30 N.Y.S. 191 | Superior Court of Buffalo | 1894
The parties to this action entered into a written contract whereby plaintiff was to furnish and place in the house of the defendant a hot water heating apparatus, according to certain plans and specifications. The contract contains sixteen articles, by the first of which it is provided that plaintiff shall well and sufficiently perform and finish the work under the direction and to the satisfaction of the architect, acting as agent of the defendant, agreeably to the drawings and specifications made by the architect. By the second, if any dispute arises respecting the true meaning of the drawings or specifications, the arcjiitect’s decision thereon is made final and conclusive. By the third, if any alteration in the work was made and the parties could not agree upon valuation, the matter was to be determined by three arbitrators, one chosen by each party, and these parties to choose a third, no person personally connected' with the work to be chosen. Other provisions in the articles relating to delays, failure to furnish materials, and matters relating thereto, the architect
It is apparent from this contract that the parties have chosen to make the architect the arbiter, except in certain specified instances, of which no complaint is made, and to make his certificate of performance a condition precedent to the right to demand pay, and conclusive upon the defendant in the absence of fraud or mistake. Wyckoff v. Meyers, 44 N. Y. 143; Whiteman v. Mayor, etc., 21 Hun, 117; Pucci v. Barney, 1 Misc. Rep. 84; 20 N. Y. Supp. 375.
The contract price was $1,045, payable in three installments, two of $470 and one of $105. The last payment of $470 was only to be made when the entire apparatus was set up and completed, and the $105 thirty days later. Plaintiff gave evidence tending to show completion of the contract, and obtained and produced upon the trial the architect’s certificate that the work was completed to his satisfaction. This certificate within the meaning of the contract was final, as by its terms appears everything necessary to entitle plaintiff to full payment, and, although it was given before the final payment fell due, yet it certified to all the facts upon which the final payment depended. It was, therefore, the certificate contemplated by the contract.
Defendant gave evidence tending to show that there was a
Ordered accordingly.