History
  • No items yet
midpage
Gallun v. Seymour
76 Wis. 251
Wis.
1890
Check Treatment
TayloR, J.

It will be seen from the facts stated that the learned circuit judge, in getting at the plaintiffs’ damages, applied the 162-f cords delivered in September, and after the time for the delivery of the last instalment of the barb, upon the deficiency of the delivery in June under the contract. The learned counsel for the defendant contends that the 162$ cords delivered in September should have been applied, first, to extinguish the deficiency of bark delivered in August, and the balance to the deficiency delivered in July. The learned counsel for the plaintiffs contend that all the bark delivered should be applied, first, to make up the 300 cords agreed to be delivered in June, and the 350 cords agreed to be delivered in July, so that the whole deficiency would be in the August delivery, and consequently the damages should be estimated as upon the failure to deliver the 350 cords in August. Under the theory of the application of the 162-f cords of bark as claimed by the *255defendant, and upon the theory, which seems to have been acquiesced in by all the parties and the court, that the plaintiffs were entitled to recover as damages the difference in value of the bark as fixed by the contract and the actual value on the last day of the month in which the deficit occurred, the damages would have been very much less than found by the court. The shortage in July was 118$ cords; in August, 81$ cords. Under defendant’s theory, the 1621-cords delivered in September would have covered all the shortage in July and August, except 37$ cords, and left a shortage of 225 6-8 cords in June; and the damages would have been reduced to 50 cents per cord oft the 225 6-8 cords, and to $1.50 per cord on the 37$ cords, short in July, — in all, the sum of $168.93.

Upon the theory of the plaintiffs’ counsel, by applying all the bark delivered, first to make up the 300 cords to be delivered in June, then to make up the 350 cords in July, and the balance to make up the deficienc}7, as far as it would, in August, there would be a deficiency in August of 263$ cords; and the damages on that deficiency, according to the rule adopted by the parties and the court, would be $1.50 per cord, or $394.68, instead of $331.30, as allowed by the court. The learned counsel for the plaintiffs contend that, in the first place, the contract was an entire contract, and there could be no breach until the 31st of August, 1887. If that contention be correct, then the rule of damages claimed by them would be as they contend. We cannot, however, agree with the learned counsel in this construction of the contract. It seems to us very clear that it was a material part of the contract that 300 cords should be delivered in June, 350 in July, and 350 in August, and that, upon a failure to deliver the 300 cords in June, the contract was broken, and plaintiffs could have maintained an action for any damages they had sustained by a failure to make such delivery; and it is the same as to the failure to deliver in *256July and August. There wore three breaches of the contract shown on the trial. It is a stronger case than the cases of Hill v. Chipman, 59 Wis. 211; Missouri Furnace Co. v. Cochran, 8 Fed. Rep. 463. It is to us a clear case of an agreement to deliver 1,000 cords of bark in three instal-ments,— one to be delivered in June, another in July, and another in August; and a failure to deliver any part of either instalment within the time mentioned for its delivery is a breach of the contract, as much so as if the agreement had been to pay $1,000,— $300 in June, $350 in July, and $350 in August.

The counsel for plaintiffs further contend that, admitting that the failure to deliver any instalment within the time specified would be a breach of the contract, still the bark received in July should be applied to make up the deficiency in June, and the amount received in August should be applied to make up the deficiency in July. We do not think the plaintiffs, in the absence of any agreement to that effect, would have the right to make such application of the bark delivered in the months of July and August. When the month of July commenced, the plaintiffs had a cause of action against the defendant for the breach of the contract to deliver in June, and when the defendant delivered the bark in July the presumption is that he delivered it on his contract to deliver 350 cords in that month, and not that he delivered it to make up any deficiency in June. The rights of the parties as to the June delivery were fixed on the expiration of the month, and the plaintiffs were not bound to receive any more bark to apply on that part of the contract, nor was the .defendant bound to deliver anjr more thereon. We think the just rule is to apply what was delivered in each month upon the contract for that month, in the absence of any agreement to apply it differently. Excluding these views of the construction of the contract and the application of the deliveries of the bark, the judgment is sufficiently favorable to the plaintiffs.

*257The defendant’s appeal presents the question as to the correctness of the learned circuit judge in applying the .162 cords of bark delivered and accepted on the contract after a failure to deliver the whole amount on or before the 31st of August, 1887. Under our construction of the contract, the plaintiffs had three causes of action against the defendant when the bark was delivered in September —first, for a failure to deliver 300 cords in June; second, for a failure to deliver 350 cords in Juty; and, third, for a failure to deliver 350 cords in August. Had these defaults been for a failure to pajT money instalments, there could be no question as to the right of the plaintiffs, in the absence of any directions by the defendant, to apply the payment to the oldest debt, and, if no application had in fact been made, the court would so apply it as a general rule, when all the debts were due and equally secured. Hannan v. Engelmann, 49 Wis. 278; Yellow River Imp. Co. v. Arnold, 46 Wis. 214; Cuer v. Ross, 49 Wis. 652; Robbins v. Lincoln, 12 Wis. 1; Turner v. Pierce, 31 Wis. 342; Jones v. Williams, 39 Wis. 300; Stone v. Talbot, 4 Wis. 442; Sleeper v. Goodwin, 67 Wis. 592; Jenkins v. Gunnison, 50 Wis. 388, and the cases cited by the learned counsel in their briefs. It might be urged that this rule would not be just in all cases where the payment is to be made in property at a fixed price, and this case, to some extent, tends to show that such rule would .not be always a just one. At the time the defendant delivered the bark in September, the plaintiffs, upon the findings of the jury as to the prices, had three causes of action against the defendant,— one for a failure to deliver 225+ cords of bark in June, for which failure the plaintiffs were entitled to recover as damages, fift\? cents per cord; a cause of action for a failure to deliver 118 + cords in July, and 81 + cords in August, and for which failures the plaintiffs were entitled to recover damages at the rate of $1.50 per cord. Afterwards the defendant delivered 162 *258cords on the contract. Suppose it had been shown that when those 162 cords were delivered the bark had advanced so that it was in fact worth $9.50 instead of $8 in June and $9 in July and August, there would be a very grave question whether a court, in making an application of those 162 cords for the parties, would so apply them as to enhance the plaintiffs’ damages $1 per cord, when it could be be applied so as to avoid that result. There is, however, nothing in this record which shows the value of bark at the time these 162 cords were delivered and accepted; and, in the absence of any proof on the subject, we cannot say that there was any injustice in making the application as was done by the court. Had there been no change in the value of bark, or had it lessened in value from the June price, there could be no question as to the propriety of making the application of the 162 cords to the June deficit; and, in the absence of any proof on that subject, there is no presumption that there was any enhancement of its value over the June prices in September.

The learned counsel for the defendant also claims that it was error to allow interest from the commencement of the action on the amount of damages. We think there is no force in this objection. Whereatt v. Ellis, 68 Wis. 69; Van Rensselaer v. Jewett, 2 N. Y. 135; Chapman v. C. & N. W. R. Co. 26 Wis. 295; 1 Suth. Dam. 174.

By the Court.— The judgment of the circuit court is affirmed upon both appeals.

Case Details

Case Name: Gallun v. Seymour
Court Name: Wisconsin Supreme Court
Date Published: Mar 18, 1890
Citation: 76 Wis. 251
Court Abbreviation: Wis.
AI-generated responses must be verified and are not legal advice.
Your Notebook is empty. To add cases, bookmark them from your search, or select Add Cases to extract citations from a PDF or a block of text.