9 Utah 350 | Utah | 1893
It appears from this record that in 1889 the Bear Lake
While these actions were pending, Garland finished his work, and filed his statement for a lien, and included in it the amount due, according to the measurement and estimate of the company’s engineer, and the excess claimed by his subcontractors. In these actions the waterworks and irrigation company was made a party, and the result of the trial was, the estimates of the company’s engineer were rejected, and the court, in its judgment against Garland, allowed the subcontractors the full amount of their claims, and rendered judgment against the waterworks and irrigation company, in favor of Garland, for the amount of the excess over the estimate of the company’s engineer.
• The plaintiff did not commence this suit to enforce his lien until nine months after he had filed the statement for a lien in' the recorder’s office. The law in force when plaintiff made his contract, and commenced work, required an action to enforce the lien to be commenced within 90 •days after filing the statement. The water and irrigation company insist that the plaintiff lost his lien because he did not commence suit within that time, while the plaintiff claims that his right to a lien, and to the remedy to enforce it, must be determined (as the court below held) by the law in force March 12, 1890, which permits the suit to be com-' menced within one year after the statement is filed. Section 32 of the latter act is as follows: “All acts and parts of acts inconsistent with the provisions of this act,
If the party contracting for the labor or materials refuses to comply with the contract before the other party has done any work or furnished any materials, the latter has his right to damages, and the ordinary remedy to recover them, but in that case there is no mechanic's lien. If, after the latter commences work or furnishes some material, the former refuses to permit him to complete the work or furnish more material, the party who has done some of the work or furnished some material, upon filing the-statement required, has a lien to that extent, and may-avail himself of the remedy to enforce it. The obligation to perform the contract arises when it is signed by the-parties, and delivered. The lien arises when work is done- or materials are furnished under it, and the statement is filed, and it relates then to the time the work or delivery of the materials commenced. The lien does not arise until some of the work is done or some of the materials are-furnished, and the party for whom the work is done or to-whom the materials are furnished has refused or failed to-
So with respect to the remedy. If the party to the contract for whom the worlc is to be done, or the material is to be delivered, violates it before such work or delivery is ■commenced, the other party has a right to the ordinary remedy, but not the right to the lien, or to the remedy to ■enforce it, referred to in the mechanic's lien law. But if, after such work or delivery commences, the party for or to whom such work or delivery is due violates the contract, and the statement is duly filed, the right to the remedj^ to enforce the lien accrues. The plaintiff did not complete the contract to do the work and furnish the materials until after the law of March 12, 1890, took effect, and there was no breach on the part of the water and irrigation company until after such completion, and the statement required was not filed' till after that. It is plain that the court ■committed no error in applying the law of March 12, 1890, to the facts of the case. Turney v. Saunders, 4 Scam. 527; Ogden v. Saunders, 12 Wheat. 349.
The Bear Lake & River Waterworks & Irrigation Company insists that the court erred in holding that the plaintiff and Corey Bros. & Co. had a lien on the irrigation ditch in question, because it found that the right of way was acquired after the lien attached. The ditch was constructed on the public lands of the United States, for irrigation purposes, and the right of way was obtained by going upon the land, and making the ditch. By so doing the water and irrigation company obtained a right to occupy ,so much of the land as was necessary for its canal. It acquired such a right to use or transfer the same as the law recognizes and protects. Sections 2339 and 2340 of the Revised Statutes of the United States are as follows: “Sec. .2339. Whenever, by priority of possession, rights to the
These sections recognized the right of individuals to go upon the public land of the United States, and to construct ditches and canals for mining, agricultural, manufacturing, and other useful-purposes, and the right of 'way so. taken and held the law acknowledges and confirms, and makes all patents granted, and pre-emptions and homesteads allowed, subject to such rights. Jennison v. Kirk, 98 U. S. 453; Broder v. Water Co., 101 U. S. 274. The law under which this suit was instituted, securing liens to mechanics and others, declares “that whoever shall do work or furnish materials by contract, express or implied with the owner of any land * * * shall have a lien upon such land, building, structure or other improvement for the amount and value of the work so done or materials so furnished to the extent of the interest or claim of such owner * * * any person having an assignable, transferable or conveyable interest or claim in or to any land, building, structure or other property mentioned in this act, shall be
The lien of the plaintiff and of Corey Bros. & Co. relates to the time they commenced work on the ditch, and as fast as it was constructed the right of way was obtained by the water and irrigation company. The contract was binding on both parties, and we must hold that the lien attached as the work progressed. The water and irrigation company will not be heard to say that the lien did not attach to the ditch which the parties who constructed it brought into existence. The law will not permit-the company to say ii_VVe have the property that your labor created and gave us, but we will not compensate you for it, or concede your lien to secure its payment.” We are of the opinion that the defendant was the owner of the ditch, within the meaning of the-law quoted, and that a lien -to secure the amount due the plaintiff and Corey Bros. & Co., respectively, relates to the time they commenced work. Turney v. Saunders, 4 Scam. 527.
The Jarvis-Conklin Mortgage Trust Company insist that the court below erred in holding that the lien in favor of Corey Bros. & Co. on the canal was superior to the trust deed on the same property to secure its debt. It is true that the Jarvis-Conklin Mortgage Trust Company obtained their deed of trust before Corey Bros. & Co. commenced work, and that the deed, by its terms, included all the property the water and irrigation company then had, or might thereafter acquire. When mechanics, material men, or other persons make improvements on land on which there is a mortgage or trust deed, such mortgage or trust deed will be superior to the lien to secure the mechanics or other persons; but the water and irrigation company had
In the suit by the; subcontractors Annett & Thompson against William Garland, and the suit of the latter against the subcontractor McMartin, it was alléged that the measurements and estimates authorized by the contracts, and made by the engineer of the Bear Lake & Biver Waterworks & Irrigation Company, were fraudulent and incorrect; and on motion of Garland the latter company was made a party to those actions, and the issue as to the correctness of the measurements and estimates of the engineer was tried, and decided against the company, and the actual amount found due exceeded such estimate by $23,000, and a decree was rendered against Garland for the full amount of the subcontractors’ demand, including this excess,— $23,000. A decree was also rendered in favor of Garland against the water and irrigation company for this $23,000, but the amount due Garland, according to the estimates of the engineer, was not litigated between him and the company. In the suit in hand the plaintiff claims, not only the amount due according to the estimate, but the $23;000 ■ excess, as well. The trial court, in its decree, gave him
Numerous other errors are alleged in this record, which, upon examination, we hold are not well assigned. The judgment of the court below is affirmed.