202 Mass. 48 | Mass. | 1909
This is an action of contract to recover damages for the breach by the defendant of a written contract between it and the plaintiff according to which as the plaintiff contends he was to excavate rock from and remove a ledge on the defendant’s premises in Beverly, crush the rock to certain specified sizes, and deliver the crushed rock as provided in the contract. The breach complained of was the defendant’s action in refusing to allow the plaintiff to go on with the contract, he being ready and willing to do so. There was a verdict for the plaintiff and the case is here on the defendant’s exceptions.
, The first question relates to the construction of the contract. The defendant contends that according to the true construction of the contract the plaintiff was only to excavate and crush so much of the ledge as should be needed in the construction of new buildings and that when the buildings were. completed it had a right to terminate the contract as it did. It also contends that the changes of grade ordered by the defendant’s engineer came within the terms of the contract and did not constitute a breach of it. The plaintiff contends, on the other hand, that the Contract is for the removal of the entire ledge, and not merely for so much as would have to be removed to furnish the crushed stone required for the construction of certain buildings. He also contends that the change of grade ordered by the defendant’s engineer was not warranted by the contract.
' It is plain we think that the construction contended for by the-plaintiff, and which was the one adopted by the presiding judge,
The only reference to buildings in process of construction in the entire contract is in article “ Ten,” and the reference there is simply for the purpose of providing that if work upon the buildings is suspended by strikes the engineer may order the prosecution of work under the contract to be suspended also. There is nowhere in the contract any provision that the ledge shall be removed only so far as may be necessary to furnish material for the construction of the buildings which the defendant was erecting, and there is no provision that upon completion of such buildings the contract shall or may be terminated. The auditor found that the main purpose of the defendant in having the ledge excavated was to obtain material for new buildings, and that no clause was inserted in the contract limiting the amount to be excavated because the defendant supposed that approxi
The contract provided in article “ One,” as already observed, “ that the excavation and removal shall be to grade thirteen (13) or such other grade as may be specifically designated by the said engineer ” ; and it further provided in article “ Ten ” that “ The engineer in charge may at any time during the progress of the work give written notice to the contractor, as hereinbefore provided, changing the grade to which the ledge or any portion thereof shall be levelled, and the grade so designated shall be in substitution of the grade thirteen (13) mentioned in this instrument.” The defendant, assuming to act under these provisions in the contract, gave notice to the plaintiff on April 2,1907, that thereafter the grades would be eighteen and twenty-three instead of thirteen, and on the plaintiff’s refusal to acquiesce in the change as warranted by the contract virtually put a stop to work under the contract, and prevented the plaintiff from performing the contract. The auditor found that the effect of the change from grade thirteen to grades eighteen and twenty-three was that only a small amount would be excavated from the top of the ledge and that the change was made by direction of an officer of the defendant corporation for the purpose of terminating the plaintiff’s work under the contract. At the trial the defendant’s engineer testified on cross-examination, amongst other things, that “ he did not know of any purpose to which the tops of the ledges levelled off to grade twenty-three and grade eighteen could be put,” and that his object in changing the grade was to stop the plaintiff from further working. The presiding judge instructed the jury that “ The engineer under the terms of the contract . . . was authorized to make any change of grade incidental to the purpose of carrying out the provisions of the
The plaintiff made a sub-contract for a stone crusher with an engine and an engineer to run it, boiler, cars and other equipment required to crush the stone into the sizes called for by his contract with the defendant, and, subject to the defendant’s objection and exception, was allowed to put in, as bearing on the question of damages the price which he was required to pay for what was thus furnished.
The plaintiff was entitled to recover as damages, if he prevailed, the difference, if any, between what it would have cost him to complete the work according to the contract and the sum which he was to receive therefor, and the judge so instructed the jury in accordance with the defendant’s request. Fox v. Harding, 7 Cush. 516. Smith v. Flanders, 129 Mass. 322. Magnolia Metal Co. v. Gale, 189 Mass. 124. The case of Smith v. Flanders, 129 Mass. 322, would seem to be decisive in favor of the admissibility of the evidence.
But we fail to see how the defendant could have been harmed even if the evidence was wrongly admitted. The measure of damages was, as already observed, the difference between the contract price and the cost of completing the work, and the jury were so instructed, and the instruction was repeated more than once. Whether in estimating the profits which the plaintiff would have made if he had been allowed to complete the contract the jury included as part of it the profits which the sub-contractor would be entitled to recover by way of damages from the plaintiff for breach of the sub-contract, or whether in estimating the
We see no error in the rulings and instructions or the refusals to rule and instruct of the presiding judge.
Exceptions overruled.
Stevens, J.