Galveston, Harrisburg & San Antonio Railway Co. v. Johnson

74 Tex. 256 | Tex. | 1889

Gaines, Associate Judge.

This suit was brought by appellee to recover of the appellant corporation a balance alleged to be due upon a contract for grading a part or its road. The petition, after setting forth the execution and terms of the contract, alleges that the plaintiff complied in all respects with its stipulations as to five sections of the road and admits a full payment therefor by defendant except in two particulars. It is averred that by the terms of the agreement the plaintiff was to receive for rock embankment thirty cents per cubic yard, to be actually measured in the embankment, and for overhaul ” on the material in the embankment two cents per cubic yard per hundred feet, to be estimated by the same measurement. By overhaul ” we understand is meant the distance in excess of one hundred feet that the material was transported. The *259petition admits a partial payment for the rock embankment and for the overhaul on that work.

The defendant pleaded a general denial, and also denied specially that under a proper construction of the contract it was liable to plaintiff in any amount beyond that which had been paid. There were other matters alleged in defense that will be considered in another part of the •opinion.

We think the determination of the case in this court depends upon the construction of the written agreement between the parties. There is but little conflict in the evidence. The facts upon the main issues are undisputed. The testimony shows that the rock embankments were made almost wholly from the material taken from the'cuts, and that after being placed in the embankment the cubic contents of the embankment was about fifty per cent more than the contents of the excavation from which it was taken; for example, when the excavation in solid rock measured 6000 feet the embankment made with the rock taken from it would measure 9000 feet.

The plaintiff claimed that under the terms of the contract in estimating his compensation both for the enbankment itself and for the overhaul of the rock which composed it the actual measurement of the ■embankment was to be taken; while on the other hand defendant claimed that he was to be paid by excavation measure. If thé defendant’s construction of the contract is correct, then it is not disputed that the plaintiff has been fully paid. If, however, the construction claimed by plaintiff be the true one, the evidence shows beyond controversy that he is entitled to the full amount claimed in his petition and awarded him by the verdict of the jury. The testimony of the only witness introduced by defendant as to the quantity of the embankments would have given .him more than he claimed, if he was to be paid by the actual measurement of the rock embankments.

The following is the stipulation in the contract as to the compensation to be paid for the work:

“And the party of the second part (appellant) hereby covenant and agree that whenever in the opinion of their chief engineer this contract shall have been wholly completed by the party of the first part (appellee) they will pay in currency for the performance of the same in full for material and labor as follows, to wit: Barth work, per cubic yard, 23 cents; solid rock, per cubic yard, $1.22-|-; loose rock, per cubic yard, 90 cents; compact gravel, per cubic yard, 35 cents; side hill, excavating rock, per cubic yard, 90 cents; clearing and grubbing, $16 per acre; rock embankment, per cubic yard, 30 cents; average overhaul, 2 cents per yard per 100 feet; freehaul, 100 feet; overhaul outside right of way to include actual haul, 2 cents per yard per 100 feet; 100 feet of embankment free ■dirt. * * *
*260“The above price for excavation includes delivery into banks where the extreme haul does not exceed 2000 feet. Where the haul exceeds 100 feet the price for haul on average overhaul, 2 cents per cubic yard per 100 feet. The extreme haul, however, shall not exceed 2000 feet.”

If this stood alone we think there could be no question that in estimating the amount to be paid for the rock embankment it should be fixed by the number of cubic yards in the embankments themselves. But the contract refers to certain specifications as being annexed to it and as constituting a part of the agreement. In point of fact no specifications were annexed to the written agreement. The plaintiff testified that he never saw any specifications, and that he knew of none. On the other-hand James Converse, who was the chief engineer of the defendant corporation and its superintendent of construction, and who executed the contract on its behalf, testified that the contract and specifications were fully discussed between him and plaintiff at and before the execution of the contract, and that at the time he delivered him a copy of the specifications. The specifications were printed, and as he testified were made a part of all the construction contracts of the company. The specifications introduced in evidence contained this provision:

“ The measurements of quantities will usually be made in the cuts or pits from which the material has been taken. When quantities are determined by a measurement of embankments the engineer will estimate the actual quanity, and no allowance will be made for shrinkage. If required by the engineer, rock shall be piled for measurement by the contractor.”

