General Electric Company v. Litton Industrial Automation Systems, Inc. And Litton Industries, Inc.General Electric Company v. Litton Industrial Automation Systems, Inc. And Litton Industries, Inc.
This is an action brought by General Electric (“GE”) pursuant to the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA) of 1980, § 107(a),
I.
In 1959, Royal McBee Corporation opened a typewriter plant on a forty-acre plot in Springfield, Missouri. 2 From 1959 to 1962, Royal McBee dumped cyanide-based electroplating wastes, sludge, and other pollutants onto part of the forty-acre tract. Over time, these wastes migrated from the original dumping location, contaminating a larger area of land.
In 1965, Royal McBee merged with Litton Industries, Inc., and Litton became the surviving corporation. 3 The typewriter plant was closed in 1969, and in 1970 GE bought the plant and the surrounding land. In 1980, the Missouri Department of Natural Resources (“MDNR”) learned of the hazardous substances that had been dumped at the site and GE was notified. The MDNR and GE concluded in 1981 that there was no potential for groundwater contamination, and performed no cleanup work at the site.
In 1984, GE agreed to sell the vacant nineteen acres at the site (where the dumping had occurred) to Enterprise Park, a real estate concern that intended to develop the property for commercial purposes. In July 1985 the MDNR changed course and decided to propose that the site be placed on Missouri’s Registry of Abandoned and Uncontrolled Hazardous Waste Sites of Missouri. GE appealed this proposed registry, while Enterprise Park notified both GE and Litton of potential CERCLA claims. On three separate occasions from September 1985 to March 1986, the Missouri Hazardous Waste Commission held public meetings to discuss, among other things, the proposed registry of the GE site. In October 1985, the Missouri Department of Health (“MDOH”) stated that the contaminants in the soil at the site posed “a significant health threat and ... should be removed.” Appellants’ Appendix, vol. VIII, § 58, at 1861.
During that same month, GE hired OH Materials Company to investigate the site and conduct any response actions deemed necessary. In December 1985, the Envi
In late 1985 and early 1986 GE, the MDNR, and Enterprise Park negotiated a Consent Decree. The Decree called for the development and implementation of a cleanup plan for the site. It required any cleanup action to be consistent with the National Contingency Plan (“NCP”), EPA Superfund Programs,
Pursuant to their site investigation, OH Materials produced an analysis of several possible cleanup actions. Although the most expensive alternative, excavation was chosen as the best and most effective response action. Excavation began on October 13, 1986. On that day, three large drums were discovered buried at the site. Shortly thereafter, a trench was discovered, along with a fourth drum. This drum contained extremely hazardous substances. Excavation continued until December 7, 1986, when work was halted pending further site analysis. More excavation was performed in May 1987 and the cleanup was completed in December 1987.
Most of the soil was disposed of as a nonhazardous waste, minimizing cleanup costs. The drums and the more-contaminated soil were disposed of as hazardous wastes. In early 1988 the MDNR approved the cleanup of the site, withdrew the proposed registry, and stated that the site had been properly cleaned.
Even though Litton had been notified by both GE and Enterprise Park in 1985 about its potential CERCLA liability, Litton never participated in any of the investigation, evaluation, or cleanup of the site. In March 1987, while the cleanup was still in progress, GE made a formal demand on Litton asking it to indemnify GE for the cleanup costs. In June 1987 GE filed suit, seeking to recover its response costs for cleaning up the site. In August 1988 GE filed an amended complaint, seeking to recover its cleanup costs pursuant to § 107(a) of CERCLA,
Following a four-day bench trial in May 1989, the District Court found that there had been a release of hazardous substances, that Litton was responsible for the release, that GE’s response was necessary, and that GE’s cleanup actions met the provisions of CERCLA and the NCP. The District Court ordered Litton to pay GE more than $940,000 as reimbursement for the response costs incurred. The District Court also ruled that attorney fees were recoverable, and ordered Litton to pay GE more than $419,000 in attorney fees and expenses.
On appeal, Litton claims that 1) GE should not be allowed to recover its cleanup costs because the cleanup was induced by the threat of a lawsuit; 2) GE’s response was not consistent with the NCP; 3) the District Court erred in not apportioning some of the response costs to GE; and 4) the District Court erred in allowing GE to recover its attorney fees.
II.
Although couched in terms of causation, this argument is really an “unclean hands” defense to GE’s CERCLA claim. Litton asserts that GE failed to tell Enterprise Park of the known contaminants at the site
This argument is without merit. CERCLA is a strict liability statute, with only a limited number of statutorily-defined defenses available.
United States v. Aceto Agric. Chem. Corp.,
III.
Litton next argues that the mandate of
A.
