35 Pa. Commw. 32 | Pa. Commw. Ct. | 1978
Opinion by
General Electric Company lias petitioned for review of decisions of the Unemployment Compensation Board of Review awarding unemployment compensation benefits to the claimants in two test cases involving 155 General Electric Company employees. The Board concluded that the claimants’ unemployment was not due to a stoppage of work which existed because of a labor dispute, within the meaning of Section 402(d) of the Unemployment Compensation Law, Act of December 5,1936, Second Ex. Sess., P.L. (1937) 2897, as amended, 43 P.S. §802(d).
Since, in accordance with the holding of California Department of Human Resources Development v. Java, 402 U.S. 121, 28 L.Ed. 2d 666 (1971), these claimants were paid unemployment compensation benefits immediately following the initial determination of their eligibility our decision will determine only whether General Electric’s reserve account in the Unemployment Compensation Fund is charged with the monies paid to the claimants in these cases.
General Electric Company’s Philadelphia facility houses a production process known as the Metal Enclosed Switchgear (M.E.S.) operation. This operation produces large electric switchgears and consists of the fabrication of steel to specification and the assembly of the switchgear, including wiring, testing, inspection, needed rewiring and shipping. The M.E.S. operation is an assembly or production line, the flow; of which is as follows: The process begins in the fabrication shop where the steel is cut to the proper, shape for switchgear doors and punched with holes for the instruments which will be later attached. After the doors are painted, they may go to one of several different shops, depending upon, the customer’s specifications. For .example, an instrument door would remain in storage until the subassembly wiremen could
On March 15, 1972, approximately 80 wiremen and assemblers who comprised the top plate assembly and the final assembly units commenced a strike as the result of a labor dispute. The effect of this work stoppage, which continued until May 1, 1972, was the complete cessation of production in those two areas. When the strike began, the fabrication shop and sub-assembly workers, the so-called “upstream” workers who are the claimants in No. 1313 C.D. 1975, continued to work for about three weeks after the strike began but were then laid off by General Electric. The claimants in No. 1312 C.D. 1975 are the so-called “downstream” workers who perform the testing, inspecting and expediting functions in the M.E.S. operation. To a large extent, their duties are performed either during or after the final assembly unit has worked on the particular item. These claimants worked for several days after the commencement of the strike and were then laid off by the company. All of the claimants and the strikers were members of International Union of Electrical Workers Local 119.
The “upstream” and “downstream” workers applied individually for unemployment compensation benefits. The Bureau of Employment Security consolidated the cases into two representative groups: the Binder group which is comprised of the claimants who worked in upstream jobs, and the Saddie group made up of those claimants employed in downstream
Section 402(d) of the Unemployment Compensation Law, 43 P.S. §802(d) provides:
An employe shall be ineligible for compensation for any week—
(d) In which his unemployment is due to a stoppage of work, which exists because of a labor dispute (other than a lock-out) at the factory, establishment or other premises at which he is or was last employed: Provided, that this subsection shall not apply if it is shown that (1) he is not participating in, or directly interested in, the labor dispute which caused the stoppage of work, and (2) he is not a member of an organization which is participating in, or directly interested in, the labor dispute which' caused the stoppage of work, and (3) he does not belong to a grade or class of workers of which, immediately before the commencement of the stoppage, there were members employed*37 at the premises at which the stoppage occurs, any of whom are participating in, or directly interested in, the dispute.
Since the claimants and the striking workers belonged to the same Local, we need not concern ourselves with the proviso to this section. We need only determine whether the Board erred in concluding that the claimants’ unemployment was not due to the work stoppage which existed because of a labor dispute other than a lockout.
In its decision with respect to the upstream workers, that is, fabrication shop and subassembly employees, the Board made the following findings of fact:
8. The relationship of the various operations in the M.E.S. operation is such that all products must proceed through the Final Assembly Unit and many products must proceed through the Top Plate Assembly Area and from there they eventually proceed to the Final Assembly Unit.
9. From the Final Assembly Unit all products proceed to the Finish Paint Shop and then to the Shipping Department.
10. The claimants involved in this appeal were employed in the fabrication shop, in pre-assembly work, and in the storage rooms; claimant Binder was employed as a punch press operator in the fabrication shop.
11. The work done in the fabrication shop, in pre-assembly work and in the storage rooms proceeds eventually to the Final Assembly Unit.
12. After the commencement of the work stoppage involving the wiremen and the assemblers, claimant Binder continued to work.
13. Due to the work stoppage by those in the Top Plate Assembly Area and Final Assembly*38 Unit, work which proceeded from the other areas and units could not he economically and efficiently processed; a production imbalance resulted.
14. The. fabrication shop employees continued to work until the employer determined that from an inventory cost standpoint it was not economically feasible to. continue work in the fabrication shop; claimant Binder was laid off on April 14, 1972 because of the economic decision of the employer to lay the claimant off.
