182 P. 444 | Cal. | 1919
Action on a bond given by a contractor to secure payment of claims for labor and material to be furnished in the construction of a building. Defendant appeals from a judgment in favor of plaintiff, a corporation that supplied certain materials for use in the building.
The bond in question had at its beginning the following words: "This bond is required by section 1183 of the Code of Civil Procedure, as amended in 1911, and must be equal to fifty per cent of the contract price; bond to laborers, materialmen, etc." By the terms set forth in the body of the instrument it is "expressly made to inure to the benefit of any and all persons who perform labor upon or furnish materials to be used in the work described" in the building contract. There is a further provision as follows: "Any and all such persons shall have and are given a right of action to recover upon this bond against the said principal and surety, or either of them, in any suit brought to foreclose mechanics' liens, which may be filed by such persons, or any *677 of them, upon the property mentioned in said contract, or in aseparate suit brought upon this bond, and may recover in such action or actions, the value of such labor done or materials furnished, or both." (The italics are ours.)
Defendant sets forth in its answer a special defense based upon the failure of respondent to file any claim of lien under the provisions of section 1187 of the Code of Civil Procedure. It was alleged that during the time within which a claim of lien might have been filed a large sum of money was due from the owner to the contractor which could and would have been applied to respondent's claim if the lien had been thus formally asserted. The court sustained a demurrer to this special defense and also on motion ordered it stricken out. These rulings are specified as erroneous. The question for this court to decide, therefore, is whether or not a materialman may sue on a bond, conditioned as is the one which is the basis of this action, without first duly filing a claim of lien.
Appellant insists that this is strictly a statutory bond, and that no liability arises upon it as a common-law obligation. The learned district court of appeal of the second appellate district agreed with appellant's view and reversed the judgment upon the authority of Miles v. Baley,
The first of these cases arose not under section 1183 of the Code of Civil Procedure, but under an act to secure the payment of the claims of materialmen, etc., employed upon public work. By the terms of the act it was made the duty of the contractorbefore entering upon the performance of the work to file the prescribed bond binding the sureties to pay for materials or labor, up to the amount specified therein, in case of the contractor's default "provided that such claims shall be filed" as thereafter required.
It appears in Miles v. Baley that the verified statement prescribed by section 2 of the act (Stats. 1897, p. 201) as a condition precedent to the maintenance of a suit upon the bond had not been filed by the claimant. Therefore the sureties on the bond were held not to be liable. Said section 2, after requiring that the materialman or laborer must file a verified statement of claims within thirty days from the time *678
when the work is completed, provides that "At any time within ninety days after the filing of such claim," the materialman or laborer "may commence an action against the sureties." This is the fundamental and essential difference between Miles v. Baley
and the case at bar. In that case the materialman under the plain terms of the statute governing the performance of the public work and the remuneration therefor was required to file his claim before and as a precedent condition to the maintenance of a suit on the bond. The section governing the materialmen in the case at bar (Code Civ. Proc., sec. 1183), contains no such restriction. Miles v. Baley, therefore, is not authority sustaining defendant's theory in the case at bar.Hubbard v. Jurian distinctly holds, however, that only those claimants who have duly perfected their liens within the statutory time are entitled to recover upon the bond given by section 1183 of the Code of Civil Procedure. Crane Co. v.Maryland Casualty Co.,
We are of the opinion that this construction gives an importance to section 1187 of the Code of Civil Procedure, and limits the rights of materialmen in a manner not contemplated by the legislature. Section 1197 of the same chapter clearly contemplates suits which may be maintained without the previous filing of liens, for it provides that: "Nothing contained in this chapter shall be construed to impair or affect the right of any person to whom any debt may be due for work done or materials furnished to maintain a personal action to recover said debt against the person liable therefor; . . . but the judgment, if any, obtained by the plaintiff in such personal action shall not be construed to impair or merge any lien held by said plaintiff under this chapter; provided, only, that any money collected on said judgment shall be credited on the amount of such lien in any action brought to enforce the same, in accordance with the provisions of this chapter." The bond by its terms creates a direct obligation on the part of the surety to pay for materials used in the construction of the building and the right of action on such bond is preserved by said section 1197 as well as by section 1183
It can no doubt be persuasively argued that the bond which must "be also conditioned for the payment in full of the claims of all persons performing labor upon or furnishing materials to be used in the work" relates to claims of lien *680 filed within time. But it seems to us that this is a strained interpretation. The mere use of the word "claim," which is as apt a description of the demand of the individual who has filed no claim of lien as it is of one who has filed such claim, is not persuasive.
