General Elec. Co. v. Anson Stamping Co. Inc.General Elec. Co. v. Anson Stamping Co. Inc.
MEMORANDUM OPINION AND ORDER
This matter is before the Court on the motion of Anson Stamping Company, Inc.,
ARGUMENTS
Anson argues that the above language refers to KRS 360.040, Kentucky’s post-judgment interest statute. The statute provides, “A judgment shall bear twelve percent (12%) interest compounded annually from its date.” Based on this 12% rate, Anson calculates that it is due annual interest of $122,403.58 for May 7, 2004, until May 6, 2005, the first year beginning ten days after entry of the revised arbitration award. Anson calculates that, it is entitled to receive $375.59 in daily interest for the second year of post-award annual interest from May 7, 2005, until the date on which the amended judgment is entered. 1 Anson has tendered, along with its reply brief, a proposed order and judgment that construes its motion to amend as being a request to confirm the arbitration award pursuant to Section 9 of the Federal Arbitration Act, 9 U.S.C. § 9.
General Electric has filed an opposition to Anson’s motion to alter. GE argues that Anson is time-barred from seeking confirmation of the arbitration award based on the statute of limitations created by 9 U.S.C. § 9 (1999), which provides:
If the parties in their [arbitration] agreement have agreed that a judgment of the court shall be entered upon the award made pursuant to the arbitration, and shall specify the court, then at any time within one year after the award is made, any party to the arbitration may apply to the court so specified for an order confirming the award, and thereupon the court must grant such an order unless the award is vacated, modified or corrected as prescribed in sections 10 and 11 of this title. If no court is specified in the agreement of the parties, then such application may be made to the United States court in and for the district within such award is made.
9 U.S.C. § 9 (1999) (emphasis added). See
Photopaint Technologies, LLC v. Smartlens Corp.,
GE continues to argue that if the Court should find that KRS 360.040 is the appropriate statute to determine post-award interest, then this Court should conduct its own evidentiary hearing based on the language of KRS 360.040 that provides,
When a claim for unliquidated damages is reduced to judgment, such judgment may bear less interest than twelve percent (12%) if the court rendering such judgment, after a hearing on that question, is satisfied that the rate of interest should be less than twelve percent (12%).
KRS 360.040 (Michie 1982). GE insists that a 12% interest rate is wildly in excess of any reasonable return that could have been earned by Anson since the time that the arbitration award was entered; therefore, the Court should permit GE to submit proof on the appropriate rate of interest.
Finally, GE asks that the Court clarify its prior final order to weigh the interests of the intervening secured creditors. GE points out that the Sixth Circuit may dismiss any appeal without prejudice under
Daleure v. Kentucky,
Anson counters in its reply that
Kentucky River Mills
holds the language of 9 U.S.C. § 9 (1999) to be permissive rather than mandatory, a holding that the
Wacho-via Securities
case confirms. (DN 37) An-son also insists that the arbitration award was never intended to be, and is not, a judgment entered by a federal court. The decisions cited by General Electric all are federal cases, and therefor do not apply in the present context. Further, Judge McDonald intended by his award that interest be added to the
quantum meruit
recovery to ensure that Anson is fully compensated for the inevitable delays due to General Electric’s resistance to making payment. Anson points out that GE never previously complained about the interest component of the award. Anson concludes that the arbitration award is subject to KRS 360.040, which remains the substantive law of Kentucky that the parties agreed to apply in PSA 2. No hearing is required, or even permissible, at this stage of the proceedings, to alter the plain language of the arbitration award, which expressly re
LEGAL ANALYSIS
Confirmation of the Award.
The first task for the Court is to determine whether Anson’s motion to amend the final order of August 25, 2005, may be addressed on its merits as a motion to confirm the arbitration award.' To answer this question, the Court must decide whether the language of Section 9 of the FAA is merely permissive, so that the passage of more than one year after entry of the arbitration award will not bar this Court from confirming the award now that the motion to vacate has been denied; or, whether the language of § 9 of the FAA creates a mandatory statute of limitations that compels the prevailing party at arbitration to bring a timely motion to confirm “within one year after the award is made .or be left with only an action of law. 9 U.S.C. § 9 (1999).
Here, the disputed award was entered on April 27, 2004. Not until Anson filed its reply in support of its motion to amend on October 11, 2005, nearly six months beyond the presumptive deadline, did An-son specifically request confirmation by name. If the language of 9 U.S.C. § 9 (1999) is a mandatory statute of limitations, that requires a formal “motion to confirm,” then Anson may be time-barred from seeking confirmation, absent some other consideration such as tolling of the limitation period or a liberal construction of what constitutes a motion to confirm. Without confirmation, Anson will be required to file a separate action at law to attempt to collect its favorable arbitration award. On the other hand, if the language of 9 U.S.C. § 9 (1999) is merely permissive based on the use of the phrase “may apply to the court so specified for an order confirming the award,” then Anson’s request for confirmation will easily overcome GE’s procedural challenge. 9 U.S.C. § 9 (1999) (emphasis added).
Unfortunately, the language of § 9 that relates to confirmation is far from clear. The ambiguity in the language of the statute has resulted in a split among the federal circuit courts on this exact issue. See
Connolly v. Arthur Andersen, LLP,
No. 04 C 7458,
The pertinent question is on which side of the split does the Sixth Circuit find itself. In other words, does Sixth Circuit case law treat the relevant language of 9 U.S.C. § 9 (1999) as being permissive or does the Sixth Circuit, assuming that it has spoken unequivocally on the matter, join those courts that deem 9 U.S.C. § 9 (1999) to create a mandatory one-year statute of limitations. William Howard, Ph.D., Annotation, Statute of Limitations Under Federal Arbitration Act, 3 A.L.R.Fed.2d 419 (2005) (collecting cases interpreting § 9 of the FAA).
