The plaintiffs brought this action for damages, alleging a breach of the defendants’ agreement to perform “the agreements and items of work” as set forth in a judgment. The judgment referred to was rendered, without any adjudication of the issues, in November, 1959, by the Court of Common Pleas by agreement of the parties in fulfilment of a stipulаtion entered into by the parties to the present action and by others not involved in the present proceedings. The defendants have appealed to this court from an award of damages to the plaintiffs by the Superior Court.
The portion of the 1959 judgment pertinent to this appeal provided that the defendants herein “shall have the following work performed in a competent, workman-like manner by a competent contractor selected by the plaintiffs and agreed to by said defendants; said work to be performed within a reasonable time and as soon as practicable, and said work to include thе following: a. Install berm or curbing as needed on Brook Lane in the area of the culvert adjoining the property of the defendant, Wilmott, and in front of the property of the defendant, Crosby, for the purpose of diverting the normal
The essence of the judgment rendered by the Court of Common Pleas conforming to the stipulation of the parties was that the parties to the litigation voluntarily entered into an agreement ostensibly setting their dispute or disputes at rest.
Bryan
v.
Reynolds,
The present cause of action is for damages which, in effect, is an action to enforce the terms of the judgment. Although an action on a judgment is not favored as being generally vexatious and oppressive, the weight of authority is to the effect thаt an allegation of nonpayment is sufficient reason for instituting suit.
Denison
v.
Williams,
The basic facts necessary to a disposition of the questions involved may be summаrized as follows: Pursuant to the judgment the plaintiffs consulted
Although the judgment only required that in сhoosing a contractor the plaintiffs select one who is competent, they nevertheless submitted estimates from four contractors for the approval of the defendants. Much of the matter contained in the finding and briefs relates to the reasonableness of the so-called bids from the four contraсtors so selected. The word “competent” in the sense which it is used in the judgment means that a contractor must be capable or qualified or that he possess the knowledge, skill, experience and available equipment which a reasonable man would realize that a contractor must have in order tо do the work which he
The trial court found and сoncluded, inter alia, that the estimates of The North Haven Construction Company, Inc., The Velleca Construction Corporation, and The Roma Construction Company were all reasonable in the light of what each company proposed to do under its respective bid; that the work proposed tо be done was reasonably necessary to comply with the terms of the judgment of the Court of Common Pleas; that each company was a reliable and reputable contractor; and that the difference in prices between each of these bids received by the plaintiffs was not unusual since a bid is generally made on intangibles and is the result of the personal consideration of the various items involved by the person making the estimate.
The defendants claim that an interpretation of paragraphs (a), (b) and (e) of the judgment did not require them to (1) instal more than seventy-five feet of berm or curbing, (2) dredge the pond to a depth in excess of five and one-half feet, or (3) clean out the brook.
The parties were at all times in substantial disagreement as to the work to be performed and the total amount to be paid for the work to be done
As long as the judgment was in effect the plaintiffs could seek process to enforce it. See
Christmas
v.
Russell,
A resolution of the issues raised in this action necessarily required the trial court to interpret the terms of the judgment to which the parties consented. See
United States
v.
Atlantic Refining Co.,
In its interpretation of paragraph (a), the court concluded that the judgment did not specify any minimum or maximum of linear feet for the berm or curbing on Brook Lane, and the length which was needed as called for by the judgment was a question of fact for the trier to determine. This was correct since thе court was compelled to determine, in view of the conflict in language, what was a reasonable course to take under all the circumstances. Paragraph (a) of the judgment stated that the berm or
The court construed paragraph (b) оf the judgment to mean that the plaintiffs’ pond was to be dredged to an average depth of five and one-half feet because some of the contractors testified that in certain places they would dredge to a depth of from seven to eight feet but that on the overall the average depth would be five and one-half feet. The evidence and testimony from competent witnesses to the contrary, however, the judgment specifically stated “dredge ... to a maximum depth of five and one-half feet.” The court was incorrect in this interpretation since the word “maximum” as used herein, under the circumstances, cannot be interpreted to mean average. 2
The claim of the defendants that cleaning out of a brook was not required under paragraph (e) of the judgment is without merit since a reasonable interpretation of the judgment contemplated such a procedure and since there was abundant evidenсe for the court to find and conclude that this work was necessary for the normal flow of water under the terms of the judgment and was in accordance with good engineering practice.
Basically, it is the claim of the defendants that the plaintiffs did not submit any bid to the defendants which corresponded with the work to be done under the stipulation for judgment in the Court of Common Pleas; that the estimate of C. W. Blakeslee and Sons, Inc., “did not correspond with the aforesaid stipulation in that it included the dredging of a pond to a depth from seven to eight feet when the stipulation required dredging to a depth of five and one-half feet”; and that a bid of D. Y. Frione and Company, Inc., of $2185 submitted by the defendants in response to a letter from one of the plaintiffs’ former attorneys was improperly rejected by the plaintiffs.
The judgment of the Court of Common Pleas determined that the work should be performed by the defendants. There was evidence upon which the court could properly find and conclude, as it did, that the contractors selected by the plaintiffs to do the work were competent contractors. The defendants did not at any time, however, consult with any one of them in an effort to perform its agreement. Since the parties could not agree and since the plaintiffs proceeded to enforce the judgment by asking for damages, the court acted properly in determining a reasonable amount in damages from all the
Upon the evidence, the court acted properly in deciding that the plaintiffs need not accept the vague, ambiguous and, what appeared to be, unreasonable estimate offered by the defendants, which, incidentally, was not contemplated in the terms of the judgment upon which the рlaintiffs brought suit.
An assessment of damages was required by the court in the present ease since the amount of the judgment upon which this action was brought was unliquidated and because the judgment was not definitive so as to be conclusive upon the parties and so as to terminate the litigation. The nature and amount of the work to be done was in controversy. The rights of the parties were not settled by the judgment, and it was ambiguous and uncertain, required legal interpretation, and was silent as to the amount of recovery. See
Grant
v.
Phoenix Mutual Life Ins. Co.,
The judgment of the Court of Common Pleas was sadly defective in its lack of specificity. “A judgment of the nature of the one here attempted should be so precise and definite in its terms that the parties
There is no error.
In this оpinion Alcorn, Thim and Ryan, Js., concurred; House, J., concurred in the result.
Notes
No question of unreasonable delay in asking for relief has been raised so that the issue of failure to take prompter action to enforce the judgment is not before us. See
Weil v. Poulsen,
This interpretation did not affect the correctness of the ultimate decision of the court since, in awarding damages, the court accepted the opinion of Norman Picard of O. W. Blakeslee and Sons, Inc., and found in that connection upon conflicting evidence that “Blaheslee proposed to dredge the existing pond to a depth of five and one-half feet.”
