Garratt-Ford Co. v. Brennan

232 Mass. 493 | Mass. | 1919

Carroll, J.

The defendant Brennan made a contract in' August, 1894, with the city of Boston (the trustee in the present action) to build surgical operating and open ward buildings. The plaintiff was a subcontractor under Brennan. On August 11, 1896, the parties modified the contract; and pursuant to the terms of the modification the city took possession and was using the buildings, except the amphitheatre and adjacent rooms, prior to July 30, 1898, — the date of the service of -the trustee process in this action. To this process the city answered, “No funds.”

In December, 1899, Brennan was adjudicated a bankrupt, and in March, 1900, filed a plea of bankruptcy in the instant case, *497and the action was continued. In 1904 Brennan’s trustee in bankruptcy brought an action against the city to recover the balance due Brennan, and additional damages for delay in the work under the contract above referred to.

In February, 1908, the plaintiff in the present case filed interrogatories to be answered by the trustee, the city of Boston. The city answered setting forth that Brennan’s trustee- in bankruptcy claimed the sum of $19,721.05 under the building contract, and that this claim was disputed by the city; that it did not know until the termination of the suit of Brennan’s trustee against it how much, if anything, was due from the city, and “that until such judgment or verdict is entered it ought not to be called upon to answer to plaintiff’s interrogatories.”

The present case then stood without further action until the determination of the action of the trustee in bankruptcy against the city of Boston. The latter action was referred to an auditor, who in March, 1913, filed a report stating that there was due from the city to Brennan the sum of $10,879.41 with interest. The city agreed to an entry of judgment based on the report of the auditor, and later paid the trustee in bankruptcy $12,184.94. In the report of the auditor subsequently appointed, dated February 1, 1917, and hereinafter referred to, it was found that this payment was made through inadvertence.

On December 26,1914, the plaintiff in the present action moved that the city answer the interrogatories already filed; and it also filed additional interrogatories. After the interrogatories were answered, the plaintiff filed allegations of fact not stated nor denied by the city, under R. L. c. 189, § 15. To these allegations of fact the city made no answer.

On October 7,1915, the plaintiff moved that the city of Boston be charged as trustee. At the hearing of this motion the city denied the allegations of fact on file. Oral evidence was introduced as well as the pleadings, the report of the auditor in the case of Brennan’s trustee in bankruptcy against the city, and the pleadings in a case brought by one Van Norden against Brennan, in which the city was summoned as trustee under date of March 8, 1899, and in its sworn answer admitted it owed Brennan $4,129.41. The auditor in the case of Brennan’s trustee against the city found that by the terms of the contract the city was to *498pay Brennan $221,476, and that provision was made for extra work; that he had already been paid $233,099.84, and a balance was due, which Brennan contended was $19,721.05, and the city $4,129.41.

The defendant Brennan was called as a witness at the hearing on the motion to charge the trustee, and testified that before July 30, 1898 (the date of the present action), he had completed the work called for in the contract with the city and neither he nor any subcontractors employed by him, with his knowledge or consent did any work or furnished any material after that date, “that the city of Boston long before that time was in possession of the building and occupying the same for the purpose for which it was erected.” The written correspondence between Brennan and the city during May, June and July, 1898, was also in evidence. ‘ After the evidence was introduced the court appointed an auditor to determine whether any work was done or materials furnished by Brennan after July 30, 1898, and before February, 1904, under his contract with the city; and if such work was done, whether the city owed Brennan therefor. His report was filed February 1, 1917, and on March 1, 1918, it was offered in evidence by the plaintiff. The city introduced no further evidence but filed requests for rulings. On March 11, 1918, the court granted some of the requests, refused others, and allowed the plaintiff's motion charging the city of Boston as trustee, from which ruling the city appealed and alleged exceptions.

Under R. L. c. 189, § 15, the answer and statements of a trustee under oath shall be considered as true in determining how far he is chargeable. But on the question of charging or discharging the trustee, either party may allege and prove facts not stated or denied by the trustee, which may be material; and a question of fact which arises upon such additional allegations may be tried by the court or a jury. R. L. c. 189, § 16. In this procedure the party is confined to the proof of facts “not stated nor denied by the supposed trustee.” Gouch v. Tolman, 10 Cush. 104. No objection, however, was raised to the procedure adopted nor to the evidence; and no complaint is made that at the hearing on the motion to charge the city as trustee any facts were alleged or proved which were not admissible under the statute.

*499The trustee’s exceptions must be overruled. The first and second requests ask for the discharge of the trustee on all the evidence. As all the evidence is not reported we cannot say that the judge was wrong in denying these requests. Requests numbered 8, 12, 14, 15 and 17 also are based upon all the evidence in the case, and for the reasons given there was no error in refusing these requests.

The third request asked the judge to rule that if all the work contemplated by the contract of Brennan with the city was not completed on or before July 30, 1898, the city owed nothing to Brennan, “absolutely and without any contingency.” This request called for consideration of the whole evidence. There was evidence that the work was entirely completed on that date, and also to the contrary. It was for the judge to decide the question, and if he believed the testimony of Brennan the work under the contract was finished on July 30, 1898, when the plaintiff’s writ was served on the trustee; and if any work was done subsequently, to that time, it was done without his (Brennan’s) knowledge or consent and the city was already in possession of the buildings and occupying the same. The denial of this request was not erroneous.

What we have said disposes of requests numbered 4, 5 and 11.

Referring to the sixth and seventh requests, — that if Brennan had not completed the contract the city had no funds in its hands which could be attached by trustee process, and that Brennan was responsible for all work done in the completion of the contract, — in addition to the testimony of Brennan that no work was done after the date of the writ in the present case, the auditor’s report in the case of the trustee in bankruptcy against the city was in evidence and showed that the city admitted it owed Brennan $4,129.41. This was confirmed by the city’s answer as trustee in the Van Norden case, admitting the sum of $4,129.41 due to Brennan; and in answer to the plaintiff’s interrogatory the trustee stated that approximately $4,000 was held until the contract should be completed. Although the report of the auditor of February 1, 1917, showed that some work was done by subcontractors after July 30, 1898, in completion of Brennan’s contract, in view of all the findings of the auditor and all the evidence in the case which was before the judge, including the trustee’s *500admissions, we find no error of law in refusing the sixth and seventh requests.

The ninth request refers to the article in the contract which .gave the architect the right, if dissatisfied with the progress of the work, on three days’ notice to the contractor to correct the work and complete it according to the contract, “the cost thereof . . . [to] be;paid by said contractor.” There is no evidence that the architect acted under this provision of the contract, therefore the request could not properly have been given.

The tenth request is based on article nine of the contract. The original contract was subsequently modified, and in the absence of evidence we cannot determine that the time during which the city could hold the reserve payment had not elapsed on July 30, 1898.

We treat the direction of the court in allowing the plaintiff’s motion to charge the trustee not as final but merely as an order to charge the trustee. The exceptions are before us and present all the questions' of law open on the appeal. We find no error of law. The order charging the trustee must be affirmed, and the ■exceptions overruled.

So ordered.