76 Wis. 251 | Wis. | 1890
It will be seen from the facts stated that the learned circuit judge, in getting at the plaintiffs’ damages, applied the 162-f cords delivered in September, and after the time for the delivery of the last instalment of the barb, upon the deficiency of the delivery in June under the contract. The learned counsel for the defendant contends that the 162$ cords delivered in September should have been applied, first, to extinguish the deficiency of bark delivered in August, and the balance to the deficiency delivered in July. The learned counsel for the plaintiffs contend that all the bark delivered should be applied, first, to make up the 300 cords agreed to be delivered in June, and the 350 cords agreed to be delivered in July, so that the whole deficiency would be in the August delivery, and consequently the damages should be estimated as upon the failure to deliver the 350 cords in August. Under the theory of the application of the 162-f cords of bark as claimed by the
Upon the theory of the plaintiffs’ counsel, by applying all the bark delivered, first to make up the 300 cords to be delivered in June, then to make up the 350 cords in July, and the balance to make up the deficienc}7, as far as it would, in August, there would be a deficiency in August of 263$ cords; and the damages on that deficiency, according to the rule adopted by the parties and the court, would be $1.50 per cord, or $394.68, instead of $331.30, as allowed by the court. The learned counsel for the plaintiffs contend that, in the first place, the contract was an entire contract, and there could be no breach until the 31st of August, 1887. If that contention be correct, then the rule of damages claimed by them would be as they contend. We cannot, however, agree with the learned counsel in this construction of the contract. It seems to us very clear that it was a material part of the contract that 300 cords should be delivered in June, 350 in July, and 350 in August, and that, upon a failure to deliver the 300 cords in June, the contract was broken, and plaintiffs could have maintained an action for any damages they had sustained by a failure to make such delivery; and it is the same as to the failure to deliver in
The counsel for plaintiffs further contend that, admitting that the failure to deliver any instalment within the time specified would be a breach of the contract, still the bark received in July should be applied to make up the deficiency in June, and the amount received in August should be applied to make up the deficiency in July. We do not think the plaintiffs, in the absence of any agreement to that effect, would have the right to make such application of the bark delivered in the months of July and August. When the month of July commenced, the plaintiffs had a cause of action against the defendant for the breach of the contract to deliver in June, and when the defendant delivered the bark in July the presumption is that he delivered it on his contract to deliver 350 cords in that month, and not that he delivered it to make up any deficiency in June. The rights of the parties as to the June delivery were fixed on the expiration of the month, and the plaintiffs were not bound to receive any more bark to apply on that part of the contract, nor was the .defendant bound to deliver anjr more thereon. We think the just rule is to apply what was delivered in each month upon the contract for that month, in the absence of any agreement to apply it differently. Excluding these views of the construction of the contract and the application of the deliveries of the bark, the judgment is sufficiently favorable to the plaintiffs.
The learned counsel for the defendant also claims that it was error to allow interest from the commencement of the action on the amount of damages. We think there is no force in this objection. Whereatt v. Ellis, 68 Wis. 69; Van Rensselaer v. Jewett, 2 N. Y. 135; Chapman v. C. & N. W. R. Co. 26 Wis. 295; 1 Suth. Dam. 174.
By the Court.— The judgment of the circuit court is affirmed upon both appeals.