In order the better to dispose of the assignments of error, we will first consider what, in the the light of the undisputed facts, is a proper construction of the contract, treating the specifications as a part of the agreement. The uncontroverted testimony shows that for the first month or two after plaintiff began the work the embankments then constructed were actually measured, and that the estimates were made and paid for upon the basis of that measurement. Subsequently Converse directed his subordinates in making the estimates to allow only for the contents of the excavations, and all subsequent estimates were made upon that basis. All succeeding payments were made upon the basis of excavation measurement, but also a deduction was made therefrom of the excess in the previous payments. We think the evidence shows beyond controversy that while the latter estimates were made upon the basis of the cubic contents of the excavations from which the rock was taken, in point of fact the excavations were not measured, and that their contents were arrived at by measuring the embankments themselves, and by deducting from the quantity so’ ascertained thirty-three and one-third per cent. This was shown by the book of the engineer who made the estimates, which was introduced in evidence. The testimony of Converse tends to *261show that the excavations were measured, but in the light of all the evidence it is apparent that he is testifying as to the basis upon which the estimates were made, and not as to the manner in which the contents of the excavations were ascertained. It does not appear that he witnessed the actual measurement of any part of the work. We think, therefore, that it may be assumed as an uncontroverted fact that the embankments and not the excavations were actually measured. Recurring then to the language quoted from the contract, it is to be noted that rock embankment is the only embankment mentioned in the specification of prices. It is possible, therefore, that the provision in the specifications that “the measurement of quantities will usually be made in the cuts or pits from which the material has been taken ” was not intended to apply to the rock embankment.

But conceding for the sake of the argument that it was intended to apply to the entire work, we think if in fact the excavatious were not measured and the embankments were, then that by the next stipulation the company lost its right to claim any reduction from the actual measurement so made. In the absence of some proof showing what is meant by “shrinkage” we are of opinion that the stipulation that “when the quantities are determined by measurement of embankments the engineer will estimate the actual quantity and no allowance will be made for shrinkage,” must be interpreted to mean that actual contents of the banks were to be paid for and that they were not to be reduced to excavation measure by calculation. There appears some reason for such a stipulation. The evidence shows that in blasting solid rock in order to make a cut there was a probability of some loss of material by the fragments being thrown to such distances that they could not be used with profit in constructing the grade. In estimating by embankment this was lost to the contractor, and hence the object may have been to protect him against this loss in the event resort was had to embankment measurement. It is to be remarked also that two different engineers in charge of different divisions of the company's construction at the same time, in making their estimates acted upon this interpretation of the contract until they were directed by the chief engineer to adopt a different measurement. The matter is not free from doubt, but we conclude that the better opinion is that the measurements having been made in the embankments the plaintiff was entitled by the terms both of the contract and of the contract and specifications taken together to payment for the actual cubic yards in the embankments.

The appellant assigns that the court erred in its charge in failing to construe the contract. The construction of the contract was clearly within the province of the court; but we think it follows from what we have said that the proper instruction would have been that if the embankments were actually measured, both under the contract alone and *262the contract and specifications, the plaintiff was entitled to compensation, for the full amount of that measurement. Therefore the failure to construe the contract has not in our opinion operated to the prejudice of appellant and is not a ground for reversing the judgment.

So too upon the question of considering the specifications a part of the contract, we think the instructions of the court though correct were-deficient in not giving all the law applicable to that issue, and that the-charge upon the point asked by appellant, though erroneous taken as a whole, was sufficient to call the attention of the court to the fact that the instruction given was not sufficiently broad. But since we conclude that a proper construction of the agreement, taking the specifications as-a part thereof, would have been that if the measurements of the embankments were actually made as a basis for the estimates, and that the plaintiff was entitled to recover compensation for the entire contents of the embankments so measured, it is obvious that no harm has resulted to appellant from the omission of the court in this particular.

The appellant also assigns as error the refusal to give the following instruction:

“The contract itself provides that the price for excavation includes delivery into banks when the extreme haul does not exceed 2000 feet. Under this provision the plaintiff can not recover the overhaul claimed by him unless such overhaul exceeded 2000 feet, and he can not in any event recover for overhaul any more than the measurement of the excavation. If therefore the evidence fails to show that there was an excess over 2000 feet, or if the evidence does not show affirmatively that there was such excess, then the jury will not allow anything to plaintiff for any overhaul claimed in his petition.”

The provisions of the contract with regard to compensation for what is called “overhaul” seem to us entirely irreconcilable. There is no testimony in regard to the meaning of the words employed which aids us in their construction: We quote the language in reference to this matter again:

“Average overhaul, 2 cents per yard per 100 feet; free haul, 100 feet; overhaul outside right of way to include actual haul, 2 cents per yard per 100 feet; 100 feet of embankment free dirt. * * * The above price for excavation includes delivery into banks where the extreme haul does, not exceed 2000 feet. Where the haul exceeds 100 feet the price for haul on average overhaul, 2 cents per cubic yard per 100 feet. The extreme haul, however, shall not exceed 2000 feet.”