It is to be noted also that the portion of the section (and of the bond which follows its terms), by which the rights of materialmen are safeguarded, does not use the word "claims" but the bond is made to "inure to the benefit of any and all persons who . . . furnish materials to be used in the work described" in the contract.
But there is another and a very strong reason for rejecting the theory that section 1187 of the Code of Civil Procedure restricts the terms of section 1183 of the Code of Civil Procedure, and makes them applicable only to those persons who have filed liens, and that reason is found in the history of the two sections and in the decisions of this court relating thereto.
Section 1187 was first enacted in 1872. At that time its introductory part was as follows: "Every original contractor, within sixty days after completion of his contract, and every person save the original contractor, claiming the benefit ofthis chapter, must, within thirty days after the completion ofany building, improvement or structure," etc., file his claim with the county recorder.
Section 1183 provided that persons furnishing labor or materials for the construction of buildings, etc., should have liens upon the buildings for the same, "but the aggregate amount of such liens must not exceed the amount which the owner would be otherwise liable to pay." In 1874 this section was amended by striking out the passage just quoted, the result of which was that the owner was liable for the entire value of labor and materials furnished for his building, regardless of the contract price. (Code Amendments 1873-74, p. 409.) At the same session section 1187 was amended, but the opening sentence containing the clause "claiming the benefit of this chapter" was not changed nor was any other material amendment inserted. Seeties 1183 was again amended in 1880 so as to provide that the lien should not be affected by the fact that no money is due or to become due on any contract made by the owner with a contractor. (Code Amendments 1880, p. 63.) In 1885 this court decided *681 that this section was unconstitutional so far as it made the owner liable for more than the contract price.
Thereupon in 1887, (Code Amendments 1887, p. 152), to obviate this difficulty as far as possible, the chapter was revised. Section 1183 was amended so as to provide for written contracts in all cases where the price exceeded one thousand dollars, and such contracts were required to be filed before the beginning of the work. Section 1184 fixed the provisions of the contract so that one-fourth of the price should be payable thirty-five days after completion and three-fourths in installments at specified times after the beginning of the work. Up to this time the entire chapter had contained no remedy for a laborer or materialman, except by filing a claim of lien and foreclosing the same. It follows that the words "claiming the benefit of this chapter" in section 1187 had no other scope or effect than to require the person who claimed a lien, to file the same within a specified time as there provided. The benefits of the chapter consisted solely in the right to foreclose a lien. In the amendment of 1887, for the first time, an additional remedy was given. Section 1184 provided that a laborer or materialman could at any time give the "stop notice" which has now become familiar and thereby intercept a payment and make the same applicable to his claim.
Notwithstanding this additional remedy, section 1187 was again re-enacted with some amendments, but the opening part thereof remained as before, that every person "claiming the benefit of this chapter" must within the specified time file his claim of lien. Had this provision been given its literal meaning, it would follow that no person could avail himself of the stop notice provided in section 1184 unless he also filed his claim of lien within the time specified in section 1187
Thereafter, in 1891, the decision in Bates v. Santa Barbara,
[2] According to familiar principles of statutory construction, this became the settled meaning of the phrase, and its subsequent continuation in future amendments of the same section should not be held to have changed its meaning in any particular.
It follows that the superior court properly sustained the demurrer to the special defense averred in the answer. The judgment is affirmed.
Melvin, J., Shaw, J., Olney, J., Wilbur, J., and Lawlor, J., concurred.
Rehearing denied.
Shaw, J., Melvin, J., Wilbur, J., and Angellotti, C. J., concurred. *683