G.R. Osterland Co. v. City of ClevelandG.R. Osterland Co. v. City of Cleveland
Appellant G.R. Osterland Company is appealing the trial court’s grant of appellee city of Cleveland’s motion to dismiss the complaint. For the following reasons, we affirm.
The city of Cleveland hired Anthony Allega Cement Contractors, Inc. as general contractor to renovate runways at Hopkins Airport. The contract and specifications between Allega and the city stated that a sub-base must be installed. Appellant, a subcontractor, installed the sub-base. The city refused to pay for installation of the sub-base. According to the complaint, the city stated that the plans and specifications did not call for installation of the sub-base. Allega refused to pay appellant for installing the sub-base. Appellant put a mechanic’s lien on the airport property for $180,099.08.
In order for Allega to be paid by the city, the mechanic’s lien would have to be released. Allega and appellant entered into a written agreement whereby appellant agreed to release the lien. In return, Allega assigned its right to collect from the city to appellant.
Appellant’s complaint alleged that the city breached its contract with Allega. The complaint also alleged that the city was unjustly enriched. Appellant also requested a declaratory judgment as to whether or not Allega’s assignment of its right to collect was valid and enforceable. Appellant’s causes of action against
The trial court granted
Appellant’s sole assignment of error states:
“The trial court erred in dismissing the G.R. Osterland Company’s breach of contract and unjust enrichment claims against the city of Cleveland for failure to state a claim.”
To dismiss a complaint for failure to state a claim, it must appear beyond a doubt that plaintiff can prove no set of facts entitling him to recovery.
State ex rel. Bush v. Spurlock
(1989),
Appellant asserts for the first time on appeal that it had a contract claim against the city completely in its own capacity and not because of the alleged assignment. Appellant contends that it is in privity with the city with respect to job plans and specifications. The general rule is that, absent an agreement otherwise, there is no privity of contract between a property owner and subcontractor.
Booher Carpet Sales, Inc. v. Erickson
(Oct. 2, 1998), Greene App. No. 98-CA-0007, unreported,
Additionally, the complaint alleges only that the city claimed that a sub-base was not in the plans. The complaint did not state that the city changed the plans and specifications after appellant performed the work. The complaint did not allege that appellant had a contract with the city because of the specifications.
Appellant argues that the city was unjustly enriched because upon learning that Allega assigned the rights to appellant, the city did not pay Allega for the sub-base. According to appellant, the city induced appellant to confer a benefit upon it, by providing plans and then changing them after construction. As stated above, the complaint did not allege that the city changed the plans.
Moreover, the doctrine of unjust enrichment does not apply to a municipal corporation.
Cuyahoga Cty. Hosp. v. Cleveland
(1984),
Accordingly, appellant’s assignment of error is overruled.
The judgment of the trial court is affirmed.
Judgment affirmed.
Notes
. Appellant did not raise any assignments of error as to Allega.