241 F. 38 | 6th Cir. | 1917
The General Electric Company sued the Chattanooga Coal & Iron Corporation for the purchase price of a turbo-compressor, or blowing engine, manufactured by plaintiff for use in connection with defendant’s blast furnace, under contract between plaintiff and the receiver of defendant’s predecessor corporation, which contract defendant assumed. Defendant refused to accept the machine, because not completed within the time contracted for. By agreement between the parties, plaintiff sold the machine, realizing $4,000 less than its contract price, and for this sum recovery was asked.
At the conclusion of the testimony defendant moved for directed verdict in its favor, which was refused, and the case submitted to the jury under a charge to which no exception was taken. As construed by the court, the original contract provided for the delivery of the completed machine f. o. b. Lynn, Mass., on or before January IS, 1913. The machine was not actually ready for shipment until April 28th following, and was never shipped; defendant having refuses! to receive it. By the charge the verdict was made to turn upon questions relating to alleged waiver by defendant of the time of completion and shipment and reasonable time for performance. There was verdict for defendant, on which judgment was entered. The errors assigned relate only to the refusal to direct verdict and the denial of a motion for new trial, which, so far as reviewable, raises no questions except those involved in the refusal to direct verdict.
“In case of delay by the purchaser, shipment shall be extended for a reasonable time, based on period of purchaser’s delay and1 conditions at the factories of the company.”
And plaintiff claims that it was not until November 12, 1912, that it received from defendant the complete instructions necessary for building the blower. Jf this is so, it ends the defense, for plaintiff was ready to ship within 6% months from that time. But we cannot review the court’s conclusion "in this regard because of defendant’s testimony, which was competent in view of the general and obscure language of the written contract, that there were in fact no instruc
“The evidence as to the way in which this contract has been construed by the parties, shown by their correspondence, the testimony of the witnesses, and otherwise, leaves it undisputed that the parties understood that the machine was to be shipped on or before January 15, 1913, 6% months after the contract was finally approved by the plaintiff.”
Defendant, having meanwhile heard nothing further, on December 3d urged completion and shipment, again: calling attention to the lack of reserve blower and saying that should there be delay in the installation of the new machine, “and one of our present engines break down, we will look to your company for reimbursement to cover loss' in output or profit in difference in tonnage, whichever way you wish to put it.’.’ On the next day, apparently before plaintiff’s receipt of the letter just referred to, defendant was notified that, “due to delay in drawings and congestion in shop, shipment of your turbo-blower will be delayed until March 1st,” to which, on December 5th, defendant replied, protesting and expressing surprise, saying:
“This is not at all satisfactory to us, for, as previously explained to you, we liave no surplus blowing power, and, should one of our engines bréale down, our output would be greatly reduced. When we placed the order with your company, it was with the assurance that delivery would be made*41 not laier than the-middle of January, and we have made our arrangements accordingly. We therefore insist that you stand by delivery promised. Handle tliis matter vigorously with your home oflice and advise us further on the subject, as we expect you to protect us in the event we have a breakdown.”
0 Seven days later defendant was advised that plaintiff could not ship before March 1st. On, January 3d defendant again asked for report of progress made, and on the same day (apparently before the letter just mentioned was received) plaintiff wrote defendant that:
“Duo to both suction and discharge heads being scrapped, we will not be able to make shipment before March 15th.”
On February 14th defendant was notified that delivery might be again delayed beyond March 15th, on account of certain defective castings; on March 3d that, “owing to the loss of the two diaphragms/’ the machine could not be tested before March 25th, adding that “unforeseen troubles have continually developed, hut I trust this is the last one”; and on March 21st wrote that the equipment was being-assembled for test, which it was thought would begin by March 31st, and if satisfactory, and no changes required, shipment might be made by April 15th. On April 16th defendant was again notified that shipment was expected to he made on April 18th.- Defendant, having meanwhile received no notice that the machine was shipped, on April 23d or 24th inquired of plaintiff whether shipment had been made, and on the 25th was advised that it had not yet been shipped, but that shipment would be made on April 30th. Defendant then notified plaintiff not to1 ship the machine and that it canceled the contract.
In our opinion the broad proposition that, in every case where performance on the exact date fixed by an executory contract has once been waived, neither party can rescind on account of delay, without first giving notice requiring performance within a reasonable time specified, is not fortified by authority. In Taylor v. Goelet, 208 N. Y. 253, 258, 101 N. E. 867, Ann. Cas. 1914D, 284, general language, perhaps susceptible of such import, is used. But the facts of that case and the point in issue do not call for it, and we are cited to and have found no authorities sustaining it as applied to the facts before us.
The distinctive features of this case, at least according to the tendency of the evidence, are that time was of the essence of the original contract; that the time of performance has not been postponed because of defendant’s further requirements or in its interest or at its request; that the delay was against both its interest and its protest; that it has had neither possession nor benefit of the machine, and thus is not liable on a quantum meruit; and that the question presented is merely one of right to rescind, as raised in an action at law. The clause “whichever way you wish to put it,” in the letter of December
Were the letters of June 26th and November 2d alone to be taken into account, it would perhaps be difficult to avoid the conclusion that defendant had intended to extend indefinitely the time of performance, relying upon plaintiff’s responsibility for such damages as defendant might suffer from the delay, and that there had been not merely a succession of extensions of time of delivery to definite dates; but both these letters were written previous to any notification that delivery would be postponed beyond January 15th, and in the letter of December 5th, which was the first letter written after notice that delivery would not be made according to the contract, defendant, while insisting that it Would expect to be protected in the event of breakdown, yet also insisted that delivery be made by tire previously agreed date, and we find nothing in the correspondence subsequent to1 that time referring to the question of protection, or consenting, unless by silence alone, to further delay in shipment.
Being of opinion that the motion to direct verdict was not well taken, the judgment of the District Court is affirmed.