558 F.2d 985 | Ct. Cl. | 1977
delivered the opinion of the court:
This action for patent infringement requires us to decide whether an unappealed decision of the Armed Services Board of Contract Appeals (the board) against the Government on the existence of a license to use a patent under the standard Patent Rights clause of a Government contract now precludes the Government from raising the license as a defense to the alleged infringement. The Government says that the decision does not preclude it, arguing that the board’s ruling was purely advisory and therefore not binding on it under S&E Contractors, Inc. v. United States, 406 U.S. 1 (1972). We conclude that on the peculiar facts of this case, the Government must abide by what the board held.
The controversy on which the board ruled had its genesis in contract NObsr-77628, a cost-plus-fixed-fee research and development contract entered into between plaintiff and the Government, acting through the Department of the Navy, on June 16, 1959. The contract called for plaintiff to design and furnish experimental, mock-up, and developmental models of a single sideband radio set and a single sideband portable transceiver. The Patent Rights clause of the contract
Less than 1 year after this conference, in March 1965, plaintiff informed the Navy that the latter’s then-intended procurement of single sideband radios from another contractor would infringe the five patents. The Navy responded that it was licensed to practice those inventions under the Patent Rights clause of the parties’ contract, on the theory that they had first been conceived or reduced to practice in the course of performing the contract. Plaintiff refused the Navy’s request to execute confirmatory licenses for the Government to practice the inventions, but did not again raise its infringement claim until February 1968, after the procurement from the other contractor was completed. In March 1968 the Navy repeated its original response, having concluded that plaintiffs submission of additional data in February in support of its position did not prove actual reduction to practice prior to the contract award. Following further exchange of correspondence, the contracting officer for NObsr-77628 rendered a "final decision” determining that the Government was licensed to practice the five inventions, and informed plaintiff that "[djecisions on disputed questions of fact and on other questions that are subject to the procedure of the Disputes clause [of the Government contract] may be appealed in accordance with the provisions of the Disputes clause.”
When the Government answered plaintiffs petition in this court, it pleaded as a defense that it enjoyed a license to practice plaintiffs inventions by virtue of the Patent Rights clause of the research and development contract. Plaintiff thereafter moved to strike that defense, claiming that its assertion is barred by the board’s decision that the Government had no such license. We treat plaintiffs
Defendant’s position that the board lacked jurisdiction to decide the licensing dispute, and consequently that the facts which it found in rendering its opinion are not binding on the Government in this proceeding, lies at the heart of the controversy presently before us. Where the board’s findings are made in a case within its jurisdiction, the reasoning of S&E Contractors, Inc. v. United States, supra, and United States v. Utah Constr. & Min. Co., 384 U.S. 394 (1966), mandates that they be applied in any collateral proceeding where the same facts are in issue, and that they be so applied without challenge on the Government’s part. On the other hand, where the board conducts a proceeding beyond its jurisdiction, its findings of fact therein are advisory only, see United States v. Utah Constr. & Min. Co., supra, 384 U.S. at 409-11. The contours of the board’s jurisdiction are fixed by the agreement of the parties, typically expressed in the language of their contract. Thus, "to the extent complete relief is available under a specific provision of the contract, a controversy is regarded as being within the standard Disputes clause,” meaning that the board has jurisdiction. Edward R.
