99 P. 965 | Idaho | 1909
This is an appeal from a judgment and order denying a motion for a new trial. The first assignment of error is that the court erred in overruling defendant’s demurrer to the complaint. The complaint alleges that the plaintiff and defendant on November 17, 1903, entered into a contract, which is set out in haec verba; that plaintiff had paid the defendant $550, the first payment provided for by the contract, and the further sum of $100 as shown by an indorsement on the contract, and that he stands ready and willing to make the other payments as provided for in the contract, upon the performance by the defendant of his part of the contract. It is further alleged that defendant failed, neglected and refused to comply with his part of the contract or to convey the water or water right as stipulated in the contract, and prays for $1,500 damages for breach thereof. The contract sued upon is as follows.
“This agreement, made and entered into the 17th day of November, 1903, between C. F. Molden, party of the first part, and Moise Gagnon, party of the second part, Witnesseth:
“That the first party in consideration of $550 (five hundred fifty dollars) to him in hand paid, receipt whereof is hereby acknowledged, and for the further consideration of eleven hundred dollars ($1,100), and interest at 6 per cent per annum to be paid in the manner and at the times hereinafter set forth, the said first party agrees to convey and deliver to the said second party upon the following described real es-state situated in Bingham county, Idaho, to wit: the SW. % of NW. %, NE. % of SW. 14, NW. % of SW.1/4 and SW. % of NE. % Sec. 11, township 3 South, Range 33 East, a water right of one hundred inches of water in either the People’s canal, a corporation, or the American Falls Canal and Power Company’s Canal, a corporation, provided, however, that if said water right is furnished in the said People’s canal it shall be conveyed to said land through said American Falls Canal and Power Co.’s canal and diverted as though it were taken from said last named canal.
“It is understood and agreed by and between the parties that in consideration of the covenants herein the said second*731 party agrees to pay five hundred fifty dollars with interest at 6 per cent per annum on November 17, 1904, and the balance in one year from said last named date with interest at six per cent per annum and should said water right be given in the American Falls Canal and Power Co.’s canal, said deferred payments are to be made as follows: two hundred dollars annually with intérest at 6 per cent per annum until paid.”
Defendant demurred on the ground that the complaint does not state facts sufficient to constitute a cause of action. It is urged by appellant that both the complaint and contract alleged are silent as to the time when the defendant was to perform his part of the contract, and that it necessarily follows that the covenants are mutual, and that before plaintiff can maintain an action on the contract for breach thereof, he must show that he has made all the payments provided for as constituting the purchase price or allege a tender of payment. Plaintiff, on the contrary, insists that by the terms of the contract itself, the defendant is impliedly obligated to deliver and convey the water and water right prior to November 17, 1904, the date of maturity of the first installment ; that an analysis of the contract discloses that the purchase price for the water right described in the contract was $1,650, and that $550 was paid at the time of the execution of the contract, and that the balance of $1,100 was to draw interest at six per cent per annum from the date of the contract. For and in consideration of this sum, the defendant agreed “to convey and deliver to the second party upon the following described real estate .... a water right of one hundred inches of water in either the People’s Canal, a corporation, or the American Falls Canal and Power Co. ’s Canal, a corporation.” Now, by the first part of the contract the defendant agreed, in consideration of the purchase price, to convey and deliver to and upon the plaintiff’s land a water right of one hundred inches. By the subsequent part of the .agreement “it is understood and agreed by and between the parties that in consideration of the covenants herein, the said .second party agrees to pay $550 with interest at six per cent
A great number of errors are assigned as having been committed by the court in the admission and rejection of evidence. We shall not deal with them separately, but will call attention to the more important ones. As above stated, the plaintiff alleged that he made payment of $550 at the time of the execution of the contract. The defendant denied that allegation, and, as a separate defense thereto, alleged that in a transaction involving $550 this consideration passed to one George E. Eggleston as the consideration for an assignment of a desert land entry, but that no part of that consideration was to apply on the contract sued upon. At the trial the defendant asked the plaintiff, on cross-examination, how much of the $550 alleged to have been paid on the contract was for the relinquishment of the land and how much was paid for this water right. The court refused to allow the question to be answered. The defendant when on the witness-stand also offered to testify himself concerning this first payment of $550 and what it was for, and to show that in fact it was not a part of the purchase price for the water right. The court refused to allow him to testify to these facts. This was clearly error. The defendant had an undoubted right to cross-examine the plaintiff concerning this payment, and also to prove by himself or other witnesses that the payment was not in fact made, or, if made, it was on
Exception was also taken by the appellant to the action of the court in permitting plaintiff to introduce evidence as to the extent and value of buildings and improvements he made upon his land in anticipation of receiving water under the contract. Under this ruling of the court, the plaintiff proved the value of the buildings and other improvements made by him on the land. This went to the jury, and was evidently considered by them in making up their verdict as to the amount of damages to be recovered by plaintiff. This was clearly erroneous. It was not the true measure of damages. The proper measure of damages in such case would be the difference between the contract price for the water and water right and its delivery upon the land and the price that it would cost to purchase a like water right and equal number of inches of water delivered upon his land at the time of the breach of the contract. If, however, it should appear that no water right could be purchased either at the time of the breach or at any time thereafter prior to the trial, it would then be necessary to admit evidence of the nature and character of that introduced in this case in order to arrive at the actual damage sustained through and on account of the breach of the contract. In this connection it would be proper and necessary to prove how much the plaintiff had paid on the contract, because if he is not to receive the consideration, he should, among other things, recover the money paid by him on the contract.
On account of the foregoing errors, it will be necessary to grant a new trial. We find no substantial error in the
The judgment is reversed and a new trial granted. Costs awarded in favor of appellant.