GALVESTON LFG, LLC, et al. v. BIOFERM ENERGY SYSTEMS, LLC,
22-cv-538-wmc
IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF WISCONSIN
August 21, 2023
WILLIAM M. CONLEY, District Judge
OPINION AND ORDER
ALLEGATIONS OF FACT1
Galveston LFG owns and operates a gas processing facility in Galveston, Texas. Galveston LFG is a Delaware limited liability company with its principal place of business in Texas. Galveston LFG is a wholly owned subsidiary of Montauk Energy Holdings, a Delaware limited liability company, which, in turn, is a wholly owned subsidiary of Montauk Renewables, Inc., a Delaware corporation, both with their principal place of business in Pennsylvania. Montauk is an energy company specializing in processing landfill gas for beneficial use as a fuel. Defendant BIOFerm is a Madison-based, Wisconsin limited liability company that designs аnd manufactures biodigesters that convert organic waste into Renewable Natural Gas (“RNG“), with all of its members domiciled in Wisconsin. (Dkt. #1, at ¶ 5.)2
In developing a landfill gas processing facility near Galveston, Texas, Montauk decided on the so-called “Pressure Swing Adsorption” (“PSA“) process to convert landfill gas. (Dkt. #1, at ¶ 16.) The PSA process uses a special adsorbent media to separate the gas species in landfills under high pressure, pushing the undesirable gases into pores of a molecular sieve media. Dropping the pressure, a vacuum then releases the undesired gases and regenerates the media, leaving purified RNG.
The parties executed the contract on April 17, 2018, in which BIOFerm agreed to design and commission an RNG conversion facility for Montauk in exchange for $13,150,000.00. (Dkt. #1, at ¶ 32; dkt. #1-4 (Ex. B).) Work commenced on the project in late spring 2018, and Montauk alleges the parties agreed to a series of change orders during construction. For еxample, Montauk attached to its complaint a change order dated
Power was first applied to the system on August 20, 2019, although performance testing did not start until February 2020. Montauk alleges that the performance results did not meet what it understood to be the minimum contractually agreed requirements. Over time, Montаuk allegedly discovered additional problems, including that the plates holding the media had been improperly welded by BIOFerm‘s subcontractor. In an April 21, 2020, memo to Montauk, BIOFerm recommended a fix, which entailed re-opening the PSA vessels, removing the previously installed media, properly welding the plates, then using a vacuum process to reinstall the media. (Dkt. #1-9 (Ex. G).) BIOFerm later reinstalled the media as proposed during a scheduled shutdown period in April 2020, except that Montauk alleges BIOFerm failed to replace all the media that it removed, causing continued performance problems with the RNG conversion project. Another problem Montauk alleges is that BIOFerm claimed the facility needed replacement blowers and parts, as seen in a January 20, 2020, purchase order, but refused to cover these costs. (Dkt. #1-8 (Ex. F).) Additionally, BIOFerm allegedly insisted thаt the contract warranty would expire August 19, 2020, one year after power was first applied, despite the delay in conducting preliminary testing and the performance problems that existed during the first several months. (Dkt. #1-10 (Ex. H).)
The only cause of action at issue in BIOFerm‘s pending motion to dismiss is Count Six for breaсh of the DTPA. This count accuses BIOFerm of making “false, misleading and deceptive statements and representations for the purpose of deceiving the public” through the twelve statements relating to the Galveston project that follow:
- That the biogas conversion system it intended to provide would meet the promised performance specifications.
- That the biogas conversion system it intended to provide would rеsult in cost savings.
- That the removal and reinstallation of the PSA media in April 2020 by BIOFerm was not only permissible but appropriate according to Carbotech.
That BIOFerm or its subcontractors possessed the necessary skill and expertise to properly design, build, and commission the biogas conversion system. - That BIOFerm and or its subcontractors would follow the specifications required by BIOFerm‘s design, including properly welding the bottom plates in the PSA vessels in the first instance.
- That BIOFerm or its subcontractors possessed the necessary skill, expertise, and equipment to allow them to remove and re-install the PSA media in the pressure vessels.
- That BIOFerm promised a turnkey system that was easy to install and therefore available within a short period of time.
- That BIOFerm‘s modifications to the design and or its failure to follow the specifications in the design were acceptable to Carbotech.
- That BIOFerm actually consulted and followed Carbotech‘s directions with respect to its attempts to reinstall and reuse the media, including when it failed to use all of the media originally supplied when it was re-used in April 2020.
- That BIOFerm‘s performance guarantee is the best in the industry, that it would be honored, and that it would not interfere with Galveston‘s attempts to seek additional resources (including from BIOFerm‘s alleged partner, Cаrbotech) in trying to not only meet performance testing guarantees and requirements but provide a Plant that was as promised.
- That installing the anchor bolts at a depth substantially less than the installation depth specified in the Contract was reasonable.
- That designing and building a pressurized system without a pressure relief valve was reasonable.