The decision whether to characterize a response action as a “removal” action or a “response” action is determined by
the cleanup or removal of ... hazardous substances from the environment, ... the disposal of removed material, or the taking of such other actions as ... necessary to ... mitigate damage to the public health.... The term includes ... without being limited to ... fencing, ... provision of alternative water supplies, [and] temporary evacuation and housing of threatened individuals....
consistent with permanent remedy taken instead of or in addition to removal actions.... The term includes, but is not limited to, such actions ... as storage, confinement, ... neutralization, cleanup of ... contaminated materials, recycling, ... diversion, destruction, ... dredging or excavations, ... [and] onsite treatment. ... [T]he term includes offsite transport and offsite storage, treatment, destruction, or secure disposition of hazardous substances....
42 U.S.C. § 9601(24) .
We agree with the District Court’s determination that GE’s action can be characterized as a removal action.
General Elec. v. Litton,
B.
As stated earlier, in order for removal action costs to be recoverable under
We agree with the District Court’s determination that GE “implemented the removal action consistent with
Third, an evaluation of potential response actions was prepared by OH Materials for GE. The District Court found that “OH Materials produced a Remedial Alternatives Evaluation for the site [“RATE report”] ... which analyzed several alternative response actions.”
General Elec. v. Litton,
We are satisfied that the thorough evaluation that was performed here is consistent with the NCP; specifically, with
GE’s response time also was consistent with the NCP’s removal action guidelines. The MDNR proposed registry of the site on the hazardous waste sites listing in July 1985. In December 1985 the EPA found that the wastes at the site constituted a threat to the environment. By this time GE had hired OH Materials to assess the site and develop possible alternative responses. The RATE report was completed in February 1986. After further consultation with the state, the excavation began in October 1986. We hold that such a response time is consistent with the NCP’s requirement to begin the cleanup in an appropriate manner as soon as possible.
Finally, excavation of the site is consistent with the NCP, as
We hold that GE’s response can be characterized properly as a removal action, was warranted by the hazardous conditions at the site, and was consistent with the NCP guidelines governing removal actions. Therefore, the costs associated with GE’s response action are recoverable under
IV.
Litton argues that even if it can be held liable under
As noted earlier
It was not until after the final cleanup work was performed in November 1987 that the site met the state-imposed standards and the state approved the cleanup. All of the cleanup work performed was necessary to meet the state standards. Since
V.
Finally, Litton argues that the District Court erred in awarding GE attorney fees and expenses. Litton asserts that CERCLA does not allow explicitly for private parties to recover litigation expenses and therefore, under the American rule, each side must pay its own litigation costs.
The general rule is that “the prevailing litigant is ordinarily not entitled to collect a reasonable attorneys’ fee from the loser.”
Alyeska Pipeline Co. v. Wilderness Soc’y,
As noted earlier,
Litton also questions whether the attorney fees awarded here are reasonable in amount. We give great deference to the District Court’s judgment in the award of attorney fees, because “the district court is best equipped to determine whether hours were reasonably expended [and] whether the attorneys’ hourly rates are within the general rates charged ... in the relevant community.... ”
Moore v. City of Des Moines,
Based on our reading of the statute, we find no error in the ruling of the District Court that CERCLA allows a private party to recover its attorney fees and expenses incurred in bringing a cost-recovery action pursuant to
VI.
We affirm the judgment of the District Court awarding GE the reasonable and necessary costs of its cleanup, including the attorney fees and expenses incurred in bringing this cost-recovery action.
Notes
. The Honorable Russell G. Clark, United States District Judge for the Western District of Missouri. Judge Clark’s opinion is published as
General Elec. Co. v. Litton Business Sys., Inc.,
. This land will be referred to in this opinion as “the site.”
.Royal McBee’s assets were acquired by a wholly-owned subsidiary of Litton which later was merged into a surviving corporation called Litton Industrial Automation Systems, Inc. For purposes of this opinion, “Litton" refers to both Litton Industries, Inc. and Litton Industrial Automation Systems, Inc. The judgment of the District Court as amended November 1, 1989, runs against both of these corporations.
. Litton argues that the removal action issue was never introduced by GE, nor decided upon by the District Court. On the second point, Litton is clearly wrong, as evidenced by the following passage: "The Court finds that GE’s action was consistent with the NCP as a removal action."
General Elec. v. Litton,
.
. We note that after Litton/Royal McBee stopped dumping the chemical wastes at the site in 1962, it dumped the same wastes at the Fulbright Landfill in Springfield from 1962 to 1968.
See General Elec. v. Litton,
. Having found that GE’s response was a removal action, we do not need to reach the issue of whether the response met the NCP remedial action guidelines. Similarly, as Litton’s claim that it was denied due process is predicated on the assertion that GE’s action was a remedial action, this claim also becomes moot.
. Litton’s related apportionment argument based on
. Litton argues that GE went "above and beyond the call of duty” when cleaning the site to satisfy its Settlement Agreement obligations to Enterprise Park. That agreement, however, only obligated GE to clean the site so that it would not be placed on the state hazardous site registry. Appellants' Appendix, vol. VII, § 35, at 158). To keep the site off of the registry, GE had to meet the state cleanup standards, which is what
. We are not aware of any other circuit court ruling on this issue. We note that various district courts have split on this question. Besides the District Court in this case, this issue was decided in
Pease & Curren Ref., Inc. v. Spectrolab, Inc.,