Gelinas v. Town of West HartfordGelinas v. Town of West Hartford
Lead Opinion
The plaintiffs, William P. Gelinas and Morton Weiner, challenge the trial court’s refusal to issue a writ of mandamus directing the defendants, the town of West Hartford and its town planner, Donald Foster, (town), to grant their site plan application for premises known as 115-121 Park Road, West Hartford. Gelinas also challenges the propriety of the trial court’s injunctive and penalty orders. In its appeal, the town challenges the refusal of the trial court to grant certain injunctive relief against Gelinas.
In their appeal, the plaintiffs jointly claim that the trial court improperly concluded: (1) that the town’s failure to render a decision on their site plan application did not result in automatic approval of their application pursuant to
The town’s appeal challenges the trial court’s denial of a request for an injunction against a change in the use of the basement of Gelinas’ building. We agree with the town on that issue, reverse the judgment of the trial court, and remand the case to the trial court for further proceedings regarding the town’s request for an injunction against a change in the use of the basement.
I
The Plaintiffs’ Appeal
Since December, 1986, Gelinas has owned a two-story building, located at 119-121 Park Road, West Hartford, that had formerly been owned by a fraternal organization and used for large indoor meetings and events. During the early part of 1987, he made alterations to the building including the removal of a first floor assembly hall stage and the construction of two floors of offices in place of the stage and a part of the assembly hall. Thereafter, on June 24,1987, Gelinas applied for a building permit to make changes to the interior of the building. Believing that the proposed changes constituted a change in use, town officials inspected the property and discovered that much of the work for which a permit was sought had already been completed and was in violation of the zoning ordinances and the
Weiner owned property located at 115-117 Park Road. The town planning office received his application for site plan approval for a driveway repair on November 17, 1987. On the same date, the town received Gelinas’ site plan application for regrading, repaving and storm sewer work at 119-121 Park Road. Thereafter, on February 29,1988, the plaintiffs filed a revised site plan application covering their joint properties.
The revised site plan was not approved, denied or modified, and in June, 1990, the plaintiffs brought this mandamus action against the town.
The town had filed a counterclaim in the mandamus action alleging that Gelinas had altered the building without first obtaining site plan approval and building permits, had used the building without first obtaining a certificate of occupancy, and had failed to comply with orders to discontinue or remedy the zoning violations.
A
The plaintiffs first claim that the trial court improperly concluded that the town’s failure to render a decision on their site plan application did not result in automatic approval of their application pursuant to
The trial court found, in the instant case, that the alterations to the property had been made before Gelinas had applied for the required permits and also that he had failed to identify the actual and proposed uses of the property. He anomalously sought approval therefore of an application to allow alterations to a building that had already been extensively altered without the necessary permits and had been occupied without a certificate of occupancy. These circumstances distinguish the present case from SSM Associates Limited Partnership and Carr, and require that we consider for the first time the meaning of the word “proposed” as used in
The plaintiffs next claim that the trial court improperly concluded that they were not entitled to a writ of mandamus directing the town to grant their site plan application. See
The plaintiffs contend that timetables provided in the land use statutes evidence the legislature’s intent to protect the interests of applicants from abuses of municipal authority, such as the delays in the processing of the application in this case that allegedly subjected Gelinas to civil and criminal penalties. They argue that a writ of mandamus was the proper remedy for the town’s failure to act within the prescribed time limits. The trial court found, however, that the application was incomplete because Gelinas had never provided the town with information as to the actual or proposed use of the property, and that he did not seek the certificate of approval in a timely manner, that is, before he did the work.
In light of our conclusion in part I A that the plaintiffs’ site plan application did not comply with the requirements of
C
The plaintiffs next dispute the propriety of the injunction that the trial court issued against Gelinas pursuant to
1
The plaintiffs argue that the evidence was insufficient to support the decision by the trial court to grant the injunctive relief, pursuant to
The zoning code of the town provides that no structure shall be expanded or structurally altered until a certificate of site plan approval has been issued. West Hartford Code § 177-38; see also § 177-6 (B) and (C). Additionally, no structure may be used or changed to another use until the building inspector has issued a certificate of occupancy, certifying that the zoning ordinances have been complied with in full, including any conditions attached to any site plan approval. West Hartford Code § 177-39. Section 177-41 of the zoning code specifies the content required in applications for zoning and building permits. Section 111.1 of the state
The trial court found that Gelinas had removed a stage and, in its place, added six offices, three on each of two levels of the subject building. The trial court found further that Gelinas had admittedly made the alterations and additions without first obtaining the requisite permits, thereby violating §§ 177-38 and 177-39 of the zoning code and § 111.1 of the building code.