(Dkt. #1, at ¶ 117(a)-(l).)
OPINION
BIOFerm argues there are two discrete reasons to dismiss Montauk‘s
The statute prohibits a person or firm with intent to offer anything for sale or hire from making any representations to “the public” that are “untrue, deceptive or misleading.”
I. Representations Made More Than Three Years Before Suit
BIOFerm argues that seven of the allegations in the complaint were barred by the statute of repose because on the face of the complaint more than three years had already passed between the “occurrеnce” of the alleged unlawful representations and Montauk filing the complaint, regardless of whether Montauk had discovered the injury or wrongdoing. (Dkt. #11, at 5-6 (citing Kain, 635 N.W.2d at 645).) Specifically, the complaint was filed on September 20, 2022, meaning that the critical date is September
Nevertheless, Montauk argues that this case is “unique,” because it was “impossible” for them to know of BIOFerm‘s fraudulent conduct within the three-year timeframe. (Dkt. #14, at 1, 5.) In particular, Montauk argues that BIOFerm created problems that it “fraudulently claimed it had the expertise to resolve.” (Id. at 1-2.) However, Montauk fails to distinguish BIOFerm‘s argument and caselaw. (Dkt. #14 at 6.)
In Kain, the plaintiff argued the Wisconsin Legislature “could not have intended to protect false advertisers who could hide the falsity of their representations for more than three years.” 635 N.W.2d at 645. However, the Kain court rejected that argument, explaining that a line of Wisconsin cases found limitation statutes to be the result of the legislature‘s policy considerations, and the language of
II. Representations Made After Montauk And BIOFerm Entered Into Their Contract
BIOFerm further аrgues that any remaining allegations of Montauk‘s Count Six occurred after contract formation are barred by the “public” scope of the statute. (Dkt. #11, at 9.) As already noted, the statute prohibits untrue, deceptive, or misleading representations to “the public” only.
Montauk responds that BIOFerm‘s argument is overly simplistic. (Dkt. #14, at 9.) According to Montauk, the contract “by design, envisioned further negotiations between the parties as unforeseen issues arose.” (Id.) Montauk further argues that its sixth cause
Montauk cites La Crosse County v. Trinity Industries, Inc., No. 15-cv-117-jdp, 2016 WL 1274623 (W.D. Wis. Mar. 31, 2016), to argue it was unclear BIOFerm and Montauk had a contractual relationship, but the La Crosse cоurt denied a motion to dismiss a DTPA claim because it inferred that the parties did not have an ongoing contractual relationship, and therefore, each of the induced purchases arose from separate contracts; thus, it could not definitively conclude the plaintiff was not a member of the public when the defendant made the allegedly false representations. See id., at *8-9 (noting the parties had “not filed cоpies of their sales contract (or contracts),” nor had “they described the specifics of their contractual relationship“). Here, no such inference is possible since plaintiff expressly alleges that the alleged post-April 17, 2018, representations between Montauk and BIOFerm pertain to the subject of their original contract: the Galveston RNG project.
Finally, Montauk argues that fraudulent representations made outside the three-year statute of repose may be actionable if part of a “continuing fraud,” citing Werner v. Pittway Corp., 90 F. Supp. 2d 1018 (W.D. Wis. 2000), and Northcentral Tech. Coll. v. Doron Precision Sys., Inc., No. 13-cv-425-slc, 2013 WL 5719459 (W.D. Wis. Oct. 21, 2013), but the application of that theory is misplaced here. (Dkt. #14, at 7-8 & n.1.) In Werner, the DTPA claimants had purchased or received defective smoke alarms more than three years before their complaint was filed. 90 F. Supp. 2d at 1033. In dicta, the Werner opinion suggested that plaintiffs’ claims could have survived
The Northcentral opinion does not support Montauk‘s continuing fraud theory either. As here, the DTPA claimants formed a contract with defendant more than three years before the complaint was filed. 2013 WL 5719459, at *3. Also as here, the Northcentral claimants cited to Werner in alleging that defendant “continued to violate the act during the three-year repose period.” Id. However, Northcentral held that mere allegation alone was insufficient to state a DTPA claim without an additional showing under
Accordingly, all of Montauk‘s alleged misrepresentations are either-time barred or otherwisе outside the scope of
III. Untrue, Deceptive, or Misleading Representations
In the alternative, BIOFerm argues dismissal of Count Six is appropriate because all of the statements alleged in the complaint were “non-falsifiable,” mere puffery, or not “untrue, deceptive or misleading” within the meaning of
IV. Alternative Motion for Leave
Finally, Montauk argues that if this court determines its allegations are barred as pleaded under
ORDER
IT IS ORDERED that BIOFerm‘s motion to dismiss the Sixth Cause of Action in Montauk‘s complaint (dkt. #10) is GRANTED.
Entered this 21st day of August, 2023.
BY THE COURT:
/s/
WILLIAM M. CONLEY
District Judge