Anson insists that the Sixth Circuit has joined the permissive camp based on two Sixth Circuit cases. The first is an older
Kentucky River Mills involved an action at law brought by the assignee of a New York fiber broker against a Kentucky spinning mill factory. The dispute involved payment for 95 tons of Brazilian caroa, a spinnable plant fiber that the mill had ordered in early 1944, but declined to accept after the shipment arrived late. Ultimately, a substantial ex parte arbitration award was rendered against the mill owner in the state of New York. This arbitration award was upheld by the federal district court in the face of a challenge to the contract that contained the parties’ arbitration provisions.
The mill owner raised a host of arguments on appeal to the Sixth Circuit in an attempt to upend the district court decision that affirmed the arbitration award. One of the arguments involved the provision of 9 U.S.C. § 9 currently in dispute. The Sixth Circuit offered the following discussion, which Anson now insists establishes the permissive nature of § 9:
[A]ppellant contends that the award in favor of Smith & Bird could not be enforced by an action at law commenced more than one year after the award was made. This claim is based upon the proposition that the enforcement of the award in this case is barred by Section 9 of the United States Arbitration Act, which provides that: “If the parties in their agreement have agreed that a judgment of the court shall be entered upon the award made pursuant to the arbitration, and shall specify the court, then at any time within one year after the award is made any party to the arbitration may apply to the court so specified for an order confirming the award, and thereupon the court must grant such an order unless the award is vacated, modified, or corrected as prescribed in sections 10 and 11 of this title. If no court is specified in the agreement of the parties, then such application may be made to the Untied States court in and for the district within which such award was made.” The language of the foregoing section as to application to the court for an order is not mandatory, but permissive. See United Fuel Gas Co. v. Columbian Fuel Corp.,165 F.2d 746 (4th Cir.1948); Lehigh Structural Steel Co. v. Rust Engineering Co.,61 App.D.C. 224 ,59 F.2d 1038 . A party may, therefore, apply to the court for an order confirming the award, but is not limited to such remedy. Prior to the enactment of the United States Arbitration Act, an action at law on the award was the proper method of enforcing it. Red Cross Line v. Atlantic Fruit Co.,264 U.S. 109 ,44 S.Ct. 274 ,68 L.Ed. 582 . Enforcement of the award in this case is not barred by the one-year limitation contained in Section 9 of the Act, which provides for the summary remedy of confirmation of the award by the court.
Kentucky River Mills,
At first blush, the above quotation would not appear to be unshakable support for the permissive interpretation of § 9 of the FAA. First, and most importantly,
Kentucky River Mills
did not involve a summary confirmation proceeding. Indeed, the entire point of the above quotation appears to be that the one-year language of § 9 of the Act simply did not apply since the New York broker, Smith & Bird, did not rely on the statutory confirmation process, but instead chose the traditional action at law in existence at the time the
This view explains why in the above quote the Sixth Circuit states that a party “may apply to the court for an order concerning the award, but is not limited to such remedy.” Consequently, Kentucky River Mills may be logically considered to be “permissive” only in the sense that the court indicates that a party who receives a favorable arbitration award may choose between the more abbreviated statutory confirmation process of the FAA or may instead rely upon the traditional common law action to enforce the award. Read in this fashion, the above quotation makes imminent good sense.
Nevertheless, Anson cannot be faulted for reading
Kentucky River Mills
more broadly. In fact, a series of federal court decisions exists that equate
Kentucky River Mills
with the proposition that § 9 of the FAA is permissive, despite the fact that one might reasonably ask permissive in what sense. See gen. Philip L. Bruner and Patrick J. O’Connor, Jr.,
Construction La%v,
§ 20:112.50 (West 2005)(“The use of the word ‘may’ in the ... statutory language [of § 9 has lead a number of courts to conclude that the one-year time limitation is permissive.”]) The most immediately relevant of these decisions, the only other one from the Sixth Circuit, is the unpublished decision in
Wachovia Securities. Wachovia,
The Wachovia decision involved a long-running securities arbitration dispute that spawned a series of lawsuits in state and federal court between a security brokerage firm and an investor. Recitation of the complicated procedural history in Wacho-via would not serve the interest of this opinion. Essentially, one of the issues discussed by the Sixth Circuit on appeal was whether a motion for confirmation of the arbitration award, filed one year and two days after the arbitrator’s decision, was timely.
In addressing the issue, the panel offered the observation in
dicta
that, “the District Court correctly noted that the limitation on the time for seeking confirmation in the statute [9 U.S.C. § 9] is permissive, not mandatory, and allowed the complaint to proceed.” As support for this observation, the panel cited to
Kentucky River Mills v. Jackson,
This observation does not end the matter. As noted, other federal courts have read
Kentucky River Mills
as supportive of the permissive interpretation of § 9. For example, one of the leading cases is
Sverdrup Corp. v. WHC Constructors, Inc.,
The Fourth Circuit in Sverdrup rejected the decision of the district court with the following reasoning:
The language of the foregoing section [§ 9 of FAA] as to application to the court for an order is not mandatory, but permissive ... Enforcement of the award in this case is not barred by the one-year limitation contained in section ■9 of the Act which provides for the summary remedy of confirmation of the award by the court. Kentucky River Mills v. Jackson,206 F.2d 111 , 120 (6th Cir.), cert. denied,346 U.S. 887 ,74 S.Ct. 144 ,98 L.Ed. 392 (1953); Paul Allison, Inc. v. Minikin Storage of Omaha, Inc.,452 F.Supp. 573 , 575 (D.Neb.1978); Brown v. Bridgeport Rolling Mills Co.,245 F.Supp. 41 , 45 n. 7 (D.Conn.1965). See also Derwin v. General Dynamics Corp.,719 F.2d 484 , 490 n. 5 (1st Cir.1983) (state arbitration statute construed); Heffner v. Jacobson,100 N.J. 550 ,498 A.2d 766 , 768-69 (1985) (state arbitration statute stating party ‘may’ commence action to confirm within three months was permissive).
