Gallagher v. New York PostGallagher v. New York Post
OPINION OF THE COURT
On June 28, 2004, plaintiff Hugh Gallagher, an ironworker, was assigned to remove a section of metal decking from the
Gallagher and his wife commenced this personal injury action against NYP
1
alleging, among other things, violations of
At his deposition, the assistant project manager at the NYP work site, Jonathan Schreck, testified that “safety harnesses with shock-absorbing lanyards” and “retracting lanyards that we refer to as yo-yos” were available for use at the project site on the date of the accident, but he could not say whether any such safety devices were in the area from which Gallagher fell. Schreck also testified that, at the time of the accident, there was a “standing order,” issued by project manager Mark Piazza to the project foremen, that the ironworkers should “have a harness on and be tied off.” However, he could not recall whether these instructions had been given to the ironworkers.
Schreck, who had taken Gallagher to the hospital after the accident, testified that Gallagher had given him the impression that he had been holding the saw with only one hand and that he had fallеn as he reached to grab the jammed saw with his other hand. He stated that Gallagher had told him that he had not been cleared by his doctor to return to work, following a 2002 аccident and related surgeries to his right hand. Gallagher himself stated at his deposition that he could not complete a grip with his right hand, because the tip of his little finger wаs missing. But he insisted that he had been cleared to return to work by the date of his accident.
Plaintiffs moved for partial summary judgment on their
In furthеr support of their motion, plaintiffs introduced an affidavit signed by Nover, Gallagher’s foreman, who, according to Schreck, would have been the person respоnsible for relaying safety instructions to the ironworkers. Nover stated that Gallagher had not been “provided with a safety harness or lifeline, nor were any stanchions or safety cables in the accident area at the time of the accident.”
Supreme Court denied plaintiffs’ summary judgment motion (
The Appellate Division agreed with Supreme Court’s initial rationale for denying plaintiffs summary judgment, holding that Schreck’s testimony was sufficient to raise issues of fact as to whether Gallagher had been provided with adequate safety devices and instructed to use them, but had declined to do so (
NYP relies on our decision in
Montgomery v Federal Express Corp.
(
This is not such a case. There is no evidence in the record that Gallagher knew where to find the safety devices that NYP argues were readily available or that he was expected to use them. Although Schreck testified that appropriate safety devices were available at the projeсt site on the date of the accident, nowhere in his testimony did Schreck state that Gallagher had been told to use such safety devices. Schreck referred to а “standing order” issued to the project foremen, directing workers to “have a harness on and be tied off,” but could not say whether the order had been conveyed to the workers. Moreover, the affidavit of Gallagher’s foreman, Nover, who was not deposed, does not support NYP’s claim that Gallagher was told about safety devices. Nover stated that Gallagher had not been
Finally, even if Gаllagher’s grip on the saw was not up to full strength as a result of his prior injury, such weakness in his hand would at most have contributed towards his loss of balance, and cannot as a mаtter of law have been the sole proximate cause of his fall from the second floor to the temporary floor.
Accordingly, the order of the Appellate Division, insofar as appealed from, should be reversed, with costs, plaintiffs’ motion for summary judgment as to liability on their
Chief Judge Lippman and Judges Ciparick, Graffeo, Read, Smith and Jones concur.
Order, insofar as appealed from, reversed, etc.
Notes
. Plaintiffs sued NYP as “The New York Post and NYP Holdings, Inc.”
. NYP also commenced a third-рarty action against Gallagher’s employer, Francis A. Lee Co.; that action is not before this Court.
. Supreme Court granted NYP’s cross motion to the extent of dismissing the