Defendant makes a very persuasive argument from the terms of the parties’ contract that the board had no authority to decide the licensing issue, save in an advisory sense. The Patent Rights clause, the "specific provision of the contract” to which we must look to see if "complete relief is available” from the board under the contract, makes reference only to a remedy of the contracting officer, namely, his right to withhold part of the payment due the contractor if a license is thought to belong to the Government but the contractor refuses to disclose the invention to the Government. This penalty device hardly amounts to the provision of complete relief, either for the Government or the contractor. In any event, it is not involved here, for no part of plaintiffs payment was withheld on account of the licensing dispute, so far as appears from the record before us. If the board’s declaration of the parties’ rights in the patents was intended to be the complete relief available, this is nowhere spelled out in the Patent Rights clause, or in any other clause of the contract. Though the board has for many years heard and decided licensing controversies,
That the parties to a contract may, at the outset of litigation over the contracting officer’s decision, modify
Under the foregoing precedents, we believe that there is no good reason why the Government’s challenge to the finality of the board’s determination in this court should
The Government’s agreement to modify the parties’ contract, removing all doubt from the board’s right and duty to resolve the license issue, is assuredly authorized by the essentially contractual nature of the board’s mandatory jurisdiction, and its enforcement in this action is perfectly in keeping with the policy against duplicative litigation. Were we to accede to the Government’s argument and grant yet a new hearing, going over the same facts and engaging in fact-finding already once performed, we would violate that policy. To cast aside the administrative record and disposition of the license dispute and require a de novo proceeding in this court would be a wasteful exercise, particularly in light of the fact that the parties were completely satisfied to go before the board at
The-rule which we derive by analogy from the precedents and which we apply to reach our holding, that the board’s lack of jurisdiction is a defense that may in effect be waived by failure to object in a timely fashion in that forum, is entirely consonant, as already said, with the contractual nature of the board’s authority. This rule is distinguishable from thé contrary principle, operating in the courts, that objection to jurisdiction may not be waived, for reasons explained above. Defendant says, however, that application of this rule should not defeat its position. It adheres to its contention that the board’s findings should not be accorded finality, within the meaning of S&E Contractors, Inc. v. United States, supra, because plaintiffs opposition to defendant’s motion for partial summary judgment supposedly amounts to an attack on those findings, bringing the case under Roscoe-Ajax Constr. Co. v. United States, 204 Ct. Cl. 726, 499 F. 2d 639 (1974).
We find no merit in this contention. First of all, plaintiff is not in fact appealing any part of the board’s decision. It is content to rely on the facts the board found and on the result the board reached; it proposes, in further proceedings to determine the validity of its patents, to seek no fact-finding contrary to what the board said. See Jefferson Constr. Co. v. United States, supra, 183 Ct. Cl. at 726, 392 F. 2d at 1010. Secondly, plaintiff can properly accept the board’s fact-finding on the license issue and still ask for a trial to take additional evidence on the validity dispute. Plaintiff asserts that whatever public use it made of its inventions prior to the critical dates, i.e., 1 year before the filing of the patent applications, was purely experimental in nature and thus excepted from the statute’s on-sale bar, Sauquoit Fibers Co. v. Leesona Corp. (In re Yarn Processing Patent Validity Litigation), 498 F. 2d 271 (5th Cir. 1974). The parties’ license and validity disputes concern very different legal questions, and plaintiffs experimental use claim not surprisingly can, as it does, raise genuine issues of material fact not decided by the board in the license litigation. Plaintiff, then, is not attacking the board’s decision, but is merely asking for a trial to complete the taking of evidence on a matter not before the board. Roscoe-Ajax does not apply, and so defendant may not question the board’s license determination.
Defendant additionally points out that giving res ju-dicata effect to the board’s ruling violates, in defendant’s view, 10 U.S.C. § 2386 (1970) and 28 U.S.C. § 1498 (1970),
In the first place, the fragmentation of this litigation was defendant’s own doing, not plaintiffs. Defendant’s 'contracting officer issued the "final decision” on the license dispute, including in it language which suggested that an appeal to the board would be appropriate if plaintiff disagreed with his determination. Defendant’s board heard and disposed of the case, without any objection from defendant’s attorney there as to the propriety of proceeding with the litigation in that forum. Next, we do not see how it is, on the basis of the information defendant has provided us in its briefs, that the statutes cited above compel a discarding of the board’s decision. It is true that this court has been given exclusive jurisdiction over patent infringement claims brought against the Government, but that vesting of jurisdiction is no more exclusive than that granted the court over contract claims in excess of $10,000. Nonetheless, the boards every day hear and determine in the first instance claims for equitable adjustments in excess of $10,000. Had the parties not agreed to the board’s authority to do so in their contract, those very claims would of course originally be prosecuted in this court. The court’s exclusive jurisdiction of the claims has not precluded the parties to a contract from agreeing to have the facts found in another tribunal, and to have that fact-finding applied by this court. This is not different from what has happened here. Nothing we say here should be construed, however, as indicating that we think it is inevitably appropriate to do so rather than to have a genuine de novo court proceeding throughout trial to appeal. It may be that in another case, where a direct attack on the board’s jurisdiction under the Patent Rights
Defendant’s motion for partial summary judgment asks that patents ’057 and ’301 be declared invalid, relieving the Government from liability for infringement, because granted in violation of the on-sale bar as determined from facts found by the board. Since a genuine dispute exists over the facts material to the invalidity defense, as discussed above, resolution of the matter on summary judgment is obviously not possible. Ct. Cl. Rule 101. Both sides are in agreement that a trial is needed to resolve the infringement claims on the other two patents, Nos. ’329 and ’310.
