal” to supply the information an unfair labor practice.
In a four-page decision and order, the Board summarily affirmed the AU’s rulings, findings and conclusions. Notably, however, the Board did not affirm or rely on the AU’s conclusion that G.E. was required to provide the information because it was relevant to the processing of the subcontracting grievance. Rather, the Board based its decision that G.E. had committed an unfair labor practice solely on the finding that the requested cost information was relevant to the negotiation of a successor agreement to the 1985-88 CBA. Board Decision, slip op. at 1-2. The Board ordered, among other things, that G.E. immediately furnish the Union with the requested cost information.
From this Board decision and order G.E. filed a timely petition for review in this court. The Board has cross-petitioned for enforcement of the order, and the Union has intervened. We have jurisdiction over G.E.’s petition, and over the Board’s cross-petition, under §§ 10(e) and (f) of the Act, 29 U.S.C. §§ 160(e) and (f).
II
As part of their duty to bargain in good faith, employers must often provide information requested by their bargaining adversary.
See NLRB v. Acme Indus. Co.,
The primary requirement to trigger an employer’s duty to turn over requested information is that the information be relevant to the union’s performance of its duties to administer and police the CBA or to negotiate a new CBA (or both).
See Acme Indus.,
In this case, the Board’s conclusion that G.E.’s duty to bargain in good faith required it to provide the cost data had two operative parts. First, the Board concluded that the Union’s demand was sufficient to trigger G.E.’s duty. Second, the Board concluded that costs were sufficiently relevant to require the provision of the requested data. These were primarily factual determinations, and as such they are conclusive if they are supported by substantial evidence in the record as a whole. 29 U.S.C. § 160(f);
Universal Camera Corp. v. NLRB,
Employing these standards, we determine that neither part of the Board’s ruling can withstand review.
A. The Union’s Demand
As mentioned above, the Board modified the AU’s ruling as to the valid grounds for the Union’s demand, relying only on the Union’s claim that the cost information would help it prepare for the next round of contract negotiations. The record reveals that this ground was first advanced by the Union at the third-step grievance meeting on February 12,1987. The CBA in force at that time was not due to expire until June 26, 1988, and thus had over sixteen months yet to run. Further, according to the CBA, the earliest date at which either party could serve notice that it wished to terminate or modify the CBA, and thus the earliest date at which bargaining could commence, was March 26, 1988: thirteen months after the Union’s demand.
See Board Decision,
AU Decision at 7-8. The Board dispensed with this timeliness problem as follows: “We find that the Union had specifically referred to this [negotiations] use of the information in its request, and that,
at least by the time of the hearing in this case,
those negotiations were sufficiently close at hand to require [G.E.] to provide the information.”
Id.,
slip op. at 1-2 (emphasis added). The Board cited in support
Barnard Eng’g Co.,
We begin by rejecting the Board’s premise that the relevance inquiry allowed it to consider the state of affairs “by the time of the hearing” in assessing G.E.’s refusal to turn over the information. G.E. denied the Union’s one-time demand for cost information in January/February, 1987. To determine whether this action was an unfair labor practice, the Union’s proffered reasons for demanding the information, as well as G.E.’s motives for refusing that demand, must be examined as of the time of the demand and refusal.
Cf. New York Printing Pressmen and Offset Workers Union v. NLRB,
*1170
Properly understood, neither
Barnard Eng’g,
nor the other cases cited to us by the Board in defense of its suggested “continuing refusal” argument, suggest otherwise. In
Barnard,
the AU ruled, and the N.L.R.B. affirmed, that the employer’s failure to provide the requested information was a violation because the union had, at the time it made its requests, sufficient facts to support its stated reason for needing the information and a sufficient basis for seeking it (to determine whether to file a grievance).