15. Continuing work was available to the claimant in the fabrication shop if the employer had not made the economic decision to lay the claimant off.
With respect to the downstream workers performing tests, inspecting and expediting functions, the Board made the following findings:
7. The claimants and the wiremen and assemblers work in the metal enclosed switchgear (M.E.S.) operation of the employer.
8. The relationship of the various operations in the M.E.S. operation is such that all products must proceed through the Final Assembly Unit and many products must proceed through the Top Plate Assembly Area and from there they eventually proceed to the Final Assembly Unit.
9. From the Final Assembly Unit all products proceed to the Finish Paint Shop and then to the Shipping Department.
10. The claimants involved in this appeal were employed as testers, quality control workers and expeditors; claimant Saddie was employed*39 as a tester working throughout the M.E.S. operation.
11. The work done by the testers and the work done throughout M.E.S. operation proceeds eventually to the Final Assembly Unit.
12. After the commencement of the work stoppage involving the wiremen and the assemblers, claimant Saddic continued to work.
13. Due to the work stoppage by those in the Top Plate Assembly Area and Final Assembly Unit, work which proceeded from the other areas and units could not be economically and efficiently processed; a production imbalance resulted.
14. Claimant Saddic continued to work until the employer determined that from an inventory cost standpoint it was not economically feasible to continue employing the testers; claimant Saddic was laid off on March 21, 1972 because of the economic decision of the employer.
15. Continuing work was available to the claimant if the employer had not made the economic decision to lay the claimant off.
16. Some of the testers including the claimant, were recalled to work during the work stoppage.
It is clear that these findings of fact are supported by substantial evidence in the record—with the notable exceptions of finding No. 15 made in the upstream workers case, and findings No. 15 and No. 16 made in the case of the downstream workers. Insofar as these three exceptional findings imply that the M.E.S. production line continued to operate after the strike and that its continued operation made work available,
Findings No. 15 and No. 16 in the downstream workers’ case that continuing work was available to the downstream workers and that some of them, testers, were recalled to work during the work stoppage, if read as suggesting that there was M.E.S. production line work for these workers, are also without support on the record. There is indeed evidence that some of the testers who had been laid off because of the work stoppage were for awhile called back to work during the strike. It is clear as crystal, however, that this work was not in the M.E.S. operation.
The findings of the Board which are supported by the evidence show that the M.E.S. was a continuous integrated production line and that the strike made the continued operation of any part of the line infeasible. These findings and the cases of Unemployment Compensation Board of Review v. National Valve & Manufacturing Co., 19 Pa. Commonwealth Ct. 565, 339 A.2d 137 (1975); Rusynko Unemployment
A second reason advanced by the Board as supporting its conclusion that the downstream workers were laid off for reasons other than the strike was that “some of the testers, including the claimant, were recalled to work during the work stoppage.” As we
Finally, the Board notes the testimony of witnesses that there was work available at the employer’s facility where these claimants were laid off. The question in this case, however, is not whether there is work available anywhere in the employer’s operation, bnt solely whether the claimants’ unemployment was due to the work stoppage created by the strike. In Unemployment Compensation Board of Review v. Tickle, 19 Pa. Commonwealth Ct. 550, 560, 339 A.2d 864, 869 (1975), we specifically held “that the phrase, ‘stoppage of work which exists because of a labor dispute,’ as used in Section 402 of the Act, means any cessation of work by an employe due to a labor dispute, irrespective of whether or not continuing work is available.”
The principle that the fact that an employer’s decision to lay off or call back employees as the result of a work stoppage caused by a strike is economic will not render the employees eligible for .unemployment benefits is illustrated by the General Motors Corporation Unemployment Compensation Cases, 9 Pa. Commonwealth Ct. 221, 306 A.2d 399 (1973). There, the claimants were employed in General Motors’ West Mifflin stamping plant where subassembled component parts of automobile bodies were produced for shipment to other assembly plants. Following settlement of a nationwide strike against General Motors, the claimants were not immediately recalled because the assembly plants to which the West Mifflin plant’s products were shipped were still on strike. The employer’s reason for not immediately recalling the claimants was that in the absence of a place to send the fabricated parts, the plant would be simply building unneeded inventory. We held that General Mo
It is well settled in unemployment compensation cases that a reasonable business decision to lay off employees made in good faith by the employer in the context of a labor dispute does not qualify those employees for unemployment compensation benefits. Since there is no evidence of bad faith in General Electric’s actions in laying off these claimants, we hold that Section 402(d) is applicable to render these claimants ineligible for compensation.
Order
And Now, this 18th day of April, 1978, the orders of the Unemployment Compensation Board of Review in Nos. 1312 C.D. 1975 and 1313 C.D. 1975 are hereby reversed.