A persuasive textual argument bolsters this interpretation. The use of the word ‘may,’ as opposed to mandatory language, has been deemed to have been of critical importance in determining the permissive nature of § 9. The word ‘[m]ay in a statute ... normally confers a discretionary power, not a mandatory power, unless the legislative intent, as evidenced by the legislative history, evidences a contrary purpose.’ Dalton v. United States,816 F.2d 971 , 973 (4th Cir.1987); see also Koch Refining Co. v. United States Dept. of Energy,497 F.Supp. 879 , 891 (D.Minn.1980) ( “[Wjhere the words ‘shall’ and ‘may’ are used in the same statute or regulation, ‘shall’ is usually interpreted to impose a mandatory obligation and ‘may’ is usually interpreted to grant discretion.”) (citing Farmers Bank v. Federal Reserve Bank,262 U.S. 649 , 662-63,43 S.Ct. 651 , 656-57,67 L.Ed. 1157 (1923)). However, this rule is not inflexible, and there are situations where legislative intent indicates that the term “may” should be interpreted as mandatory. Dalton,816 F.2d at 973 .
An examination of the FAA’s language gives rise to the inference that Congress understood the plain meaning of “may” to be permissive. Section 9 of the FAA states that any party “may apply” for a confirmation order by the court “must grant” the order absent a modification or vacation under §§ 10 or 11. 9 U.S.C. § 9. Furthermore, under § 12 of the FAA, a motion to modify “must be served” within three months of the award. 9 U.S.C. § 12. This Court has previously concluded that this language in § 12 is mandatory, and thus, modification motions made beyond three months after the award are time barred. Taylor v. Nelson,788 F.2d 220 , 225 (4th Cir.1986). In this instance, the use of alternating permissive and mandatory language throughout the FAA indicates that Congress was cognizant of the difference in meaning between “may” and “must” and intended that the term “may” be construed as permissive.
Sverdrup Corp.,
Not all courts read
Kentucky River Mills
in a fashion similar to those identified above. For example, in
Insurdata Marketing Services, LLC v. Healthplan Services, Inc.,
In addition to summary confirmation pursuant to federal or state statute, enforcement of an arbitral award is available by civil action on the award.
Id.
(citing
Kentucky River Mills v. Jackson,
The benchmark decision to part ways with the broad reading of
Kentucky River Mills
is the Second Circuit decision of
Photopaint Technologies, LLC v. Smartlens Corp.,
The Second Circuit rejected
Sverdrup
and
Val-U Const,
based on two primary authorities. The first authority was the Supreme Court decision in
Cortez Byrd Chips v. Bill Harbert Const. Co.,
In
Cortez Byrd Chips,
the Supreme Court considered whether the word “may” used in the context of the FAA’s venue provision in § 9 is permissive or mandatory. The case involved an arbitration award rendered in Alabama to resolve a dispute between a construction company that had agreed to build a wood chip mill in Mississippi for Cortez Byrd Chips. After the construction company received the favorable award, Cortez Byrd sought to vacate the award in the District Court for the Southern District of Mississippi. The construction company brought an action to confirm the award one week later in the Northern District of Alabama where the award had been entered.
Cortez,
Cortez Byrd moved to dismiss, transfer or stay the Alabama action. The Alabama District Court denied the motion based on its view that venue was proper only in Alabama where the award was rendered. The Eleventh Circuit affirmed, and the Supreme Court granted certiorari to resolve a split among the circuits over the permissive or mandatory character of the FAA’s venue provisions. Id. As in Sverdr-up, the parties focused their arguments on the use of the term “may” in the venue provisions of § 9 to debate whether the venue provisions were merely permissive. The Supreme Court, however, declined to focus its analysis solely on the language of the statutes to the detriment of their legislative history, purpose and policy considerations.
In the words of the Court:
Enlightenment will not come merely from parsing the language, which is less clear than either party contends. Although ‘may’ could be read as permissive in each section [of the FAA] ..., the mere use of ‘may’ is not necessarily conclusive of congressional intent to provide for a permissive or discretionary authority. Certainly the warning flag is up in this instance. While [appellant] points to clearly mandatory language in other parts of the Act as some indication that ‘may’ was used in á permissive sense, 9 U.S.C. §§ 2, 12 [appellee] calls attention to a contrary clue and even more obviously permissive language elsewhere in the Act ... Each party has a point, but neither point is conclusive. The answer is not to be had from comparing phrases.
Id.
at 199,
The Supreme Court concluded, after a review of the general venue statute in force at the time the FAA was enacted, that the venue provisions of the FAA were intended to liberalize the options of the parties so that they could proceed either in the district in which the award was rendered or the district where the defendant resided in keeping with traditional venue rules.