Accordingly, in view of the foregoing, plaintiffs motion for partial summary judgment is granted, defendant’s motion for partial summary judgment is denied, and the case is remanded to the Trial Division for further proceedings not inconsistent herewith.
Selected portions of the clause follow:
"33. Patent Rights
"(a)(i) The term 'Subject Invention’ means any invention, improvement or discovery (whether or not patentable) conceived or first actually reduced to practice either—
"(A) in the performance of the experimental, developmental, or research work called for or required under this contract; or
"(B) in the performance of any experimental, developmental, or research work relating to the subject matter of this contract which was done upon an understanding in writing that a contract would be awarded;
provided that the term 'Subject Invention’ shall not include any invention which is specifically identified and listed in the Schedule for the purpose of*611 excluding it from the license granted by this clause.
"(bXl) The Contractor agrees to and does hereby grant to the Government an irrevocable, nonexclusive, nontransferable, and royalty-free license to practice, and cause to be practiced by or for the United States Government, throughout the world, each Subject Invention in the manufacture, use and disposition according to law, of any article or material, and in the use of any method. No license granted herein shall convey any right to the Government to manufacture, have manufactured, or use any Subject Invention for the purpose of providing services or supplies to the general public in competition with the Contractor or the Contractor’s commercial licensees in the licensed fields.
"(c) The Contractor shall furnish to the Contracting Officer the following information and reports concerning Subject Inventions which reasonably appear to be patentable:
"(i) a written disclosure promptly after conception or first actual reduction to practice of each such Invention together with a written statement specifying whether or not a United States patent application claiming the Invention has been or will be filed by or on behalf of the Contractor;
"(ii) interim reports, at least every twelve months, commencing with the date of this contract, each listing all such Inventions conceived or first actually reduced to practice more than three months prior to the date of the report, and not listed on a prior interim report, or certifying that there are no such unreported Inventions; and
"(iii) prior to final settlement of this contract, a final report listing all such Inventions including all those previously listed in interim reports.
"(f) If the Contractor fails to deliver to the Contracting Officer the interim reports required by (c)(ii) above, or fails to furnish the written disclosures for all Subject Inventions required by (c)(i) above shown to be due in accordance with any interim report delivered under (e)(ii) or otherwise known to be unreported, there shall be withheld from payment until the Contractor shall have corrected such failures either ten percent (10%) of the amount of this contract, as from time to time amended, or five thousand dollars ($5,000), whichever is less. After payment of eighty percent (80%) of the amount of this contract, as from time to time amended, payment shall be withheld until a reserve of either ten percent (10%) of such amount, or five thousand dollars ($5,000), whichever is less, shall have been set aside, such reserve or balance thereof to be retained until the Contractor shall have furnished to the Contracting Officer:
"(i) the final report required by (c)(iii) above;
“(ii) written disclosures for all Subject Inventions required by (c)(i) above which are shown to be due in accordance with interim reports delivered under (c)(ii) above or in accordance with such final reports or are otherwise known to be unreported; and
"(iii) the information as to any subcontractor required by (h) below. The maximum amount which may be withheld under this paragraph (f) shall not exceed ten percent (10%) of the amount of this contract or five thousand dollars ($5,000), whichever is less, and no amount shall be withheld under this paragraph (f) when the amount specified by this paragraph (f) is being withheld under other provisions of this contract. The withholding of any amount or subsequent payment thereof to the Contractor shall not be construed as a waiver of any rights accruing to the Government under this contract. This paragraph (f) shall not be construed as requiring the Contractor to withhold any amounts from a subcontractor to enforce compliance with the patent provisions of a subcontract.”
See, e.g., Physics Technology Labs., Inc., 77-1 BCA ¶ 12301; Bell Aerosystems Co., 67-1 BCA ¶ 6203; Doak Aircraft Co., 1963 BCA j[ 3684; Kearfott Div. of Gen. Precision, Inc., 61-2 BCA ¶ 3241.
To make this argument, defendant seems not to be requesting a trial de novo as it did under its lack-of-jurisdiction contention, but only the opportunity to challenge the correctness of the board’s conclusions on the law applied and under the substantial evidence test. Without a Roscoe-Ajax attack by plaintiff on the board’s determination, defendant would be precluded from challenging the administrative ruling here by S&B Contractors, Inc. v. United States, supra.