66 N.Y.S. 759 | N.Y. App. Div. | 1900
The damages recovered in this action were for the breach of the conditions of a joint and several bond executed by the defendant, Matthew Baird, together with the Sargent Granite Company, to the plaintiff, in the 'penal sum of 16,000. The condition of the bond was that the Sargent Granite Company should well and truly perform the stipulations and agreements in a contract made by it with the plaintiff to furnish all the granite for the erection of the Armory Building on Fourth avenue, in this city, cat, fitted, and ready to set, and deliver the same on a certain dock in New York City. The granite was to be furnished in conformity to and in pursuance of an agreement between the plaintiff and the mayor, etc., of the city of New York, by the armory board of said city, and the plans, drawings, and specifications attached thereto; and such contract, plans, drawings, and specifications were, so far as they, or either of them, referred to the work or material, or. either, therein mentioned, made a part of the contract between the plaintiff and defendant, for the faithful performance of which the bond in question was executed. The contract further provided that the work of furnishing the granite should be commenced within seven days from its execution, and the furnishing and delivery should be completed within eight months from the 1st day of May,
It is conceded that no certificate of the architect showing his approval of the quantity and quality of the material furnished was procured or presented by the defendant when his demand for money was made; but it is contended that plaintiff waived the production of such certificate, for the reason that he had himself procured the certificate; and that he did not put his refusal upon that specific ground, nor himself suggest that such certificate was required, or would be demanded. But there was, concededly, a bona fide dispute as to what amount was due upon the contract, and, if a technical demand was to be relied upon, it should have been made in the method required by the contract, as there was no other way than by the architect’s certificate to ascertain the amount due. The certificate furnished by the plaintiff to the city on receiving payments does not certify with respect to the quantity or value of the granite work as required by the Sargent contract, but embraced the value of the granite cut and set in the building, which, of course, included the cost, of transportation, for work in setting it, and for the labor and expense of the material used. The granite company should have obtained a certificate showing the granite cut and fitted ready to set, and delivered at the company’s expense on the dock at New York; and only after such granite was set in the building was the certificate to be given. At the time of the demand some of the granite was in transportation. After the defendant stopped work on the contract, the plaintiff sought to obtain the granite necessary for the completion of the armory in the open market. The building having been partially constructed of this particular kind and color of granite, it was necessary for the plaintiff to procure other of the same quality and color, and such as would meet the approval of the architect, as required by his contract. He was unable to find the required article in the open market, and could find only two places where the same could be produced, viz. the quarry known as the “Mt. Tuck” and the “Mt. Waldo” quarries, both in the state of Maine. The Mt. Tuck quarry had not been opened, and the Mt. Waldo was so situated as to be inaccessible in winter, it being on an inlet of the main river, which freezes up. Under these conditions, being obliged to secure promptly the granite to finish his contract, the plaintiff leased and opened the Mt. Tuck quarry. In so opening and procuring the granite from this quarry, he necessarily expended, including freight paid on the granite so obtained and on certain cargoes shipped by Sargent & Co., which charges he was obliged to pay to obtain the granite, about the sum of $58,000. It appears that the plaintiff used diligence and care in his efforts to procure the granite in open market, and made all reasonable efforts to diminish the damages. His operations in procuring the granite were made necessary by the failure of the defendant to perform his contract and the special
Upon these facts three questions have been presented and argued in this court, which substantially resolve themselves into—First, that there was no breach of the contract to furnish the granite; second, that the architect’s certificate was not required as a condition precedent to payment upon the contract, or, if so, it was waived; third, that an improper measure of damages was adopted as a basis for the recovery. It is clear from the foregoing statement of facts that not only was there a breach of the contract, but there was a complete abandonment of it. For this act there was no justification. When the demand for money was made, it was not for the sum due upon the contract, but was, in substance, a demand for an advance of money, to be thereafter repaid by the fulfillment of the contract. The plaintiff was not bound to respond to such demand. He in fact did all and more than was required, as he offered to pay all that was then due, or for which a demand could be properly made. By the express provisions of the contract it was a condition precedent to payment that the architect’s certificate in writing should be obtained and presented, approving the quantity and quality of the material furnished, and no payment should be due or become due until compliance was had with the contract in this respect. It is not pretended that the Sargent Company or the defendant made compliance with the contract in this regard, or that any architect’s certificate was obtained at any time. This being a condition precedent to payment, no demand could be made which would place the plaintiff in default, so long as he did nothing to prevent the delivery of the certificate, and did not by act or word waive the provision. Weeks v. O’Brien, 141 N. Y. 199, 36 N. E. 185. No waiver of this clause of the contract is shown by the proof. Indeed, it clearly appeared that the demand for payment was not of the sum due, but for more than the sum which could be due. So that this demand could not possibly have placed the plaintiff in default for more than the amount earned under the contract, whether the architect’s certificate was produced or not; and this sum plaintiff offered to pay. In no view, therefore, does the Sargent Company or the defendant justify the abandonment of the contract.
It is said that the liquidated damages for which the contract made provision furnished the measure of damage. But this clause relates to delay in completion of the contract. Its language so shows: “In case the said party of the first part shall fail to fully and entirely * * * complete within the time hereinbefore limited for such completion and delivery, * * * the said party of the first part shall and will pay to the said party of the second part the sum of fifty dollars for each and every day that the said party of the first part shall be in default.” It is manifest that this clause contemplated a completion of the contract, with damages for delay. There was no completion or attempt to complete, but an utter abandonment, and such clause was not intended to cover such a case,
There are no other questions which require discussion. As we think the judgment below is correct, it should be affirmed, with costs. All . concur." ■