Id.
at 199-201,
The other guidepost for the Second Circuit in
Photopaint
was the
Seetransport
decision, a decision rendered by the Sec
Within three years after an arbitral award falling under the Convention is made, any party to the arbitration may apply to any court having jurisdiction under this chapter for an order confirming the award as against any other party to the arbitration.
9 U.S.C. § 207 (1999).
In Seetmnsport, the question at issue was when the arbitration award was “made” for the purpose of starting the running of the three-year statute of limitations. Although the permissive or mandatory character of § 207 was not explicitly debated, the Second Circuit in Seetmns-port held that a petition filed beyond the Convention’s three-year period of limitations was time-barred. Based on Cortez Byrd Chips and Seetmnsport, the Second Circuit held as follows:
[W]e read the word ‘may’ in § 9 as permissive, but only within the scope of the proceeding adverbial phrase: ‘at any time within one year after the award is made.’ We therefore hold that § 9 of the FAA imposes a one-year statute of limitations on the filing of a motion to confirm an arbitration award under the FAA. Our construction of the text is not inevitable, but it is intuitive: for example, tax returns may be filed any time up to April 15, but one senses at once that the phrase is permissive only up to a point.
Photopaint,
The Second Circuit continued in Photo-paint to take on the policy arguments made by the Fourth Circuit in Sverdrup as justification for its permissive interpretation of § 9. The Sverdrup court had reasoned that reading § 9 as a strict statute of limitations would be an exercise in futility. Such an interpretation would in the court’s view in Sverdrup merely encourage an otherwise time-barred party to bring an action at law. Such a result was considered contrary to the fundamental policy of the FAA, which was intended to expedite and simplify such proceedings.
Photopaint
disagreed with
Sverdrup
on all of these points. In the Second Circuit’s view, the existence of a separate action at law, long the traditional means of pursuing enforcement of an arbitration award, was not identical to the summary confirmation proceeding, but not antithetical to it either.
Photopaint,
It was therefore not ‘futile’ for Congress to have specified a statute of limitations for the filing of summary proceedings: consistent with the wording of the statute, a party to an arbitration is entitled to the benefits of the streamlined proceeding only if, as it may do, it files at any time within one year after the award is made.
Id. at 159-160. Thus, the Second Circuit concluded that its approach encouraged the fundamental goals of speed and simplicity by giving the affected party an incentive to timely'move for confirmation.
While I am of course cognizant of the binding nature of Sverdrup Corp. v. WHC Constructors, Inc.,989 F.2d 148 , 151-56 (4th Cir.1993), holding that the one-year period within which a petition to confirm an arbitration award ‘may’ be filed pursuant to the Federal Arbitration Act is ‘permissive,’ I am also of the view that the Fourth Circuit is likely to reconsider that holding in light of Photopaint Technologies, LLC v. Smartlens Corp.,335 F.3d 152 (2nd Cir.2003) (noting that the Fourth Circuit’s decision in Sverdrup Corp. has been seriously undermined by the Supreme Court’s later decision in Cortez Byrd Chips, Inc. v. Bill Harbert Construction Co.,529 U.S. 193 ,120 S.Ct. 1331 ,146 L.Ed.2d 171 (2000), and concluding that the one-year period is a statute of limitations).
Maryland Transit Administration,
Certainly,
Photopaint
is widely followed within the Second Circuit and outside it. See
Faust v. Fox,
No. 05 Civ. 3962(JSR),
The above discussion of the split between the Second Circuit view and the Fourth and Eighth Circuits’ view admittedly has been extended, but is necessary to frame several important observations. First, the
Kentucky River Mills
decision has been read far too broadly by those courts that unequivocally proclaim the decision to hold that 9 U.S.C. § 9 (1999) is a “permissive” statute. The true scope of the
Kentucky River Mills
decision cannot be divorced from its procedural setting. The decision involved not a confirmation proceeding, but an action at law. When one appreciates this distinction, the oft-quoted language from the decision makes perfect sense.
Kentucky River Mills
en
Second, the far better course in terms of giving effect to the entire language of 9 U.S.C. § 9 (1999) is to adopt the approach taken by
Photopaint,
The fact that even the lower courts of the Fourth Circuit, such as the District Court of Maryland in Maryland Transit Administration are now openly calling for reconsideration and possible abandonment of Sverdrup merely serves to underscore the fundamental point that the entire line of cases that rely on what this Court believes to be an indiscriminate reading of Kentucky River Mills is now in serious doubt as to their continued viability. The natural and necessary reading of 9 U.S.C. § 9 (1999) and its confirmation provisions requires that the courts give full effect to the entire language of the statute including its one-year statute of limitations provision for confirmation proceedings. Accordingly, this Court joins with Photopaint and the Photopaint line of cases to hold that § 9 of the Act creates a mandatory one-year statute of limitations.
This conclusion might cause one to presume incorrectly that Anson is left with nothing more than an action at law to enforce Judge McDonald’s arbitration award. Such a presumption, however, would be entirely premature. The discussion to'this point has only established that § 9 of the Act created a one-year statute of limitations for confirmation proceedings. This interim conclusion merely leads to the next question — what circumstances will satisfy the one-year statute of limitations requirement.
A number of decisions involving the Federal Arbitration Act discuss when the one-year statute of limitations of § 9 may be satisfied by proceedings short of an express motion to confirm. Anson has cited a number of these decisions to the Court. They now bear discussion if for no other reason than to demonstrate that the statute of limitations of § 9 is not sacrosanct in the sense that a specifically denominated “motion to confirm” needs to be filed to meet the one-year deadline. The procedural equivalent of a motion to confirm will suffice even if not denominated as such.
