286 Mass. 544 | Mass. | 1934
This is an action of contract to recover from the defendant town compensation for building a bridge. The declaration as amended is in five counts — the first on a written contract dated May 15, 1911, the second, third and fourth each on an account annexed, and the fifth on an express contract alleging that on or about May 15, 1911, the plaintiff entered into a written contract with the defendant; “that immediately thereafter it commenced the construction of the bridge in accordance with the terms of said contract and with specifications and the plans accompanying the same; that thereafter by agreement of the parties said contract was modified in certain respects so as to provide among other things that the plaintiff should proceed with changes in and additions to said work
The written contract of May 15, 1911; including plans, specifications and “proposal sheet” which were a part of it, was in evidence. It provided that the work should be completed on or before October 15, 1911. The contract price fixed thereby was $12,750 with a further provision for payment for “extra work or materials, if any, performed or furnished” in accordance with art. 5 of the contract, “the reasonable cost of the work or materials as determined by the Engineer plus fifteen percentum (15%) of such cost.” Said art. 5 is as follows: “The Engineer may at any time make such changes in the amount of any of the descriptions of work to be done, or in the quality of the material to be used, as the interests of the work or of the Town may in his opinion require. If any such
There was evidence that the payments by the defendant to the plaintiff aggregated $14,578.75. It was agreed “that the bridge was completed and accepted by the town about August 10, 1912,” and “that the final estimate and certificate of the engineer [for which provision was made in the contract] showed there was a balance of
The defendant’s contentions on its bill of exceptions are that the judge erred (a) in refusing to rule that the plaintiff could not recover more than the unexpended balance of the appropriations made by the town for doing the work, (b) in refusing to rule that the plaintiff could not recover payment for work alleged to have been done as extra work unless such work was performed as extra work upon the written order of the engineer, and (c) in refusing to direct a verdict for the defendant on the fifth count of the plaintiff’s declaration. The defendant’s exceptions which are not covered by these contentions have not been argued and are treated as waived.
1. The judge did not err in refusing to rule that the plaintiff could not recover more than the unexpended balance of the appropriations made by the town for doing the work.
There is no contention that the building of the bridge was not within the corporate powers of the town • — • for the purpose of replacing an existing bridge constituting a part of a public way — which, by vote of the town, could be exercised through a committee acting as an agent of the town, and not as a board of public officers, if the laws
The vote of the town on March 7, 1911, did not limit the amount to be expended by the bridge committee to the amount therein referred to. There was no such express restriction of cost to a specified amount as in Nelson v. Georgetown, 190 Mass. 225, and in Vinal v. Nahant, 232 Mass. 412, 420-421. The vote dealt with two distinct matters, (a) raising money by issuing “notes, bonds or script of the Town for $14,000” for building the bridge, and (b) authorizing agents of the town to build such bridge. But it is not implied that the amount of money authorized to be raised in this manner under the first part of the vote is the limit of authorized expenditure under the second part of the vote. The vote in this respect cannot be distin
The vote of the town on March 5, 1912, did not purport to limit the amount which the bridge committee could expend under the previous vote, and the vote of the town on July 30, 1912, to borrow money “for the purpose of completing” the bridge, even if intended to limit expenditures on the bridge, could not affect liabilities already lawfully incurred.