The words “the above price for excavation includes delivery in banks where the extreme overhaul does not exceed 2000 feet” seem to indicate that there was to be no charge for overhaul where the material placed in the embankments was taken from the cuts. On the other hand the language “one hundred feet of embankment free dirt” conveys the idea *263as strongly as thought can be conveyed by implication that all of the embankment haul over one hundred feet was to be paid for. Taking the first four provisions as to the overhaul together they seem to admit of no other construction. Taking the whole language by itself the construction is involved in the gravest doubt. But it appears from the testimony that in making all the estimates the overhaul from excavation to embankment was in every instance allowed and paid for by excavation measurement. This shows that by the construction of the parties as deliberately acted upon by them the defendant was to pay for the hauling from cut to embankment. This interpretation involved many thousand dollars, and it is unreasonable to conclude that it would have been adopted if it had not been distinctly understood that the parties to the contract so intended. Converse, who made the contract, testified as follows:

“This clause in the contract (referring to the clause reading the above price for excavation includes delivery into banks where the extreme haul does not exceed 2000 feet') means that if the haul is over 2000 feet it shall be paid double." He also testified that “if the contract had provided for paying Johnson one dollar and fifty-two and a half cents for all excavations, with two cents for overhaul and nothing for embankment, he Avould have received just the same for his Avork as he does under my construction of his contract." This admits that plaintiff was entitled to recover one dollar and twenty-two and a half cents for the solid rock excavation and thirty cents for rock embankment as called for in the contract, and also for the overhaul from cut to embankment.' It merely claims the construction that the contents of the excavation were to determine the contents of the embankment.

In Chicago v. Sheldon, 9 Wallace, 50, the Supreme Court of the United States announce this rule of construction: “In cases where the language used by the parties to the contract is indefinite or ambiguous and hence of doubtful construction, the practical interpretation by the parties themselves is entitled to great if not controlling influence." They further say: “ The interest of each generally leads him to a construction most favorable to himself, and Avhen the difference has become serious and beyond amicable adjustment it can be settled only by the arbitrament of the law. But in an executory contract, and where its execution necessarily involves a practical construction, if the minds of both parties concur there can be no great danger in the adoption of it by the court as the true one." This is the rule of the Civil Code of Louisiana (D’Aquin v. Barbour, 4 La. Ann., 441) and has been recognized in many cases in courts of common law. See Bish. on Con., sec. 412, and cases there cited.

The language of the contract being doubtful the practical construction deliberately given it by both parties should control its interpretation. It follows that it would have been error to give the charge under consideration.

*264What has already been said is sufficient to dispose of appellant's fourth assignment of error. The fifth complains that the court erred in refusing to charge the jury in effect that if plaintiff received payment for his work upon the estimates furnished by the company's engineer, including the final estimates, without objection or protest, he could not recover. The charge was properly refused. Johnson testified that he did object and protest at the time the payments were made. This is uncontradicted by any person who was present at the payments.

It is true that Converse testified that he did not object until thirty days after the last payment, but he does not pretend that he was present when the transactions occurred, and Johnson testified expressly that he was not. Johnson was practically uncontradicted upon this point, and it follows that in our opinion there was no evidence which would have authorized the charge requested. It Avas not shown that evidence to contradict Johnson, if any ever existed, could not have been obtained, and the failure to produce it should be deemed conclusive upon the question. We will say, however, that Ave think that Johnson's failure to protest after the completion of the work, if he had failed, Avould not have deprived him of the right to demand the full measure of his compensation under the contract. In the absence of a dispute and a compromise agreement the receipt of a part Avithout objection would not discharge a Avhole. It may be that if the company had the right at any time to pay Johnson for the work already done and to annul the contract, and that knowing 'the company claimed that he was to be paid by excavation measurement the plaintiff had recovered payment upon current estimates so made without objection, he Avould be held estopped to claim a different measurement for all subsequent Avorlc. But in order to establish the defense the company should have shown affirmatively that he did not object. This we think it has failed to do. Besides the answer did not set up this defense and to make it available it should have been pleaded.

It Avas beld by this court in the case of this same appellant against Henry & Dilley (G. H. & S. A. Ry. v. Henry, 65 Texas, 658), in deciding upon a contract precisely like the contract in controversy in this suit, that the company's chief engineer did not have the power to finally determine the construction of that agreement. We adhere to that ruling for the reasons given in the opinion in that case.

Appellant also complains of the refusal of the court to give the following charge:

“The fact that the defendant has made a settlement Avith another contractor by which additional pay Avas made to such other contractor does not entitle the plaintiff in this case to demand or receive like additional pay-”

There was testimony drawn out by the defendant upon cross-examination of one of plaintiff’s witnesses that another contractor had been paid *265an additional amount after payment upon the final estimates by way of compromise. The charge could have been correctly given. But since it appears that by a proper construction of the contract the plaintiff was entitled to recover, and that the only question for the jury was as to the amount, the appellant has not been prejudiced by the court’s ruling.

It is also complained that the court erred in refusing to give the jury an instruction to the effect that if the suit was not instituted within two years after the plaintiff was furnished with the final estimates of his work his action was barred by the statute of limitations. This Avas an action “of debt where the indebtedness is evidenced by” and “founded upon a contract in writing,” and Avould not have been barred until four years had elapsed from the time the cause of action accrued. Rev. Stats., art. 3205.

Other assignments raise the same questions already considered and need not be discussed.

There is no error in the proceedings of the court below which calls for a reversal of the judgment, and it is therefore affirmed.

Affirmed.

Delivered June 7, 1889.

midpage