For example, one fashion in which the one-year statute of limitations of § 9 has been held to be satisfied is when the prevailing party at arbitration successfully opposes a timely motion to vacate or modify the award filed by the non-prevailing party pursuant to § 12 of the FAA. 9 U.S.C. § 12 (1999). Section 12 provides that “notice of a motion to vacate an arbitration award must be served upon the adverse
In this instance, GE filed its motion to vacate on July 9, 2004 (DN 1), well within three months from the date on which Judge McDonald entered his final arbitration award on April 27, 2004. The question is what, if any, effect did Anson’s opposition to GE’s timely motion to vacate pursuant to § 12 have on the running of the one-year statute of limitations in which to seek confirmation. A related and equally important question is what type of motion, pleading or request, even if not denominated as one strictly for “confirmation,” will sufficiently put the court on notice that the prevailing party in arbitration seeks to have the court summarily affirm the arbitrator. On this latter point, the federal courts have been understandably liberal in their view on what types of motions, filings or pleadings will be construed to be the equivalent of a motion to confirm. The case law set forth below amply demonstrates that no “magic words” are required by the confirmation provisions of § 9. In fact, a motion to dismiss a motion to vacate an arbitration award repeatedly has been held to satisfy the one-year limitation period.
In
Maidman v. O’Brien,
Primarily, it should be noted that although Evans has not sought to have the arbitration decision confirmed pursuant to 9 U.S.C. § 9, there is authority for treating such motions to dismiss as implicitly seeking that confirmation and when a party objects to an arbitration decision on the merits, the possible untimeliness of the confirmation application has been viewed as waived.
Maidman,
The basis for the Maidman decision is reflected in the directly related nature of a motion to vacate under § 12 and a motion for confirmation under § 9 of the Act. In many respects, these two motions analytically are the opposite sides of the same coin. This point was driven home forcefully in the Bridgeport Rolling Mills decision, which involved an initial action to vacate a labor arbitration award followed by a subsequent action to confirm the award. The question in Bridgeport Rolling Mills was whether the employer who had unsuccessfully sought to vacate the award could attempt to resist the efforts of the employee union to confirm the same award with arguments previously rejected in the initial proceeding. The district court offered the following insightful explanation in concluding that denial of the motion to vacate was in effect a judgment confirming the challenged award pursuant to § 9. To quote the court:
Viewing the prior proceeding strictly as one pursuant to Section 10 to vacate the award, however, the judgment entered therein had the effect at least of collateral estoppel by judgment (and perhaps of res judicata) in the instant proceeding pursuant to Section 9 to confirm the award. In a converse situation under the Arbitration Act, the Court of Appeals for this Circuit in The Hartbridge, 57 F.2d 672 , 673 (2 Cir.1932), cert. denied,288 U.S. 601 ,53 S.Ct. 320 ,77 L.Ed. 977 (1933), stated:
Upon a motion to confirm the party opposing confirmation may apparently object upon any ground which constitute a sufficient cause under the statute to vacate, modify, or correct, although no such formal motion has been made. As we understand the statute a motion to confirm puts the other party to his objections. He cannot idly stand by, allow the award to be confirmed and judgment thereon entered, and then move to vacate the award just as though no judgment existed.
In short, in a proceeding to confirm an award not only may an opposing party object upon grounds which might be urged in support of a proceeding to vacate an award; he must do so, or he waives his right to do so.
Conversely, the same principle should be applied as a matter of common sense in a proceeding to vacate an award where, as here, the opposing parties (Brown and the Union) were required to object upon all grounds which might be urged in support of a proceeding to confirm the award. Brown and the Union did just that in the prior proceeding (Civil No.8995); they not only opposed the motion to vacate the award but affirmatively moved for judgment on the record and pleadings. Accordingly, this Court’s judgment in the prior proceeding denying the Company’s motion to vacate the award and granting the motion by Brown and the Union for judgment on the record and pleadings was in effect a judgment confirming the award pursuant to Section 9.
Id. at 44-45 (emphasis added).
The same practical considerations are reflected in the more recent decision of
Andrea Doreen Ltd. v. Building Material Local Union 282,
After consideration, the Court has decided to treat Local 282’s motion for summary judgment as implicitly seeking to confirm the arbitration award. Usually, arbitration awards are confirmed by a court when a party seeks confirmation pursuant to 9 U.S.C. § 9 (2000). There is some authority, however, for treating other motions made after an award has been issued as implicitly seeking that confirmation. Maidman v. O'Brien,473 F.Supp. 25 , 27 (S.D.N.Y.1979) (noting that “there is authority for treating ... motions to dismiss as implicitly seeking ... confirmation” of the arbitration award, despite the fact that the defendants had not sought such confirmation explicitly pursuant to 9 U.S.C. § 9). Although the court in Maidman inferred a request for confirmation from a motion to dismiss, the court’s reasoning also applies to the summary judgment motion in this case. Local 282’s motion for summary judgment (filed approximately two weeks after the award was issued) relies on the validity of the arbitration award to undermine Doreen’s RICO claim.
Andrea Doreen Ltd.,
Several unpublished decisions also take the same commonsense approach advocated in
Maidman.