We conclude that the trial court properly exercised its discretion in fashioning its orders for prohibitory and mandatory injunctive relief for violations of the building code that had occurred prior to the approval of a site plan application as required by law.
2
The plaintiffs argue in the alternative that the town was estopped from seeking an injunction because it had issued various mechanical permits for work in areas of the building that the town then maintained had been put to illegal uses.
Gelinas began work on the premises before he had submitted the June 24, 1987 building permit application, the approval of which would have allowed him to commence structural alterations to the interior of the building. The zoning enforcement officer testified that the building permit application to replace windows, to do electrical work, and to make interior alterations had been denied within thirty days of submission. He also testified, however, that: a permit for a heat pump had been issued, but only because unauthorized work on the new second floor had cut off the heat source that had previously protected the fire sprinkler system from freezing; one electrical permit had been issued for a change of service location only; and a permit for fire damage repair that did not involve any room reconfiguration had been issued. Although
D
Gelinas also claims in his amended appeal that the trial court abused its discretion by refusing to open the judgment in which it had assessed a daily fine of $100 from June 29, 1987, to June 15, 1990, for the “wilful violation” of zoning ordinances pursuant to
The gravamen of Gelinas’ claim is that
“A motion to open and vacate a judgment ... is addressed to the [trial] court’s discretion, and the action of the trial court will not be disturbed on appeal unless it acted unreasonably and in clear abuse of its discretion. ... In determining whether the trial court abused its discretion, this court must make every reasonable presumption in favor of its action. . . . The manner in which [this] discretion is exercised will not be disturbed so long as the court could reasonably conclude as it did.” (Citations omitted; internal quotation
It is undisputed that the trial court imposed the fine for “wilful violation” of the zoning ordinances.
E
Gelinas finally alleges that the trial court abused its discretion because its injunctive order was so overly broad in its scope and application as to deprive him permanently of the use of an entire floor of the subject building. Gelinas requested that the trial court limit the scope of the injunction, as it related to the first floor, to the area formerly occupied by the stage. The trial court, however, enjoined the use of the entire first floor. Contrary to Gelinas’ assertions as to the unreasonableness of the court’s order, however, the trial court allowed him either to take the necessary steps within
We conclude, therefore, that the trial court did not abuse its discretion in framing the scope of the injunctive relief granted.
II
The Town’s Appeal
The town claims in its appeal that the trial court improperly denied the town’s request for an injunction against a use change in the basement of Gelinas’ building that was in violation of § 177-39 of the West Hartford Code. We agree.
The town introduced evidence that Gelinas had illegally introduced commercial uses into the basement beginning in February, 1987, and had entered into additional commercial leases in 1988 and 1989. These commercial uses were in addition to the valid nonconforming assembly hall main use and dining and kitchen accessory uses by the tenant fraternal organization. On July 10, 1987, the assistant zoning enforcement officer ordered Gelinas to return the entire basement to the prior valid nonconforming uses and issued him an infraction ticket. It is undisputed that Gelinas did not appeal the order.
The town consequently requested an injunction, pursuant to
However, “[e]ven in an action brought by a zoning enforcement officer to require conformity with the zoning regulations, the granting of injunctive relief, which must be compatible with the equities of the case, rests
We conclude, therefore, that the trial court abused its discretion by refusing to render judgment entitling the town to injunctive relief from the unauthorized business use of the basement. Accordingly, we reverse the judgment of the trial court on this issue and remand the case to the trial court with direction to render judgment for the town consistent with this opinion. We leave it to the discretion of the trial court to fashion the scope of the injunctive relief to which the town is entitled.
The judgment is reversed in part with respect to the plaintiffs’ appeal, the judgment is reversed with respect to the town’s appeal, and. the case is remanded for further proceedings in accordance with this opinion.
