Gemma Construction Co. v. City of New YorkGemma Construction Co. v. City of New York
Order, Supreme
In its first cause of action, plaintiff contractor seeks to recover damages of $1,457,049.38 for delay in completing work under its contract with the City. The second cause of action, which seeks to recover a $35,000 balance alleged to be due under the contract, is not at issue. An internal memorаndum from defendant’s project manager specifies three periods of “delays encountered by the Prime Contractors on this project directly attributable to actions on the part of the city” totaling “225 calendar days, or approximately 71/2 months”. Defendant unquestionably had contemporaneous notice of these delays, which were occasioned by the inability to timely obtain building permits (the City’s filed plans were incomplete), an improperly elevated foundation at one of the sites (the City’s specifications were inaccurate), and the City’s failure to timely correct a dangerous condition (an unstable wall on an adjacent property posed a hazard).
The City’s аnswer alleges that plaintiff waived its right to seek delay damages pursuant to the provisions of article 13 of the contract and that plaintiff failed to comply with notice provisions of article 27, entitled “Disputed Work, Determination оr Order”. In its moving papers, however, the City does not raise the waiver provision, advancing only plaintiffs failure to comply with article 27 as the basis for dismissal of the complaint. In opposition, plaintiff contends that the notice provision contained in article 11 governs claims for delay damage and that articles 27 and 28 concern the notice to be given to the City regarding claims for extra or disputed work. In its reply papers, the City takes the position that cоmpliance with the notice and documentation requirements of article 27 is a “condition precedent for all claims for damages under the contract” whether or not they involve “extra” or “disputed” work.
Article 1 of the contraсt provides that “ ‘Extra work’ shall mean work other than that required by the Contract at the time of its execution.” The contract does not define either “disputed work” or “delay damages”. In Naclerio Contr. Co. v Environmental Protection Admin. (
By contrast, “delay damage claims seek compensation for increased costs * * * whether the costs result because it takes longer to complete the project or because overtime or additional costs are expended in an effort to complete the work on time” (Corinno Civetta Constr. Co. v City of New York,
Chapter III of the disputеd contract is entitled “Time Provisions”. Comprising articles 8 through 17, this chapter deals with the progress of the work and contains provisions expressly
Defendant suggests no compelling reason to look beyond the provisions of Chapter III in respect of the notice to be given where, as here, damages are sustained solely because of the City’s delay. Indeed, as Supreme Court pointed out, thе contemporaneous notification of damages required by article 27 is in conflict with the deferred notification for delay damages provided in article 42.1 of the contract. Therefore, application of article 27 to a delay damages claim would have the effect of rendering the notice provision of article 42 without force and effect, in violation of “a cardinal rule of construction” (Corhill Corp. v S. D. Plants,
In Huff Enters. v Triborough Bridge & Tunnel Auth. (
In its moving papers, the City relies on a particular paragraph contained in article 27 as the basis for dismissal of plaintiffs claim for delay damages. It provides: “If the Contractor shall also claim to be sustaining damаges by reason of any act or omission of the City or its agents, he shall within five days after the sustaining of such damage, notify the Commissioner in writing and within thirty days thereafter, or within such additional time in excess of thirty days as may be granted by the Commissioner upon written rеquest therefor, submit to the Commissioner verified detailed statements of the damages sustained together with documentary evidence of such damages. On failure of the Contractor to fully comply with the foregoing provisions, such claims shall bе deemed waived and no right to recover on such claims shall exist.” (Emphasis added.) The scope of this provision is not completely clear, although the Appellate Division, Second Department, has held that similar language in a different contract encompasses delay damages (American Std. v New York City Tr. Auth.,
In its moving papers, the City contends that the provision operates to bаr plaintiffs claim because “Gemma failed to give timely written notice to the Commissioner of such acts or omissions with the required verified detailed statements and documentation of the damages sustained.” The City, however, conveniently оverlooks the use of the word “also” in this paragraph. The provision has potential application where a plaintiff asserts claims for both extra work and delay damages or a claim predicated upon delay tоgether with tortious conduct (e.g., National States Elec. Corp. v City of New York,
By way of example, in MRW Constr. Co. v City of New York (
The instant appeal presents no question regarding the nature of the damages for which recovery is sought. The cause of action states a claim for delay damages exclusively, to which the disputed provision is, by its terms, inapposite. Therefore, defendant’s motion for summary judgment was properly denied. Concur—Milonas, J. P., Ellerin, Wallach and Rubin, JJ.