Assessing the Union’s demand when made, the record as a whole establishes that it was insufficient to trigger G.E.’s duty to provide the information. The context in which the demand was made is telling: the Union was pursuing one of its many, non-arbitrable grievances concerning shutdown subcontracting. Although we accept the AU’s and Board’s determination that the Union added to its primary grievance-related purposes the need to prepare for “upcoming negotiations,” we cannot accept the conclusion that the addition of this rationale was sufficient standing alone to require G.E. to turn over the cost data. The demand was made over a year before bargaining could begin. The CBA did not provide for mid-term bargaining, nor does the record contain any evidence (i.e. specific testimony, bargaining history, etc.) that the parties nonetheless had begun to negotiate over a new contract or were preparing in earnest for such negotiations.
Cf. San Diego Newspaper Guild,
B. The Relevance of Cost
Even if we accept the Board’s “continuing refusal” argument or otherwise accept the Union’s demand as timely and sufficient, enforcement of the Board’s order must be denied because the record as a whole fails to support the Board’s conclusion that subcontracting costs were sufficiently in issue to require the disclosure of the cost data. The Board ruled that the cost information was relevant to the Union’s proffered negotiation purpose because the record established that cost factors played a “clear role” in G.E.’s subcontracting decisions. On that basis, the Board found no merit in G.E.’s contention that it was not required to provide the cost data even for negotiation purposes because it never raised costs in defense of its subcontracting practices. Board Decision, slip op. at 2-3. A full review of the precedents and the record reveals these conclusions to be unreasonable and unsupported.
Some information requested by unions is “presumptively relevant” because it relates directly to unit employees and their conditions of employment and therefore goes to the core of the employer-employee relationship.
See WCCO Radio, Inc. v. NLRB,
In this case, the Union demanded the dollar amounts that G.E. paid to outside subcontractors for certain jobs, information relating to a non-arbitrable, non-bargaining unit activity that G.E. had insured its right to continue with each successive CBA. Neither the Union nor the Board has endeavored to show that this information relates to “the core of the employer-employee relationship.” Thus, the requested cost data does not fall within the presumption, and the Union had the burden to establish relevancy.
Western Massachusetts Elec. Co. v. NLRB (“WEMECO”),
One would expect the Union to attempt to meet this burden by coming forward with evidence that G.E. at some point raised cost in defense of its subcontracting practice, either in the context of defending grievances or of bargaining to retain subcontracting as a management right in the CBAs. Indeed, some support exists for the notion that the Union was
required
to make such a showing.
WEMECO,
Viewed as either a requirement or as the most relevant consideration, that G.E. raised costs as a defense to subcontracting is not supported by the record. The testimony and documentary evidence in this case reveal that at no time in the grievance process did G.E. offer comparative cost as a defense. Instead, G.E. consistently offered other reasons or defenses, including especially that unit maintenance employees lacked the time, skills or tools to do the jobs, most of which could only be done during shutdown. The AU and (apparently) the Board rejected this evidence based primarily on the Union representative’s testimony that G.E. had at many, unspecified times in the past stated at meetings concerning grievances that it needed to stay “competitive.” As we have held in an analogous context, however, an employer’s general statements about “competitive disadvantage” cannot be transmogrified into an explicit evocation of cost as a defense, thereby triggering the employer’s obligation to turn over financial data.
Harvstone,
This failure of proof is not ameliorated by the other evidence adduced by the AU as to G.E.’s budgetary and record-keeping practices. The two internal worksheets examined and relied upon by the AU, one of which referred to an unrelated, nonunit project in 1982, establish nothing other than the wholly unsurprising fact that G.E. keeps track of the costs on its subcontracted jobs, as well as on the overall maintenance projects. Further, there is no evidence that in granting a project a priority designation (i.e. “should do during shutdown/ can do at another time but greater cost”), G.E. was referring to the comparative cost of using regular maintenance workers versus subcontractors, as much as the costs associated with attempting the project during production versus during shutdown. 9 Similarly, that G.E. endeavors to complete its projects “within budgetary constraints” and that it takes bids on subcontracted jobs are insufficient to support the Board’s decision to presume comparative labor cost-driven subcontracting in the absence of an evocation of this defense by G.E.