In this opinion Peters, C. J., Borden and Katz, Js. concurred.
Notes
The parties appealed from the judgment of the trial court to the Appellate Court, and we transferred the appeals to this court pursuant to
As supervisor of inspections, Charles J. McCarthy served as the building inspector and the zoning enforcement officer for the town. In his capacity as the town’s building inspector, McCarthy inspected the site on June 25, 1987. He based his subsequent orders to stop work and not to occupy on §§ 177-38 and 177-41 of the West Hartford Code. Section 177-38 provides in relevant part: “No structure shall be erected, expanded or structurally altered and no land use shall be established until a permit therefor has been issued . . . .” Section 177-41 provides in relevant part: “All applications for required permits shall be made to the Building Inspector on forms provided by his office. . . . An application for a building permit or zoning permit shall include the following: (1)... a plot plan . . . drawn to scale . . . showing . . . (c) The existing and proposed use of all existing and proposed structures and lot areas, if other than a one- or two-family residence. ... (2) Such additional information as required by the Building Inspector or by the Planning Director or Commission where a . . . site plan approval is required, where necessary to determine that the requirements of the Zoning Ordinance are met.” The town asserts that the application lacked the required square foot use information so that the town planner could not calculate the off-street parking requirements specified in § 177-321 and was unable, therefore, to fulfill his responsibilities pursuant to § 177-42B (2) that the town planner shall “determine that the requirements of the Zoning Ordinances are met in fact.”
The state building code is the building code for the town pursuant to
The trial court stated: “Apparently, there was a technical problem, as indicated by the testimony relative to the accelerated rehabilitation, where there was never really a finding made whether the conditions were met, and somehow because it didn’t get listed on the calendar, it was dismissed, and there was not a judicial finding regarding the conditions of the accelerated rehabilitation being met.”
Section 177-42B (1) of the West Hartford Code provides that the town planner “shall approve, disapprove or approve with modification . . . proposed site plan[s] . . . within fifteen (15) days after having received the application. . . .”
“(b) Whenever the approval of a site plan is the only requirement to be met or remaining to be met under the zoning regulations for a proposed building, use or structure, a decision on an application for approval of such site plan shall be rendered within sixty-five days after receipt of such site plan. . . .” (Emphasis added.)
Although Gelinas conceded that there had been correspondence between the town and himself concerning the November 17,1987 site plan application, he claimed that the town had not issued a decision approving, denying or modifying his application. The plaintiffs complained jointly that they had received no decision on their revised application for a site plan and sought a writ of mandamus ordering the town to issue a certificate approving the site plan.
In its answer, the town raised numerous special defenses. The town asserted that:
Gelinas raised five special defenses to the town’s counterclaim. The trial court rejected his assertions that site plan approval had arisen by operation of law (
The trial court enjoined Gelinas from using the altered parts of the building until he had obtained all necessary zoning and building authorizations, certificates and permits. The court further ordered Gelinas to remove some of the alterations unless he obtained necessary zoning and building permits and inspection approvals, to pay fines of $100 per day from June 29, 1987, the date on which he had been ordered to obtain site plan approval and building permits, to June 15, 1990, the date on which he had sought the writ of mandamus, for the wilful violation of zoning regulations pursuant to
The plaintiffs contend that this result bars an applicant from ever bringing illegal current uses into compliance with zoning ordinances because current uses cannot be “proposed” uses and, therefore, is “clearly nonsensical.” We reject this characterization. The plaintiffs’ argument would inappropriately deprive responsible zoning officials or commissioners from obtaining the factual information upon which such approval should be predicated, and the argument would reward, with a guarantee of zoning approval, applicants who apply for permits after they have fully implemented changed uses.