A town cannot escape liability under a contract legally made by failing to make a sufficient appropriation to meet the requirements thereof. And no statute in force during
The defendant, however, relies on R. L. c. 27, § 1, in force during 1911 and 1912, providing that “Cities and towns shall not incur debts, except in the manner of voting and within the limitations as to amount and time of payment prescribed in this chapter,” as limiting the authority of the bridge committee to incur debts for the construction of the bridge to amounts appropriated therefor. We need not consider whether the statute can be so interpreted with respect to debts to which it is applicable, for it does not apply to the liability of the defendant to the plaintiff under the contract. R. L. c. 27, § 20, provides that “The restrictions of the preceding sections shall not exempt a city or town from its liability to pay debts contracted for purposes for which it may lawfully expend money.” And it was said in Smith v. Dedham, 144 Mass. 177, 179, that “although the statute was prohibitory with reference to the borrowing of money and the contracting of debts, it was not intended to interfere with the limited corporate powers and duties of cities and towns. . . . They are authorized to make contracts necessary and convenient for the exercise of their corporate powers, without bringing themselves within the limitation of this statute.” See also Agawam National Bank v. South Hadley, 128 Mass. 503, 505. Building the bridge was a purpose for which the town
2. The judge did not err in refusing to rule that the plaintiff could not recover payment for work alleged to have been done as extra work, unless such work was performed as extra work upon the written order of the engineer.
The provisions of art. 5 of the written contract with regard to extra work preclude recovery by ° the plaintiff for extra work not performed upon the written order of the engineer, unless the contract in this respect was modified by the parties. It could have been found, however, that the written contract was so modified by an oral agreement. Such a modification ordinarily can be made by an oral agreement (Bartlett v. Stanchfield, 148 Mass. 394, Zarthar v. Saliba, 282 Mass. 558, 560, and cases cited), and this is true where one of the parties to the written contract is a town, if the town acts by a duly authorized agent. McGovern v. Salem, 214 Mass. 358, 362-363. Here there was evidence warranting a finding that the bridge committee gave the plaintiff oral instructions to make changes in the work described in the plans and specifications without written orders of the engineer, as required by art. 5 of the written contract, and promised that the town would pay the additional cost of such work, and a finding that oral orders were given by the engineer and carried out by
The bridge committee was authorized by the town to modify the written contract by an oral agreement to the extent at least of substituting oral for written orders for changes in the work. Even where a committee is required to make a single contract for the whole work according to certain plans and specifications, the committee has “authority to add to or to change the specifications in order to remedy defects in them, and to improve them in minor details, within reasonable limits.” Shea v. Milford, 145 Mass. 528, 531. See Morse v. Boston, 253 Mass. 247, 253. Here the authority of the bridge committee was not limited to contracting for building the bridge either by a single contract for the whole work or by several contracts. This committee was authorized to build the bridge and impliedly to make any necessary contracts for that purpose. Its power to contract, therefore, was not exhausted when it made a contract, or contracts, for the whole work. Compare Friend v. Gilbert, 108 Mass. 408, 411. In this respect the case is distinguishable from Keyes v. Westford, 17 Pick. 273, and from Boston Electric Co. v. Cambridge, 163 Mass. 64. There is nothing in the vote of the town authorizing the committee to build the bridge which raises an implication that the power of such committee did not extend to modifications of the contract which were reasonably adapted to the exercise of the powers conferred by the town on the committee. “As a broad proposition, the power of a municipality to modify a public improvement contract is lodged in the principal or officer authorized to make the contract. . . . Such modifications, it is safe to assume, may be lawfully made when required by an exigency to meet a situation in the nature and progress of the work, that was neither understood nor contemplated when the contract was made.” Atlantic City v. Warren Bros. Co. 226 Fed. Rep. 372, 382. It cannot be said as matter of
3. The judge did not err in refusing to direct a verdict for the defendant on the fifth count of the plaintiff’s declaration.
The defendant’s contention is, in substance, that, though the plaintiff on proper allegations could recover the sum of $2,976.61, it cannot recover any amount on the fifth count of the declaration, for the reason that the evidence does not support the allegations of that count with respect to a modification of the written contract, and that, consequently, there is a variance between the allegations and the proof. This contention is disposed of by the preceding consideration of the other contentions of the defendant. It could not have been ruled that the evidence did not warrant a verdict for the plaintiff on the fifth count of the declaration.
It follows that the defendant’s exceptions must be overruled. Since the plaintiff states that if the defendant’s exceptions are overruled it does not insist upon its own exceptions, those exceptions are overruled.
So ordered.