For example, in
Thyssen v. M/V MARKOS,
No. 97 CIV
Another case to follow
Maidman
was
Markowski v. Atzmon,
Civ.App. No. 92-2865(LFO),
The district court in Markowski concluded that the plaintiffs petition to vacate the arbitration award and its attempt to appeal the dismissal of that petition would be “treated as waivers of any objection by plaintiff to the timeliness of defendant’s motion to confirm and it will be treated as timely filed.” Id. See generally, 3Fed. Proc. Forms § 4:125 (“Under some circumstances, the untimeliness of an application to confirm an [arbitration] award may be waived.”) (West 2006) (citing Maidman); 4 Am. Jur.2d Alternate Dispute Resolution, § 230 (West 2005) (“Motion to dismiss claim on basis of arbitrator’s decision may be treated as implicitly seeking confirmation of the decision pursuant to 9 U.S.C. § 9, and when party objects to arbitration decision on the merits, the possible untimeliness of the confirmation application has been viewed as waived.”) (citing Maid-man ); Thomas Oehnke, 3 Commercial Arbitration, § 134:3 (West 2005) (“If an untimely petition has been filed to confirm an award, and the opposing party responds by objecting to the arbitration award on its merits, such an objection may waive the untimeliness of the application to confirm the award.”) (citing Maidman).
Review of the record in this case reveals that on July 12, 2004, well within the one-year limitation period of 9 U.S.C. § 9 (1999), Anson filed a motion to dismiss GE’s motion to vacate the arbitration award (DN 3). Anson’s motion to dismiss directly put at issue the merits of that award including GE’s claim that Judge McDonald, as arbitrator, lacked authority to render an arbitration award and acted in manifest disregard of the law in doing so (DN 3, pp. 9-20). Indeed, GE in its motion for a hearing (DN 8) asserted its “entitlement” to the arbitrator’s award. Further, in its reply memorandum in support of its motion to dismiss GE’s motion to vacate, Anson specifically argued, “The time has now come to affirm the arbitrator’s award by dismissing GE’s Motion to Vacate [sic] it.” (DN 11, p. 7) (emphasis added). This specific request for affirmation of the arbitrator’s award was made on August 4, 2004 (DN 11) again well within the one-year limitation period of § 9.
Only the most hypertechnical reading of the law would refuse to acknowledge what is apparent. Vinson requested that the Court confirm the arbitration award. It is true that Anson did not use the term “confirmation” in doing so, but no case law cited to the Court establishes such a sense
Because the motion to dismiss filed by Anson expressly requested the affirmation of the arbitration award, and the parties fully argued the merits of the award under the applicable standard of § 10 of the Act, the Court concludes that Anson’s motion to dismiss GE’s motion to vacate is in all respects the practical equivalent of a motion to confirm and should be so construed for the purpose of the one-year statute of limitations of § 9. To hold otherwise would work a grave injustice to the underlying policies that support the Arbitration Act, which is “intended to be a speedy, efficient and relatively inexpensive method of resolving disputes.” See
Scherk v. Alberto-Culver Co.,
“With Interest as on a Judgment.”
The Court has rejected GE’s argument that Anson’s motion to alter, amend or vacate is procedurally defective. The next question is whether Anson’s request for what is, in effect, post-award, pre-judgment interest on the award at the rate of 12% under KRS 360.040 is “substantively wrong” to use the words of GE.
The original arbitration and the amended arbitration decisions of Judge McDonald employ the same language. Both awards specify a dollar amount to be awarded “with interest as on a judgment” to begin ten (10) days after entry of the award. GE insists that the only appropriate statute to be applied under the circumstances is not the state post-judgment interest statute, KRS 360.040, but the federal interest statute found at 28 U.S.C. § 1961, which provides:
Interest shall be allowed on any money judgment in a civil case recovered in a district court ... such interest shall be calculated from the date of the entry of the judgment, at a rate equal to the weekly average 1-year constant maturity Treasury yield, as published by the Board of Governors of the Federal Reserve System, for the calendar week preceding, [sic] the date of the judgment.
Id. Based on 28 U.S.C. § 1961, GE argues that the appropriate interest rate for the calendar week before entry of the arbitration award on April 27, 2004, was 1.5% rather than the 12% rate established by KRS 360.040. Using this interest rate, GE arrives at interest of $15,264 for the first year following entry of the amended award and daily interest of $42.45 thereafter.
Essentially, the Court must now determine whether the 12% or the 1.5% interest rate applies, or a combination thereof. In addressing this question, it would be helpful to recall the fundamental principles that govern when a federal court sits to review an arbitration award under the FAA. The role of the courts in such situations is extremely limited. See
Dawahare v. Spencer,
These principles now apply to.the question of what interest should be included in the arbitration award. At least on this point, the law is well-established in the Sixth Circuit. GE correctly cites to
Estate of Riddle ex rel. Riddle v. Southern Farm Bureau Life Ins. Co.,
The Sixth Circuit discussed the application of this principle in a case involving Kentucky law in
Hale v. Life Ins. Co. of North America,
When a federal court’s jurisdiction rests upon diversity, the award of prejudgment interest is governed by state law. Glens Falls Ins. Co. v. Danville Motors, Inc.,333 F.2d 187 (6th Cir.1964). Under Kentucky law, if the claim is liquidated, interest follows as a matter of right, but if it is unliquidated, the allowance of interest is in the discretion of the trial court. General Accident Fire & Life Assur. Corp. v. Judd,400 S.W.2d 685 , 687 (Ky.1966).... . A liquidated claim is a ‘[cjlaim, amount of which has been agreed on by the parties to [the] action or is fixed by operation of law.’ Tapp v. Tapp’s Trustee,299 Ky. 345 ,185 S.W.2d 534 , 535 (1945). If the amount of the claim is a sum certain, the debt is still liquidated even if the refusal to pay is based upon a good faith denial of liability.