Were it simply that the evidence established a set of reasons that G.E. raised and/or relied upon in deciding to subcontract some jobs during shutdown and the Board picked cost as an operative one, we, of course, would defer.
See Universal Camera,
*1174 III
In January-February, 1987, the Union demanded that G.E. turn over, among other things, cost data on certain subcontracts. The record as a whole reveals that, at the time the demand for the financial information was made, G.E. had every right to refuse it: the Union’s demand was premature and uncompelling, and comparative subcontracting costs were not on the table. Thus, for the reasons more fully explained above, the Board’s finding that G.E. violated sections 8(a)(5) and 8(a)(1) of the Act by refusing to disclose the requested cost data was unreasonable and unsupported by substantial evidence. Accordingly, G.E.’s Petition for Review is Granted, and ENFORCEMENT of the Board’s order is Denied.
Notes
. G.E.’s representative at the February 12 meeting later testified before the ALJ that he "did not hear” the Union representative raise at that meeting future contract talks as a reason for wanting the cost information. The ALJ, however, chose to credit the Union representative’s testimony that he did so state. Id. at 13 n. 7. As the ALJ was in a better position than we to make such credibility determinations, we accept her finding, and will assume that at the February 12 meeting the Union representative raised the negotiation of future contracts as one reason for the Union’s request for cost information.
. A union’s request for information must also be "bona fide” and made in “good faith.”
See J.I. Case Co. v. NLRB,
Further, in some cases, a union’s asserted need for relevant information must be balanced against an employer's asserted confidentiality interests.
See Detroit Edison,
. The Board's footnote explaining the concurring view of panel member Cracraft on this issue is revealing. The footnote states, “Member Cracraft believes that the request for information at [the time it was made during the grievance meeting] was not premature,” and therefore she did not find it necessary to rely on Barnard and the "by the time of the hearing” notion. Board Decision, slip op. at 2 n. 3. By negative implication, this statement appears to admit that the other two Board members believed the request was premature when made, and therefore found it necessary to revert to their reading of Barnard.
. We also note that there is no evidence in this case that the Union ever renewed its request for cost information linking it more closely, both in time and purpose, to contract negotiations. Although it is true that unions, like employees, are generally “not required to request ... data on more than occasion or hound the employer when the information is not produced,"
Harvstone Mfg.,
. Contrary to the Board’s suggestion, our holding in
II. Case Co. v. NLRB,
An examination of these three statements reveals that our holding here is not in conflict with our holding in I.I. Case. In the first statement, we pointed out that the union there had a valid, compelling purpose for information related to the "continuing process” of administering the CBA apart from any pending wage negotiations; in this case, the Board has limited the Union’s valid purposes to negotiations. Second, we do not today rely on the lack of evidence of pending negotiations as our “sole consideration," as our analysis makes clear. Third, unlike in I.I. Case, the record in this case is devoid of evidence that G.E. and the Union were "actually preparing for contract negotiations."
. This reading of
WEMECO
was ratified by the First Circuit in
NLRB v. Davol, Inc.,
. We note that there is some disagreement among the parties on this issue. G.E., unsurprisingly, argues that the Union was required to show that G.E. raised costs. The Board, in its brief, appears to agree, as it states at one point that "the question is whether [G.E.] raised cost as an issue.” Board Brief at 25. The Union, for its part, argues that it need not generally be shown that the employer raised cost as a defense to make cost information relevant. Our resolution immediately following obviates the need to resolve this debate.
. The Board’s attempt to distinguish these
Southwestern Bell
cases on factual grounds is unconvincing.
See Board Decision,
slip op. at 3 n. 4. We also note that the Board’s reliance on
NLRB v. Westinghouse Broadcasting and Cable, Inc.,
. The same can be said of the evidence that G.E. scheduled one job for shutdown rather than for a weekend during production.