The plaintiffs cursorily advance alternative arguments that fail to persuade us. They claim that the involvement of the housing court did not take
The plaintiffs briefly suggest, similarly, that there was no evidence of topical fraud or private mischief to which the trial court alluded in its oral decision. The trial court stated: “[T]he [Supreme] Court in [M & L Homes, Inc. v. Zoning & Planning Commission,
The plaintiffs mention also that they did not waive the time limits set forth in
See footnote 12. The trial court stated: “The court in trying to pierce through all the circumstances, feels it almost can be summed up in the lines of a famous movie: What we have here is a failure to communicate. That’s almost what it sounds like. It might also be stronger than that. It might even be that the failure to communicate has resolved into a dispute which may even have gotten into a feud between the parties. I’m not quite sure, but there is definitely a failure to communicate.” See “Cool Hand Luke” (Warner Brothers 1967) (Strother Martin: “What we’ve got here is a failure to communicate.”).
See footnote 10. The trial court enjoined Gelinas from using the first and second floors of the property except for the uses that had existed pursuant to a 1925 building permit (the first floor store fronts and the second floor apartment), unless and until he had obtained all necessary zoning and building authorizations, certificates and permits. The court granted the defendant sixty days to comply with its order and retained jurisdiction to
The town contends that we should not consider the plaintiffs’ estoppel claim because it was not raised distinctly at trial, stated in their trial briefs, or pleaded in their answers. See
The trial court order read: “The defendant shall pay $100 per day from June 29,1987, to June 15,1990, as a fine for his unlawful alteration of the structure without zoning and building permits at 119 Park Road and for his unlawful maintenance and use of the rooms in the first floor for offices without authorization, permits or a certificate of occupancy, such fine shall be for the wilful violation of the zoning regulations pursuant to
See footnote 8.
In 1987, the General Assembly increased the maximum civil penalty for failure to comply with an order to discontinue or a cease and desist order from $500 to $2500. Public Acts 1987, No. 87-347. Senator Frank D. Barrows remarked: “[Substitute House Bill 6750] raises . . . penalties [for] violating local zoning . . . regulations from $500 to a maximum of $2500. The penalties may be imposed on (1) someone who fails to comply immediately with cease and desist orders from the zoning enforcement official for violation of land [grading] or earth removal violations, (2) someone who fails to comply within 10 working days of being served with the order to [discontinue] any violations, and (3) someone who continues to violate the regulation specified in either order.” 30 S. Proc., Pt. 11,1987 Sess., p. 3838.
Because we conclude that the trial court improperly assessed the daily fines, we need not reach Gelinas’ related claim that the trial court improperly computed the time frame within which the fines would be assessed.
Dissenting Opinion
dissenting. I disagree with the majority’s conclusion that the defendant town’s failure to render a decision on the plaintiffs’ site plan application did not result in automatic approval of the application.
The majority rejects the plain meaning of
The majority’s conclusion that the “use of the adjective ‘proposed’ indicates that the legislature meant to distinguish planned structures, alterations or uses from structures, alterations or uses that have already been fully or significantly implemented . . . without the required building permits or zoning approvals” is unfounded. The better reading of these statutes is that “proposed” simply refers to the project that the applicant seeks to have approved rather than to the status of the project at the time the site plan is submitted. The only reason for distinguishing between planned changes and changes that have been significantly implemented would be to penalize applicants who begin work on a project without first obtaining approval for their
The plaintiffs correctly point out that the majority’s construction of
I believe that the court’s decision today adds another layer of confusion to our law of zoning. The court makes application of the mandatory time limit of
Local zoning boards are composed of citizen volunteers, most of whom probably are not lawyers. The court’s decision will force the local boards in all 169 of Connecticut’s towns and cities to grapple with another mass of complexities in what is already a maze for the unwary. Uncertainty and confusion in the law may be great for some, but not for those who volunteer their time to serve on local zoning boards.
What troubles me the most about today’s decision is that the court does not offer any practical considerations in support of its construction of the statutes. The purpose of
In statutory construction, “ ‘[w]e must avoid a consequence which fails to attain a rational and sensible result which bears most directly on the object which the legislature sought to obtain.’ LaProvidenza v. State Employees’ Retirement Commission,
I would hold that the plaintiffs’ site plan was automatically approved with the passage of time. Accordingly, I would remand with instructions to issue the writ of mandamus requested by the plaintiffs and dissolve the injunction issued against the plaintiff Gelinas. I would also hold that per diem civil penalties may not be assessed against Gelinas beyond the date when automatic approval of his application would have occurred.
See footnotes 5 and 6 of the majority opinion.