Id. at 24.
A separate series of federal cases has addressed the calculation of prejudgment and post-judgment interest on arbitration awards. The First Circuit in
Fort Hill Builders, Inc. v. National Grange Ins. Co.,
Northrop
applied state law to determine pre-judgment interest in a diversity suit under the Federal Arbitration Act.
Id.
This approach is well justified given that “Congress deleted a suggested provision making [28 U.S.C. § 1961] ... applicable to pre-judgment interest.”
Taylor v. Central Pennsylvania Drug and Alcohol Services Corp.,
Consideration of the above case law persuades the Court that the federal interest statute, 28 U.S.C. § 1961 has no role to play in the calculation of post-award, prejudgment interest. The arbitration award entered by Judge McDonald cannot be appropriately characterized as being a federal judgment. It is not a federal judgment entered by district court as required by the clear language of § 1961. GE cites no persuasive authority that would lead this Court to conclude otherwise. The Riddle, First Heights, Conte, Sterling and Hale decisions all confirm that the prejudgment interest rate to be applied in this diversity action is determined, not by federal law, but by state law such as KRS 360.040. Only when this Court entered its federal judgment on August 25, 2005, did the 1.5% rate as determined by 28 U.S.C. § 1961 become applicable.
The appropriate state statute to calculate the interest component of Judge McDonald’s arbitration award clearly is KRS 360.040 given the language of the arbitration award that it shall bear interest “as if on a judgment.” His use of a post-judgment interest statute to calculate what is, in effect, post-award, pre-judgment interest is not grounds to vacate under § 10 of the Act, nor has GE argued it to be so. Even assuming that Judge McDonald was in error in relying upon the state post-judgment interest statute to calculate post-award, pre-judgment interest, his error would not constitute manifest disregard of the law sufficient to justify vacating the award. In fact, the Sixth Circuit has on at least one occasion in a diversity action applied state law to calculate pre-judgment interest based on a state post-judgment interest statute. See generally
FDIC v. First Heights Bank, FSB,
Judge McDonald’s intention to include an interest component in the
quantum meruit
award is clear cut. His reliance on KRS 360.040 was within his discretion as arbitrator as the
Hale
decision confirms. Obviously, he intended that Anson recover interest for any period of prejudgment delay. What he did not do, is enter a federal judgment on April 27, 2004, so as to make his ref
The plain language of the final ruling in arbitration entered on April 27, 2004, provides that, “Anson shall recover as an award from General Electric Company the sum of $1,020,029.90 with interest as on a judgment starting ten (10) days hence.” Interest began to run on May 7, 2004, at a rate of 12% compounded annually. The interest that accrued from May 7, 2004, to May 6, 2005, totaled to $122,403.58. When this annual interest is included with the principal award amount, a total of $1,142,433.40 results. This amount then accrues interest at a rate of 12%, or a daily interest amount of $375.59 beginning on May 7, 2005, up until the date on which this Court entered its original judgment. Because the Court’s original judgment was entered on August 25, 2005, the amount of interest accrued from May 7, 2005, until August 24, 2005, is $41,314.90. When this amount is added to the prior total of $1,142,433.40 a judgment amount of $1,183,372.71 results. This judgment amount shall bear post-judgment interest pursuant to the federal interest statute, 28 U.S.C. § 1961, at a rate of 1.5% from date of entry of the original federal judgment on August 25, 2005.
Hearing Request of GE.
In its response to Anson’s motion to amend, GE requests a hearing before this Court on the appropriate rate of post-award, prejudgment interest. GE’s request is based on the final two sentences of KRS § 360.040. This portion of the statute states that,
Provided that when a claim for unliqui-dated damages is reduced to judgment, such judgment may bear less interest than twelve percent (12%) if the court rendering such judgment, after a hearing on that question, is satisfied that the rate of interest should be less than twelve percent (12%). All interested parties must have due notice of said hearing.
KRS 360.040 (Michie 1982). Based on this language, GE now desires to argue in this Court that the 12% interest rate far exceeds a reasonable market return on investments for the time period in question.
Unfortunately, GE waived its opportunity to raise this argument in a timely fashion. The quoted language of the statute indicates that such an argument must be made prior to the decision to impose interest, rather than two years later. GE had the opportunity to raise this issue before the arbitrator if it so desired. In fact, GE successfully moved Judge McDonald to
This Court, as a federal court reviewing an arbitration award pursuant to §§ 9-12 of the Act, does not sit to conduct evidentiary hearings. At most, the Court could remand the matter if such a hearing were justified. Remand is a procedure, however, that should be used sparingly. Whenever possible, “a court should avoid remanding a decision to the arbitrator because of the interest in prompt and final arbitration.”
Teamsters Local No. 579 v. B & M Transit, Inc.,
Finality.
General Electric correctly points out in its response to the motion to amend that the prior order of the Court entered pursuant to Rule 54(b) of the Federal Rules of Civil Procedure is incomplete in the sense that the order fails to discuss the interest of the intervenors Leasing One Corporation and J.P. Morgan Chase Bank, both of whom are secured creditors of Anson that assert an interest in any arbitration award. GE is concerned that unless the Court expressly considers the interest of these intervening parties in rendering its final judgment pursuant to Rule 54(b), the Court of Appeals may dismiss any attempted appeal. GE’s concerns are well-founded given the requirements of Rule 54(b) as explained in
General Acquisition, Inc. v. GenCorp., Inc.,
In General Acquisition, the Sixth Circuit carefully set out the requirements for entry of the judgment pursuant to Rule 54(b). General Acquisition explains those requirements as follows:
Rule 54(b) of the Federal Rules of Civil Procedure permits immediate review of certain district court orders prior to the ultimate disposition of a case. See, e.g., Curtiss-Wright Corp. v. General Electric Co.,446 U.S. 1 , 3,100 S.Ct. 1460 , 1462,64 L.Ed.2d 1 (1980); Liberty Mutual Ins. Co. v. Wetzel,424 U.S. 737 , 742-43,96 S.Ct. 1202 , 1205-06,47 L.Ed.2d 435 ; Sears, Roebuck & Co. v. Mackey,351 U.S. 427 , 435,76 S.Ct. 895 , 899-900,100 L.Ed. 1297 (1956). Although Rule 54(b) relaxes the traditional finality requirement for appellate review, it does not tolerate immediate appeal of every action taken by a district court. The rule is specifically designed to facilitate the entry of judgment on one or more claims, or as to one or more parties, in a multi-claim/multi-party action. Solomon v. Aetna Life Ins. Co.,782 F.2d 58 , 60 (6th Cir.1986).
Rule 54(b) certification requires two independent findings. First, the district court must expressly direct the entry of final judgment as to one or more but fewer than all the claims of parties in a case. Second, the district court must expressly determine that there is no just reason to delay appellate review. Fed. R.Civ.P. 54(b), supra note 7; 10 Charles A. Wright, Arthur R. Miller & Mary Kay Kane, Federal Practice and Procedure: Civil 2d § 2655 (1983 & Supp. 1993) (hereinafter Wright, Miller & Kane). A district court certifying an order under Rule 54(b) must clearly explain why it has concluded that immediate review of the challenged ruling is desirable. Solomon,782 F.2d at 61-62 . The first step in certification, entry of partial final judgment, is satisfied wheresome decision made by the district court ultimately disposes of one or more but fewer than all of the claims or parties in a multi-claim/multi-party action. As the Supreme Court explained in Curtiss-Wright:
A district court must first determine that it is dealing with a final judgment. It must be a judgment in the sense that it is a decision upon a cognizable claim for relief, and it must be final in the sense that it is an ultimate disposition of an individual claim entered in the course of a multiple claims action.446 U.S. at 7 ,100 S.Ct. at 1464 (citing Sears,351 U.S. at 436 ,76 S.Ct. at 900 ); 10 Charles A. Wright, Arthur R. Miller & & Mary Kay Kane § 2656.
The second step in certification, determination of no just reason for delay, requires the district court to balance the needs of the parties against the interests of efficient case management. Not all final judgments on individual claims should be immediately appealable, even if they are in some sense separable from the remaining unresolved claims. Cur-tiss-Wright,446 U.S. at 8 ,100 S.Ct. at 1465 . Courts implementing rule 54(b) must strike a balance between the undesirability of more than one appeal in a single action and the need for making review available in multiple-party or multiple-claim situations at a time that best serves the needs of the • litigants. Wright, Miller & Kane § 2654.
Id. at 1026-27.
Here, the interests of efficient case management compel the Court to delay consideration of the claims of the secured creditors, Leasing One and Chase Bank, until such time as the Sixth Circuit has had the opportunity to determine whether the arbitration award entered by Judge McDonald was properly confirmed by this Court. It makes little sense to determine the amount and priority of the secured creditors’ interests in the arbitration award if the award itself is vacated by the appellate courts on review of this Court’s decision. Judicial economy and wise use of the Court’s scarce resources both dictate that any hearings or arguments to establish the priority, nature and extent of the secured creditors’ interests be delayed until such time as the arbitration award is either finally confirmed or vacated on appeal.
The Court therefor will enter a final judgment that denies the motion of GE to vacate the arbitration award of April 27, 2004. In the same judgment, the Court will grant the timely request of Anson for confirmation of the award in the amount set forth above.
CONCLUSION
In this case, the Court has embraced the mandatory statute of limitations interpretation of 9 U.S.C. § 9 (1999) of
Photopaint
in order to give full effect to the language of that statute. Yet, at the same time, the Court has- adopted the
Maidman
line of cases that permit the federal courts to liberally construe the motion papers of a party filed in opposition to a motion to vacate as being a motion for confirmation. Here, Anson requested affirmation of the arbitration award in a timely fashion in its motion to dismiss well within the mandatory one-year limitation period. This resolution not only preserves the full language of § 9 of the Act, but also supports the fundamental policy of the FAA for the speedy and efficient resolution of arbitration disputes. It satisfies the criteria of
Cortez Byrd Chips,
as well. The Court’s reliance on KRS 360.040 to calculate the post-award, prejudgment interest rate is in accord with the clear intention of the arbitrator, which does not run afoul of § 10 of the Act. For these reasons, the Court enters
Notes
. Anson calculates this daily amount of interest by adding the original arbitration award of $1,020,029.90 to the $122,403.58 in annual interest for the first year to arrive at $1,142,433.40. Anson calculates that the annual interest for the second year on this adjusted amount will be $137,091.91, or a daily interest amount of $375.59. (DN 37, Exh. 6, Proposed Order).
. The Supreme Court of Kentucky recently discussed the discretion of the trial court or jury to award pre-judgment interest on an unliquidated or liquidated sum in
3D Enterprises Contracting Corp. v. Louisville and Jefferson County Metropolitan Sewer District,